| Owner | Filings | Most Recent |
|---|---|---|
| DEVELOPING NY STATE | 64 | 07/08/2026 |
| ASTORIA 2 | 4 | 03/22/2026 |
| DEVLOPING NY STATE LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 8 | 06/17/2026 |
| APPLIED HVAC ENGINEERING, PLLC | 2 | 04/28/2025 |
| CHAN ASCHER ARCHITECTURE PLLC | 1 | 02/20/2025 |
| A&D ENGINEERING, PLLC | 7 | 03/19/2024 |
| TITAN ENGINEERS PC | 6 | 10/17/2023 |
| FNA ENGINEERING SERVICES PC | 2 | 10/13/2023 |
| KZ ENGINEERING, P.C | 7 | 05/10/2023 |
| REVAP CONSULTING ENGINEERS LLC | 2 | 01/25/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SYNERGY BUILDING CONSULTANTS | 7 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 50 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DEVELOPING NY STATE LLC | General Contractor | 25 | 07/08/2026 |
| COLGATE ENTERPRISE CORP | General Contractor | 9 | 07/08/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 6 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 3 | 07/08/2026 |
| SAMUEL PALACE | Electrical | 3 | 03/21/2026 |
| PLBG P & H INC | Plumbing | 3 | 07/08/2026 |
| M.R. ELEC'L SERVICE LLC | Electrical | 1 | 03/22/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIG APPLE GROUP NY A RMA | 9168 | 16 | 06/17/2026 |
| FNA ENGINEERING SERVICES | 7846 | 11 | 06/17/2026 |
| APPLIED HVAC ENGINEERING, | 7563 | 3 | 04/28/2025 |
| NKM ENGINEERING PLLC | 6244 | 3 | 04/28/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | DEVELOPING NY STATE LLC | 07/17/2025 |
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 04/28/2025 |
| DOB NOW | General Construction | Signed-off | DEVELOPING NY STATE LLC | 03/31/2025 |
| DOB NOW | Sprinklers | Signed-off | PLBG P & H INC | 04/03/2024 |
| DOB NOW | Plumbing | Permit Issued | SAFETY FIRE SPRINKLER CORP | 04/01/2024 |
| DOB NOW | Plumbing | Signed-off | SAFETY FIRE SPRINKLER CORP | 04/01/2024 |
| DOB NOW | General Construction | Permit Issued | DEVELOPING NY STATE LLC | 11/02/2023 |
| DOB NOW | Curb Cut | Signed-off | DEVELOPING NY STATE LLC | 09/26/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | COLGATE ENTERPRISE CORP | 09/11/2023 |
| DOB NOW | Supported Scaffold | Signed-off | COLGATE ENTERPRISE CORP | 09/11/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | COLGATE ENTERPRISE CORP | 09/11/2023 |
| DOB NOW | Standpipe | Signed-off | SAFETY FIRE SPRINKLER CORP | 07/12/2023 |
| DOB NOW | Construction Fence | Signed-off | DEVELOPING NY STATE LLC | 04/04/2023 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 03/03/2023 |
| DOB NOW | Standpipe | Permit Issued | SAFETY FIRE SPRINKLER CORP | 02/13/2023 |
| DOB NOW | Sprinklers | Signed-off | SAFETY FIRE SPRINKLER CORP | 02/13/2023 |
| DOB NOW | Mechanical Systems | Signed-off | DEVELOPING NY STATE LLC | 01/04/2023 |
| DOB NOW | General Construction | Permit Issued | DEVELOPING NY STATE LLC | 11/25/2022 |
| DOB NOW | Sprinklers | Signed-off | PLBG P & H INC | 11/20/2022 |
| DOB NOW | Structural | Signed-off | DEVELOPING NY STATE LLC | 10/25/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | COLGATE ENTERPRISE CORP | 09/20/2022 |
| DOB NOW | Supported Scaffold | Signed-off | COLGATE ENTERPRISE CORP | 09/20/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | COLGATE ENTERPRISE CORP | 09/20/2022 |
| DOB NOW | Curb Cut | Permit Issued | DEVELOPING NY STATE LLC | 09/16/2022 |
| DOB NOW | General Construction | Permit Issued | DEVELOPING NY STATE LLC | 09/13/2022 |
| DOB NOW | Standpipe | Signed-off | SAFETY FIRE SPRINKLER CORP | 08/10/2022 |
| DOB NOW | Support of Excavation | Signed-off | DEVELOPING NY STATE LLC | 07/12/2022 |
| DOB NOW | Foundation | Signed-off | DEVELOPING NY STATE LLC | 07/12/2022 |
| DOB NOW | Construction Fence | Signed-off | DEVELOPING NY STATE LLC | 04/15/2022 |
| DOB NOW | Foundation | Signed-off | DEVELOPING NY STATE LLC | 04/15/2022 |
