1991Year Built
2Stories
E1Building Class
M1-4Zoning
67,660 sfGross Floor Area
1Units
LL97 Covered0 Open ViolationsFDNY Report ↗
General warehouse · Owner of record: GENERATION NEXT REALTY, INC. · 75,000 sf lot · 0.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
Floor 1Under Construction64p · 3 filings · 20 docs
MezzanineUnder Construction54p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GENERATION NEXT REALTY, INC.103/22/2026
DAROGA103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
THORNTON TOMASETTI402/26/2026
HALSEY MCCORMACK HELMER INC604/24/2025
GOLDMAN COPELAND ASSOCIATES504/24/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
METROPOLIS GROUP INC2503/21/2026
THORNTON TOMASETTI, INC.203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
COLIN CONSTRUCTION CO.INCGeneral Contractor1309/07/2026
PAR PLUMBING CO., INCPlumbing408/04/2026
SIRINA FIRE PROT CORPFire Protection207/08/2026
COLE, VINCENTElectrical103/21/2026
SUTTON, ALEXElectrical103/21/2026
DAJ EMR LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PSI AGENCY INC.254402/26/2026
SHAHRISH SHUVO ENGINEERIN8524602/26/2026
Building Lifecycle
All (140)Filed (15)Permit Issued (20)Signed Off (1)Violation (23)Inspection (12)Objection (39)Special Inspection (30)
09/08/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/03/2026
Permit issued — General Construction
B01097572-Z1-GC-CX
08/18/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/13/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/13/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/06/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
08/03/2026
Permit issued — Plumbing
B01097572-S6-PL
07/24/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
07/14/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/14/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/08/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/18/2026
Permit issued — Curb Cut
B01097572-S2-CC
06/18/2026
Permit issued — Curb Cut
B01097572-S3-CC
06/18/2026
Permit issued — Mechanical Systems
B01097572-S5-MS
06/18/2026
Permit issued — General Construction
B01097572-S4-GC
06/17/2026
Permit issued — General Construction
B01082112-I1-GC
06/17/2026
Permit issued — Mechanical Systems
B01082112-S1-MS
03/10/2026
Signed off — Alteration
B01355017-I1
03/04/2026
Permit issued — Structural
B01355017-I1-ST
03/04/2026
Permit issued — Plumbing
B01082112-S2-EW-SP
03/04/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/27/2026
Permit issued — Structural
B01082112-S3-ST
02/27/2026
Permit issued — General Construction
B01097572-I1-GC
02/26/2026
Filed — Alteration
B01355017-I1
02/26/2026
Filed — Alteration
HEREWITH FILING MECHANICAL REMOVALS IN CONJUNCTION WITH FUTURE TENANT FIT-OUT PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
B01082112-P1
02/10/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
02/09/2026
Permit issued — Plumbing
B01082112-S2-PL
02/03/2026
Special inspection requirement — Final
MAURICIO ANDRADE
02/03/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
MAURICIO ANDRADE
11/20/2025
Objection resolved — Addressed
11/12/2025
Objection raised — Cost
11/12/2025
Objection resolved — Addressed
10/14/2025
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
09/17/2025
Objection resolved — Addressed
09/12/2025
Objection raised — Other
09/10/2025
Objection resolved — Addressed
09/02/2025
Permit issued — Plumbing
B01097572-S6-PL
07/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
Shahrish Shuvo
07/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Shahrish Shuvo
07/24/2025
Objection raised — Fire_Protection
07/23/2025
Objection resolved — Addressed
07/22/2025
Objection resolved — Addressed
07/22/2025
Objection resolved — Addressed
07/18/2025
Objection raised — Fire_Protection
07/18/2025
Objection raised — Energy
07/17/2025
Objection resolved — Addressed
07/17/2025
Objection resolved — Addressed
07/17/2025
Special inspection requirement — Shutoff dampers
Shahrish Shuvo
07/11/2025
Objection raised — Fire_Protection
07/11/2025
