← Back
City university
1930 SEDGWICK AVENUE
💬 Discuss this project
1930Year Built
4Stories
W5Building Class
R5Zoning
631,237 sfGross Floor Area
1Units
LL97 CoveredRent Stabilized87 Open Violations 71 unresolved · 16 paperwork only ▸FISP: No Report Filed
City university · 1,347,500 sf lot · 0.47 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction47p · 3 filings · 20 docs
Floor 2Under Construction7p · 1 filing · 20 docs
Floor 1Under Construction64p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CUNY1809/12/2026
CUNY DEPARTMENT OF DESIGN CONS AND MGMT103/22/2026
DORMITORY AUTHORITY STATE OF NY203/21/2026
CUNY DEPT OF DESIGN CONSTRUCT1103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BAZINI ENGINEERING P C2403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DYNAMIC US, INCGeneral Contractor1907/08/2026
DYNAMIC CONTRACTING CORPPlumbing607/08/2026
REDOSA ENERGY GROUP INCGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BAZINI ENGINEERING, P.C.1808210/10/2025
TECTONIC ENGINEERING CONS1061107/23/2024
Building Lifecycle
All (161)Filed (16)Permit Issued (26)Violation (60)Inspection (15)Objection (14)Special Inspection (30)
08/10/2026
Filed — Alteration
FILING TO IMPLEMENT AN UPGRADE TO THE BUILDING MANAGEMENT SYS (BMS). THE BMS UPGRADE INCLUDES THE INSTALLATION OF NEW CONTROLLERS, ACTUATORS AND CONTROL DEVICES AND UPDATED SEQUENCES OF OPERATIONS FOR ALL MAJOR AND MINOR EQUIPMENT TYPES IN THE FACILITY.
X01436321-I1
07/24/2026
Special inspection requirement — Final
07/24/2026
Special inspection requirement — Shutoff dampers
07/24/2026
Special inspection requirement — Maintenance information
07/24/2026
Special inspection requirement — Ventilation and air distribution system
07/24/2026
Special inspection requirement — HVAC-R and service water heating system controls
07/24/2026
Special inspection requirement — Energy Code Compliance Inspections
07/24/2026
Special inspection requirement — High-Pressure Steam Piping (Welding)
07/24/2026
Special inspection requirement — High Temperature Hot Water Piping (Welding)
07/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/24/2026
Special inspection requirement — Mechanical Systems
06/18/2026
Filed — Alteration
FILING FOR INSTALLATION OF NEW HOT WATER FLOW METER AS PER PLANS. WORK INCLUDES PROVIDING A BTU METER TO MEASURE SUPPLY AND RETURN TEMPERATURE & TO RE-INSTALLED ALL DISTURBED PIPING, ASSOCIATED SUPPORT AND RE-INSULATE DISTURBED PIPING AS PER SPECIFICATION
X01251108-I1
06/09/2026
Special inspection requirement — Metering
03/05/2026
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
02/18/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/17/2026
Inspection — Fail-Final Boiler Equipment Inspection
Fail
View inspection ↗
02/13/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/10/2026
Permit issued — General Construction
X00932003-S5-GC
01/26/2026
Inspection — Fail-Final Boiler Equipment Inspection
Fail
View inspection ↗
01/21/2026
Permit issued — Mechanical Systems
X00932003-S3-MS
12/29/2025
Permit issued — Plumbing
X00932003-S1-PL
12/01/2025
Permit issued — Mechanical Systems
X01279647-I1-MS
11/26/2025
Permit issued — Boiler Equipment
X01279647-S1-BE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/10/2025
Filed — Alteration
REFILING OF DOB APPLICATION No. 220113847 FOR ONE (1) REPLACEMENT EMERGENCY GENERATOR AND FUEL OIL STORAGE BELLY TANK AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01279647-S1
10/10/2025
Filed — Alteration
REFILING OF DOB APPLICATION No. 220113847 FOR ONE (1) REPLACEMENT EMERGENCY GENERATOR AND FUEL OIL STORAGE BELLY TANK AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01279647-I1
