| Firm | Filings | Most Recent |
|---|---|---|
| CNS Inspection Services | 2 | 03/05/2022 |
| Arnold Montag Architect AM/PM Desi | 2 | 11/22/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| AM PM Design Consulting P | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Upper Restoration | specialty_contractor | 3 | 03/21/2026 |
| Emerson Brothers | General Contractor | 1 | 07/08/2026 |
| Kevin J Hogan Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Afm Inspections & Engineering | 4675 | 2 | 11/22/2021 |
| Arnold Montag Architect | 4599 | 2 | 11/22/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Kevin J Hogan Plumbing & Heating | 03/18/2022 |
| DOB NOW | General Construction | Signed-off | Emerson Brothers | 02/04/2022 |
| DOB NOW | General Construction | Signed-off | Upper Restoration | 04/27/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2021 | Permit Issued | MSQ Electric Corp Dba Mister | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/02/2022 | Final | FRANK VILLANO | progress |
| 11/24/2021 | Fire-Resistant Penetrations and Joints | Arnold Montag | special |
| 11/24/2021 | Structural Stability – Alterations of existing buildings | Anthony Marmo | special |
| 11/24/2021 | Final | Arnold Montag | progress |
| 11/24/2021 | Energy Code Compliance Inspections | Arnold Montag | progress |
| 11/24/2021 | Fire-Resistance Rated Construction | Arnold Montag | progress |
| 11/24/2021 | Structural Wood Frame | Arnold Montag | progress |
| 11/24/2021 | Ventilation and air distribution system | Arnold Montag | energy_progress |
| 11/24/2021 | Insulation placement and R values | Arnold Montag | energy_progress |
| 11/24/2021 | Mechanical Systems | Arnold Montag | special |
| 11/02/2021 | Mechanical Systems | Arnold Montag | special |
| 11/02/2021 | Structural Stability – Alterations of existing buildings | Anthony Marmo | special |
| 11/02/2021 | Energy Code Compliance Inspections | Arnold Montag | progress |
| 11/02/2021 | Final | Arnold Montag | progress |
| 11/02/2021 | Fire-Resistance Rated Construction | Arnold Montag | progress |
| 11/02/2021 | Structural Wood Frame | Arnold Montag | progress |
| 11/02/2021 | Ventilation and air distribution system | Arnold Montag | energy_progress |
| 11/02/2021 | Insulation placement and R values | Arnold Montag | energy_progress |
| 11/02/2021 | Fire-Resistant Penetrations and Joints | Arnold Montag | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Filco Carting | Industrial / Warehouse | Floor 1 | Project B00673076 |