| Owner | Filings | Most Recent |
|---|---|---|
| MS Investments 3 | 5 | 03/22/2026 |
| 1952 Anthony Ave | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/08/2023 | $4.0M | — | ANTHONY RESIDENTS LLC → 1952 ANTHONY AVE MBSD LLC | — not available |
| 06/22/2023 | $1.4M | — | ANTHONY BRONX LLC → ANTHONY RESIDENTS LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| Nikolai Katz Architect | 5 | 07/16/2025 |
| Vasilios Artemiou PE | 5 | 12/20/2024 |
| FL&M Engineering Design & Inspection | 1 | 09/13/2024 |
| Elevated Engineering NYC | 6 | 08/20/2024 |
| CNS Inspection Services | 2 | 02/12/2024 |
| Badaly Architects | 1 | 01/22/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Geiger E A Group | 2 | 03/21/2026 |
| Advanced Builders Services | 13 | 03/21/2026 |
| Express Filing | 10 | 03/21/2026 |
| Badaly Architects | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Blue Shine Builders | General Contractor | 15 | 07/08/2026 |
| GWT Enterprises | Scaffold | 6 | 03/21/2026 |
| Owners GC NY | General Contractor | 3 | 03/21/2026 |
| Nikolai Katz Architect | General Contractor | 2 | 03/22/2026 |
| M.R. Electrical Service | Electrical | 2 | 03/22/2026 |
| Blue Shine Builders | Scaffold | 2 | 07/08/2026 |
| M R Electrical Service | General Contractor | 2 | 03/22/2026 |
| Prime Piping & Heating | Fire Protection | 1 | 07/08/2026 |
| Intelogic Electric | General Contractor | 1 | 03/22/2026 |
| Prime Piping & Heating | Plumbing | 1 | 07/08/2026 |
| Intelogic Electric | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF Services | 5616 | 15 | 07/16/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | Blue Shine Builders | 11/20/2024 |
| DOB NOW | Sprinklers | Signed-off | Amb Mechanical | 09/17/2024 |
| DOB NOW | Plumbing | Signed-off | Prime Piping & Heating | 09/17/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | GWT Enterprises | 09/16/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | GWT Enterprises | 09/16/2024 |
| DOB NOW | Support of Excavation | Signed-off | Blue Shine Builders | 08/05/2024 |
| DOB NOW | Foundation | Signed-off | Blue Shine Builders | 08/01/2024 |
| DOB NOW | General Construction | Permit Issued | Blue Shine Builders | 07/24/2024 |
| DOB NOW | Structural | Signed-off | Blue Shine Builders | 07/24/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Blue Shine Builders | 07/23/2024 |
| DOB NOW | Curb Cut | Signed-off | Blue Shine Builders | 07/22/2024 |
| DOB NOW | Construction Fence | Signed-off | Blue Shine Builders | 11/21/2023 |
| DOB NOW | Earth Work | Signed-off | Owners GC NY | 06/15/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/16/2025 | Signed-off | Blue Shine Builders | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2025 | Signed-off | Prime Piping & Heating | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2025 | Signed-off | Prime Piping & Heating | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2025 | Complete | M.R. Electrical Service | General Wiring |
| 09/18/2024 | Complete | Solas Electrical | — |
| 09/10/2024 | Complete | Intelogic Electric | General Wiring |
| 07/31/2024 | Complete | Hivolts Electrical | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2025 | Signed-off | Blue Shine Builders | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2025 | Signed-off | Blue Shine Builders | Fence |
| 01/22/2019 | — | — | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/18/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 02/03/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 01/31/2025 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 01/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/29/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/18/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 12/27/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 12/27/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 11/15/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/25/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 08/06/2025 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 08/06/2025 | Air barrier continuity plan testing | FAHAD FATEH | energy_progress |
| 08/06/2025 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 08/06/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 08/06/2025 | Vestibules | FAHAD FATEH | energy_progress |
| 08/06/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 08/06/2025 | Metering | FAHAD FATEH | energy_progress |
| 08/06/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 08/06/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 08/06/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 08/06/2025 | Lighting controls | FAHAD FATEH | energy_progress |
| 08/06/2025 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 08/06/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 08/06/2025 | Alternative Materials - OTCR Buildings Bulletin Number | FAHAD FATEH | special |
| 08/06/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 08/06/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 08/06/2025 | Metering | FAHAD FATEH | energy_progress |
| 08/06/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 08/06/2025 | Air barrier continuity plan testing | FAHAD FATEH | energy_progress |
| 08/06/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 08/06/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 08/06/2025 | Air barrier — testing | FAHAD FATEH | energy_progress |
| 08/06/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 08/06/2025 | Vestibules | FAHAD FATEH | energy_progress |