10/08/2025
Permit issued — General Construction
X00948663-I1-GC
09/05/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/04/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/29/2025
Special inspection requirement — Emergency and Standby Power Systems (Generator)
Joseph Bazini
08/29/2025
Special inspection requirement — Mechanical Systems
Joseph Bazini
08/29/2025
Special inspection requirement — Final
Joseph Bazini
08/04/2025
Permit issued — Structural
X00932003-S4-ST
07/03/2025
Special inspection requirement — Final
07/03/2025
Special inspection requirement — Mechanical Systems
05/21/2025
Permit issued — Plumbing
X00892428-I1-PL
05/15/2025
Permit issued — Boiler Equipment
X00932003-I1-BE
03/12/2025
Permit issued — General Construction
X00932003-S5-GC
03/05/2025
Permit issued — Boiler Equipment
X00932003-I1-BE
03/04/2025
Permit issued — Support of Excavation
X00932003-S7-SE
02/19/2025
Permit issued — Mechanical Systems
X00932003-S3-MS
01/24/2025
Permit issued — Plumbing
X00932003-S1-PL
11/07/2024
Permit issued — General Construction
X00948663-I1-GC
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/03/2024
Permit issued — Structural
X00932003-S4-ST
08/26/2024
Permit issued — Support of Excavation
X00932003-S7-SE
08/07/2024
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
07/30/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/29/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/24/2024
Special inspection requirement — High-Pressure Fuel-Gas Piping (Welding)
GEORGE GHEBRYAL
07/24/2024
Special inspection requirement — Maintenance information
GEORGE GHEBRYAL
Latest 60 of 161 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedDYNAMIC US, INC02/10/2026
DOB NOWMechanical SystemsPermit IssuedDYNAMIC US, INC01/21/2026
DOB NOWPlumbingPermit IssuedDYNAMIC CONTRACTING CORP12/29/2025
DOB NOWMechanical SystemsPermit IssuedDYNAMIC US, INC12/01/2025
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP11/26/2025
DOB NOWGeneral ConstructionPermit IssuedDYNAMIC US, INC10/08/2025
DOB NOWStructuralPermit IssuedDYNAMIC US, INC08/04/2025
DOB NOWPlumbingPermit IssuedDYNAMIC CONTRACTING CORP05/21/2025
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP05/15/2025
DOB NOWGeneral ConstructionPermit IssuedDYNAMIC US, INC03/12/2025
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP03/05/2025
DOB NOWSupport of ExcavationPermit IssuedREDOSA ENERGY GROUP INC03/04/2025
DOB NOWMechanical SystemsPermit IssuedDYNAMIC US, INC02/19/2025
DOB NOWPlumbingPermit IssuedDYNAMIC CONTRACTING CORP01/24/2025
DOB NOWGeneral ConstructionPermit IssuedDYNAMIC US, INC11/07/2024
DOB NOWStructuralPermit IssuedDYNAMIC US, INC09/03/2024
DOB NOWSupport of ExcavationPermit IssuedREDOSA ENERGY GROUP INC08/26/2024
DOB NOWPlumbingPermit IssuedDYNAMIC CONTRACTING CORP06/20/2024
DOB NOWGeneral ConstructionPermit IssuedDYNAMIC US, INC04/11/2024
DOB NOWMechanical SystemsPermit IssuedDYNAMIC US, INC03/21/2024
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP03/04/2024
DOB NOWPlumbingPermit IssuedDYNAMIC CONTRACTING CORP02/22/2024
DOB NOWGeneral ConstructionPermit IssuedDYNAMIC US, INC11/28/2023
DOB NOWMechanical SystemsPermit IssuedDYNAMIC US, INC09/11/2023
DOB NOWMechanical SystemsPermit IssuedDYNAMIC US, INC07/20/2023
DOB NOWPlumbingPermit IssuedDYNAMIC CONTRACTING CORP07/20/2023
BISOTISSUEDAKS INTERNATIONAL INC03/27/2024
BISOTISSUEDAKS INTERNATIONAL INC03/27/2024
BISOTISSUEDAKS INTERNATIONAL INC04/14/2023
BISOTISSUEDAKS INTERNATIONAL INC04/14/2023
