| Owner | Filings | Most Recent |
|---|---|---|
| Two Trees KG | 34 | 03/21/2026 |
| 194 Atlantic | 22 | 03/21/2026 |
| Independence Savings Bank | 2 | 03/21/2026 |
| NYC Department of Housing Preservation and Development | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IW Architecture | 4 | 01/06/2023 |
| Lilker Associates Consulting Engineering | 3 | 09/23/2022 |
| Howell Belanger Castelli Architects | 1 | 09/23/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| New York Sign Consultants | 8 | 03/21/2026 |
| Burnham Nationwide | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Mauceri Sign Co | Sign hanger | 4 | 07/08/2026 |
| Apb Consulting & Construction | General Contractor | 2 | 07/08/2026 |
| A + Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Advanced Plumbing Mechanical | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Walter T. Gorman, P.E., P | 268 | 4 | 09/23/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | A + Sprinkler | 12/27/2023 |
| DOB NOW | Sign | Signed-off | Mauceri Sign Co | 01/06/2023 |
| DOB NOW | Sign | Signed-off | Mauceri Sign Co | 01/04/2023 |
| DOB NOW | Sign | Signed-off | Mauceri Sign Co | 01/03/2023 |
| DOB NOW | Sign | Signed-off | Mauceri Sign Co | 01/03/2023 |
| DOB NOW | Sprinklers | Signed-off | A + Sprinkler | 12/14/2022 |
| DOB NOW | Plumbing | Permit Issued | Advanced Plumbing Mechanical | 10/18/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | Apb Consulting Construction | 10/11/2022 |
| DOB NOW | General Construction | Signed-off | Apb Consulting Construction | 10/07/2022 |
| BIS | OT | ISSUED | L.S. Sign Co | 11/17/2015 |
| BIS | PL | ISSUED | Medco Plumbing | 01/27/2012 |
| BIS | — | ISSUED | National Maintenance | 11/19/2010 |
| BIS | — | ISSUED | National Maintenance | 09/28/2010 |
| BIS | — | ISSUED | National Maintenance | 09/28/2010 |
| BIS | EQ | ISSUED | James M. Barb Construction | 09/24/2010 |
| BIS | EQ | ISSUED | James M. Barb Construction | 09/17/2010 |
| BIS | OT | ISSUED | James M. Barb Construction | 08/20/2010 |
| BIS | OT | RE-ISSUED | James M. Barb Construction | 08/20/2010 |
| BIS | MH | ISSUED | James M. Barb Construction | 08/20/2010 |
| BIS | EQ | ISSUED | James M. Barb Construction | 08/18/2010 |
| BIS | PL | ISSUED | Schmelz Brothers | 07/22/2010 |
| BIS | OT | RE-ISSUED | James M. Barb Construction | 06/30/2010 |
| BIS | MH | ISSUED | James M. Barb Construction | 06/30/2010 |
| BIS | — | ISSUED | One Main Construction | 05/20/2009 |
| BIS | — | ISSUED | One Main Construction | 02/19/2009 |
| BIS | EQ | ISSUED | One Main Construction | 02/19/2009 |
| BIS | — | ISSUED | One Main Construction | 05/29/2008 |
| BIS | PL | ISSUED | Medco Plumbing | 05/12/2008 |
| BIS | SP | ISSUED | Medco Plumbing | 05/12/2008 |
| BIS | OT | ISSUED | One Main Construction | 04/02/2008 |
| BIS | EQ | ISSUED | One Main Construction | 04/02/2008 |
| BIS | — | ISSUED | One Main Construction | 03/27/2008 |
| BIS | EQ | ISSUED | One Main Construction | 03/27/2008 |
| BIS | EQ | ISSUED | Skyline Scaffolding | 03/17/2008 |
| BIS | EQ | ISSUED | Colgate Scaffolding | 02/11/2008 |
| BIS | — | ISSUED | One Main Construction | 01/08/2008 |
| BIS | PL | ISSUED | Medco Plumbing | 01/07/2008 |
| BIS | EQ | ISSUED | One Main Construction | 01/04/2008 |
| BIS | PL | ISSUED | Medco Plumbing | 11/05/2007 |
| BIS | OT | ISSUED | One Main Construction | 08/14/2007 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/23/2022 | Signed-off | A + Sprinkler | 88 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/22/2022 | Permit Issued | Live Wire Electric 1 | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/03/2023 | Final | Israel Wertentheil | progress |
| 12/16/2022 | Final | Israel Wertentheil | progress |
| 12/15/2022 | Final | Israel Wertentheil | progress |
| 12/15/2022 | Final | Israel Wertentheil | progress |
| 09/23/2022 | Fire-Resistant Penetrations and Joints | Abbas Family | special |
| 09/23/2022 | Post-installed Anchors | Abbas Family | special |
| 09/23/2022 | Lighting controls | Abbas Family | energy_progress |
| 09/22/2022 | Shutoff dampers | Abbas Family | energy_progress |
| 09/22/2022 | Interior lighting power | Abbas Family | energy_progress |
| 08/12/2022 | Sprayed fire-resistant materials | Abbas Family | special |
| 08/12/2022 | Final | Abbas Family | progress |
| 08/12/2022 | Fire-Resistance Rated Construction | Abbas Family | progress |
| 08/12/2022 | Fire-Resistant Penetrations and Joints | Abbas Family | special |
| 08/11/2022 | HVAC-R and service water piping design and insulation | Abbas Family | energy_progress |
| 08/11/2022 | HVAC-R and service water heating system controls | Abbas Family | energy_progress |
| 08/11/2022 | Maintenance information | Abbas Family | energy_progress |
| 08/11/2022 | HVAC-R and service water heating equipment | Abbas Family | energy_progress |
| 08/11/2022 | Post-installed Anchors | Abbas Family | special |
| 08/11/2022 | Fire-Resistant Penetrations and Joints | Abbas Family | special |
| 08/11/2022 | Electrical motors and elevators | Abbas Family | energy_progress |
| 08/09/2022 | Final | Abbas Family | progress |
| 08/09/2022 | Mechanical Systems | Abbas Family | special |
| 08/09/2022 | Sprinkler Systems | Abbas Family | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Barnes & Noble | Retail | Cellar, Floor 1, Roof | Project B00790208 Project B00790230 Project B00790241 Project B00790278 |