Objection resolved — Addressed
06/26/2025
Filed — Alteration CO
HEREWITH FILING SPRINKLER WORK AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01097572-S8
06/26/2025
Special inspection requirement — Concrete - Cast-In-Place
Shahrish Shuvo
06/14/2025
Violation issued (FDNY_NOV, closed)
05/22/2025
Objection raised — Other
05/22/2025
Objection raised — Other
05/08/2025
Objection raised — Cost
05/01/2025
Objection resolved — Addressed
05/01/2025
Objection resolved — Addressed
05/01/2025
Objection resolved — Addressed
05/01/2025
Objection resolved — Addressed
Latest 60 of 140 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedCOLIN CONSTRUCTION CO.INC09/03/2026
DOB NOWPlumbingPermit IssuedPAR PLUMBING CO., INC08/03/2026
DOB NOWCurb CutPermit IssuedCOLIN CONSTRUCTION CO.INC06/18/2026
DOB NOWCurb CutPermit IssuedCOLIN CONSTRUCTION CO.INC06/18/2026
DOB NOWMechanical SystemsPermit IssuedCOLIN CONSTRUCTION CO.INC06/18/2026
DOB NOWGeneral ConstructionPermit IssuedCOLIN CONSTRUCTION CO.INC06/18/2026
DOB NOWGeneral ConstructionPermit IssuedCOLIN CONSTRUCTION CO.INC06/17/2026
DOB NOWMechanical SystemsPermit IssuedCOLIN CONSTRUCTION CO.INC06/17/2026
DOB NOWStructuralSigned-offDAJ EMR LLC03/04/2026
DOB NOWPlumbingPermit IssuedSIRINA FIRE PROT CORP03/04/2026
DOB NOWStructuralPermit IssuedCOLIN CONSTRUCTION CO.INC02/27/2026
DOB NOWGeneral ConstructionPermit IssuedCOLIN CONSTRUCTION CO.INC02/27/2026
DOB NOWPlumbingPermit IssuedPAR PLUMBING CO., INC02/09/2026
DOB NOWPlumbingPermit IssuedPAR PLUMBING CO., INC09/02/2025
DOB NOWGeneral ConstructionPermit IssuedCOLIN CONSTRUCTION CO.INC04/22/2025
DOB NOWPlumbingPermit IssuedSIRINA FIRE PROT CORP03/12/2025
DOB NOWSprinklersPermit IssuedPAR PLUMBING CO., INC03/11/2025
DOB NOWStructuralPermit IssuedCOLIN CONSTRUCTION CO.INC03/06/2025
DOB NOWMechanical SystemsPermit IssuedCOLIN CONSTRUCTION CO.INC03/06/2025
DOB NOWGeneral ConstructionPermit IssuedCOLIN CONSTRUCTION CO.INC03/05/2025
BISOTISSUEDPRECISION RENEWABLES LLC11/15/2017
BISMHISSUEDMECHANICAL EAST CO.,INC03/17/2005
BISSPISSUEDVIP FIRE SPR.01/22/1992
2 projects · most recent 02/26/2026
Others Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
02/26/2026Permit IssuedCOLIN CONSTRUCTION CO.INCOthers—
06/26/2025Permit IssuedCOLIN CONSTRUCTION CO.INCAir Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Lennox VRB096H4M-3Y 8 tons · Condensing Unit ×3
Heating
Valent VXC-212-FH-20A-0-A2 6,000 CFM · Heat Pump Outdoor ×6
Evapco ×1
Ventilation
Greenheck DC-5-8-13LV 12,800 CFM · Exhaust Fan ×22
USF-66 52,500 CFM · Exhaust Fan ×2
G-160-VG 2,000 CFM · Exhaust Fan ×1
SP-LP0810W 50 CFM · Exhaust Fan ×1
2 projects · most recent 02/26/2026
Sprinkler System
FiledStatusContractorScope
02/26/2026Permit IssuedSIRINA FIRE PROT CORPSprinkler System
06/26/2025——Sprinkler System
2 projects · most recent 02/26/2026
Water/Sanitary
FiledStatusContractorScope
02/26/2026Permit IssuedPAR PLUMBING CO., INCWater/Sanitary
06/26/2025Permit IssuedPAR PLUMBING CO., INCWater/Sanitary
2 projects · most recent 03/25/2025
General Wiring
FiledStatusContractorScope
03/25/2025Permit IssuedPREMIER ELECTRIC, INCGeneral Wiring
03/30/2018CompleteWILLDAN ELECTRICAL OF NY—
2 projects · most recent 02/26/2026
Steel Concrete Masonry
FiledStatusContractorScope
02/26/2026Permit IssuedCOLIN CONSTRUCTION CO.INC2 scope_items
06/26/2025Permit IssuedCOLIN CONSTRUCTION CO.INCSteel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
09/08/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/18/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/13/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/13/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/06/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/24/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
07/14/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/14/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/08/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
03/04/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/10/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/14/2025Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 42