| DOB NOW | Support of Excavation | Signed-off | DEVELOPING NY STATE LLC | 03/25/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/17/2026 | Permit Issued | DEVELOPING NY STATE LLC | Associated Ducts and Piping, Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems | Heat / Cool Daikin RXTQ36TBVJUA 36,000 BTU · Vrf Outdoor ×172 RXTQ48TBVJUA 48,000 BTU · Vrf Outdoor ×14 RX12AXVJU 10,900 BTU · Condensing Unit ×2 Heating Ventilation Greenheck G-097-VG 240 CFM · Exhaust Fan ×26 G-095-VG 400 BTU · Kitchen Exhaust ×24 G-100-VG 650 CFM · Exhaust Fan ×2 G-180-VG 2,200 CFM · Exhaust Fan ×2 SQ-120-VG 450 CFM · Exhaust Fan ×2 SQ-70-VG 100 CFM · Exhaust Fan ×2 SQ-90-VG 200 CFM · Exhaust Fan ×2 Panasonic FV-05VQ5 50 CFM · Exhaust Fan ×2 Ducts & Piping N/A N/A Ductwork ×7 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Signed-off | SAFETY FIRE SPRINKLER COR | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Signed-off | BRUCHE MECHANICAL NY LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | Permit Issued | DYNAMIC ELEC'L CONTRS INC | General Wiring |
| 05/27/2025 | Permit Issued | DYNAMIC ELEC'L CONTRS INC | General Wiring |
| 05/20/2025 | Permit Issued | DYNAMIC ELEC'L CONTRS INC | General Wiring |
| 11/19/2024 | Permit Issued | EQUAL ELECTRICAL CONT INC | General Wiring |
| 09/19/2023 | Complete | M.R. ELEC'L SERVICE LLC | 1 meters, 1 new_meters |
| 04/28/2023 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 02/07/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Signed-off | BRUCHE MECHANICAL NY LLC | Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/16/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/03/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/04/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 09/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/01/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/16/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/02/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/02/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 03/29/2024 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 03/29/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/27/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/28/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/27/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/20/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/22/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 05/22/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 01/04/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/29/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/29/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/11/2026 | Energy Code Compliance Inspections | Soorjbally Harilall | progress |
| 06/11/2026 | Lighting in dwelling units | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Air barrier - visual inspection | — | energy_progress |
| 06/11/2026 | Maintenance information | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Insulation placement and R values | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Exterior lighting power | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Protection of exposed foundation insulation | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Interior lighting power | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Air barrier — testing | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Metering | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Fenestration and door U-factor and product ratings | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Lighting controls | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Fenestration air leakage | Soorjbally Harilall | energy_progress |
| 06/11/2026 | Preliminary | Soorjbally Harilall | progress |
| 06/11/2026 | Lowest Floor Elevation | Soorjbally Harilall | progress |
| 06/11/2026 | Fire-Resistance Rated Construction | Soorjbally Harilall | progress |
| 06/11/2026 | Wall Panels, Curtain Walls, and Veneers | SOORJBALLY HARILALL | special |
| 06/11/2026 | Subgrade Inspections | Ahmed Abdelmohsen | special |
| 06/11/2026 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 06/11/2026 | Exterior Insulation and Finish Systems (EIFS) | Soorjbally Harilall | special |
| 06/11/2026 | Excavations - Sheeting, Shoring, and Bracing | Ahmed Abdelmohsen | special |
| 06/11/2026 | Concrete - Cast-In-Place | SOORJBALLY HARILALL | special |
| 06/11/2026 | Fenestration areas | Soorjbally Harilall | energy_progress |
| 03/19/2025 | Energy Code Compliance Inspections | Alexandra Herrera | progress |
| 03/17/2025 | Tenant Protection Plan Compliance | NARESH MAHANGU | special |