BISOTISSUEDAKS INTERNATIONAL INC05/11/2022
BISOTISSUEDAKS INTERNATIONAL INC05/11/2022
BISOTISSUEDAKS INTERNATIONAL INC06/04/2021
BISOTISSUEDAKS INTERNATIONAL INC06/04/2021
BISOTISSUEDAKS INTERNATIONAL INC02/19/2021
BISOTISSUEDAKS INTERNATIONAL INC02/19/2021
BISOTISSUEDAKS INTERNATIONAL INC01/17/2020
BISFSISSUEDDOUGLAS SIMMONS06/18/2019
BISFSISSUEDDOUGLAS SIMMONS08/29/2018
BISMHISSUEDSTALCO CONSTRUCTION INC06/23/2016
+ 25 more permits on file
1 project · most recent 10/10/2025
Generators
FiledStatusContractorScopeMake / Model / Capacity
10/10/2025Permit IssuedDYNAMIC US, INCGenerators
Generators
Caterpillar DE650SE0 600 kW · Generator ×1
2 projects · most recent 07/23/2024
Gas Water/Sanitary
FiledStatusContractorScope
07/23/2024Permit IssuedDYNAMIC CONTRACTING CORPGas, Water/Sanitary
07/25/2023Permit IssuedDYNAMIC CONTRACTING CORPGas
4 projects · most recent 03/13/2025
General Wiring
FiledStatusContractorScope
03/13/2025Permit IssuedWELSBACH ELECTRIC CORP.General Wiring
11/26/2024Permit IssuedPOLARIS ELEC'L CONST CORPGeneral Wiring
06/01/2023Permit IssuedDYNAMIC ELEC. SYSTEM INC—
12/01/2022Permit IssuedARK SYSTEMS ELEC. CORP—
▾Field Inspections (DOB CAP) — 15
DateTypeResultReport
03/05/2026Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
02/18/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/17/2026Fail-Final Boiler Equipment InspectionFailView ↗
02/13/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/26/2026Fail-Final Boiler Equipment InspectionFailView ↗
09/05/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/04/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/07/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
07/30/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/29/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/16/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/07/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
05/23/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
09/07/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/05/2023Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 58
DateRequirementInspectorRole
07/24/2026Final—progress
07/24/2026Shutoff dampers—energy_progress
07/24/2026Maintenance information—energy_progress
07/24/2026Ventilation and air distribution system—energy_progress
07/24/2026HVAC-R and service water heating system controls—energy_progress
07/24/2026Energy Code Compliance Inspections—progress
07/24/2026High-Pressure Steam Piping (Welding)—special
07/24/2026High Temperature Hot Water Piping (Welding)—special
07/24/2026Fire-Resistant Penetrations and Joints—special
07/24/2026Mechanical Systems—special
06/09/2026Metering—energy_progress
08/29/2025Emergency and Standby Power Systems (Generator)Joseph Bazinispecial
08/29/2025Mechanical SystemsJoseph Bazinispecial
08/29/2025FinalJoseph Baziniprogress
07/03/2025Final—progress
07/03/2025Mechanical Systems—special
07/24/2024High-Pressure Fuel-Gas Piping (Welding)GEORGE GHEBRYALspecial
07/24/2024Maintenance informationGEORGE GHEBRYALenergy_progress
07/24/2024HVAC-R and service water piping design and insulationGEORGE GHEBRYALenergy_progress
07/24/2024Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
06/11/2024High-Pressure Fuel-Gas Piping (Welding)GEORGE GHEBRYALspecial
06/11/2024Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
06/11/2024Maintenance informationGEORGE GHEBRYALenergy_progress
06/11/2024HVAC-R and service water piping design and insulationGEORGE GHEBRYALenergy_progress
03/26/2024Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
Latest 25 of 58.