DateRequirementInspectorRole
02/03/2026FinalMAURICIO ANDRADEprogress
02/03/2026Structural Stability – Alterations of existing buildingsMAURICIO ANDRADEspecial
07/29/2025HVAC-R and service water heating equipmentShahrish Shuvoenergy_progress
07/29/2025HVAC-R and service water piping design and insulationShahrish Shuvoenergy_progress
07/17/2025Shutoff dampersShahrish Shuvoenergy_progress
06/26/2025Concrete - Cast-In-PlaceShahrish Shuvospecial
05/01/2025Post-installed AnchorsShahrish Shuvospecial
05/01/2025MasonryShahrish Shuvospecial
05/01/2025Structural Cold-Formed SteelShahrish Shuvospecial
05/01/2025Structural Steel - DetailsShahrish Shuvospecial
05/01/2025Open-web Steel Joists and Joist GirdersShahrish Shuvospecial
05/01/2025Structural Steel - High Strength BoltingShahrish Shuvospecial
05/01/2025Structural Steel - WeldingShahrish Shuvospecial
05/01/2025Sprayed fire-resistant materialsShahrish Shuvospecial
05/01/2025Subgrade InspectionsShahrish Shuvospecial
04/27/2025Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
04/25/2025Fenestration and door U-factor and product ratingsShahrish Shuvoenergy_progress
04/25/2025Fenestration air leakageShahrish Shuvoenergy_progress
04/25/2025Air barrier - visual inspectionShahrish Shuvoenergy_progress
04/22/2025Fire-Resistant Penetrations and JointsShahrish Shuvospecial
04/22/2025Post-installed AnchorsShahrish Shuvospecial
04/09/2025HVAC-R and service water heating system controlsShahrish Shuvoenergy_progress
04/09/2025Fire-Resistant Penetrations and JointsShahrish Shuvospecial
04/09/2025Post-installed AnchorsShahrish Shuvospecial
04/09/2025Duct leakage testing, insulation and designShahrish Shuvoenergy_progress
Latest 25 of 42.
▾Documents — 76 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
08/23/2026B01082112-S1Request digital key ↗
08/23/2026B01082112-P1Request digital key ↗
08/23/2026B01082112-S3Request digital key ↗
Showing 3 of 15 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
10/26/2017340556669Open ↗
▸BISWORK PERMIT APPLICATION1
11/15/2017340556669Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWRestrictive Declaration/Easement 17
08/13/2026B01097572-Z1Open ↗
08/13/2026B01097572-S5Open ↗
08/13/2026B01097572-Z2Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications33
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/23/2026B01082112-S2Open ↗
08/23/2026B01082112-P1Open ↗
08/23/2026B01082112-S3Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/01/2026B01082112-P1Open ↗
09/01/2026B01097572-Z1Open ↗
08/29/2026B01097572-S5Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/01/2026B01082112-P1Open ↗
09/01/2026B01097572-Z1Open ↗
08/29/2026B01097572-S5Open ↗
Showing 3 of 8 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
10/26/2017340556669Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist3
08/13/2026B01097572-Z1Open ↗
08/13/2026B01097572-S4Open ↗
08/13/2026B01097572-I1Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
10/26/2017340556669Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
12/18/2018340556669Open ↗
10/26/2017340556669Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/18/2018340556669Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
11/14/2017340556669Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
01/18/2019340556669Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
12/18/2018340556669Open ↗
10/26/2017340556669Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION1
11/06/2017340556669Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/18/2018340556669Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
12/18/2018340556669Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
12/18/2018340556669Open ↗
11/14/2017340556669Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
11/06/2017340556669Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/26/2017340556669Open ↗
▸Other Documents1
▸DOB NOWProperty Ownership Certification1
08/13/2026B01097572-I1Open ↗