▾Documents — 272 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/22/2026X00892422-P2Request digital key ↗
08/22/2026X00892422-I1Request digital key ↗
08/22/2026X00892422-P1Request digital key ↗
Showing 3 of 16 on file for this type
▸Applications & Permits52
▸BISWORK PERMIT APPLICATION30
04/19/2023220682991Open ↗
04/19/2023220682991Open ↗
05/13/2022220682991Open ↗
Showing 3 of 30 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION22
05/01/2025220682991Open ↗
02/04/2025220682991Open ↗
02/03/2025220682991Open ↗
Showing 3 of 22 on file for this type
▸Seals & Professional Certifications71
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION29
07/17/2019220682991Open ↗
07/17/2019220682991Open ↗
07/17/2019220682991Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/22/2026X00892428-I1Open ↗
08/22/2026X00892428-P1Open ↗
08/22/2026X00948663-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
09/23/2026X01279647-I1Open ↗
09/23/2026X00932003-I1Open ↗
09/02/2026X00932003-S5Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/23/2026X01279647-I1Open ↗
09/23/2026X00932003-I1Open ↗
09/02/2026X00932003-S5Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
04/20/2011220113847Open ↗
04/20/2011220113847Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
04/20/2011220113847Open ↗
▸Trade Schedules & Equipment20
▸BISSELF-CERT PLUMBING NOTICE6
10/20/2015220113856Open ↗
10/20/2015220113856Open ↗
12/03/2014220113856Open ↗
Showing 3 of 6 on file for this type
▸BISPLUMBING - SUPPORTING DOCUMENTATION4
10/20/2015220113856Open ↗
10/20/2015220113856Open ↗
10/20/2015220113856Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING4
05/21/2012220113847Open ↗
05/17/2012220113847Open ↗
04/20/2011220113856Open ↗
Showing 3 of 4 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
04/27/2015220232683Open ↗
06/23/2014220232683Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
10/20/2015220113856Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
04/20/2011220113847Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
02/13/2014220356923Open ↗
▸BISSTANDPIPE INSP REPORT : FP-841
10/20/2015220113856Open ↗
▸Environmental & Asbestos22
▸DOB NOWDEP ACP-5: Asbestos Assessment Report12
08/22/2026X00892428-I1Open ↗
08/22/2026X00892428-P1Open ↗
08/22/2026X00948663-I1Open ↗
Showing 3 of 12 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM3
11/02/2017220494631Open ↗
08/01/2011220113856Open ↗
05/31/2011220113847Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/21/2026X00932003-S3Open ↗
08/13/2026X01279647-I1Open ↗
08/13/2026X01279647-S1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
10/31/2019220682991Open ↗
10/03/2012220232683Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)2
08/01/2011220113856Open ↗
06/22/2016220494631Open ↗
▸Energy Compliance16
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS9
09/17/2019220682991Open ↗
07/16/2019220682991Open ↗
11/14/2017220356923Open ↗
Showing 3 of 9 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
05/23/2025220682991Open ↗
11/14/2017220356923Open ↗
11/02/2017220494631Open ↗
▸BISTECHNICAL REPORT: ENERGY2
05/31/2011220113847Open ↗
04/20/2011220113847Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
05/23/2025220682991Open ↗
10/01/2021220682991Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY2
05/23/2025220682991Open ↗
10/01/2021220682991Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
05/31/2011220113847Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
05/31/2011220113847Open ↗
▸Approvals, Objections & Sign-offs33
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter16
08/16/2026X01436321-I1Open ↗
08/13/2026X00932003-S4Open ↗
08/13/2026X00932003-S7Open ↗
Showing 3 of 16 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST8
05/27/2025220682991Open ↗
11/22/2017220356923Open ↗
11/17/2017220494631Open ↗
Showing 3 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
12/21/2018220682991Open ↗
01/07/2016220494631Open ↗
04/27/2015220232683Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
10/03/2012220232683Open ↗
05/18/2011220117111Open ↗
04/20/2011220113847Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership19
▸BISCOST AFFIDAVIT19
05/23/2025220682991Open ↗
05/23/2025220682991Open ↗
12/21/2018220682991Open ↗
Showing 3 of 19 on file for this type
▸Filing & Intake Forms18
▸BISEFILING COVER SHEET11
12/21/2018220682991Open ↗
12/21/2018220682991Open ↗
01/07/2016220494631Open ↗
Showing 3 of 11 on file for this type
▸BISADDITIONAL INFORMATION4
05/27/2025220682991Open ↗
02/12/2018220113847Open ↗
03/12/2015220113847Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
04/07/2021220682991Open ↗
11/14/2017220356923Open ↗
11/02/2017220494631Open ↗
▸Other Documents1
▸BISSupporting Document: Fee Exempt1
05/27/2025220682991Open ↗