| Owner | Filings | Most Recent |
|---|---|---|
| STEEL TONE CONSTRUCTION | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/15/2025 | $1.8M | — | Private party → Private party | $479/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| YANG ENGINEERING LLC | 6 | 02/09/2026 |
| JIAN ENGINEERING PLLC | 1 | 10/24/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| SD DESIGN STUDIO | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STEEL TONE CONSTRUCTION | General Contractor | 2 | 04/09/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JIAN ENGINEERING PLLC | 7397 | 6 | 02/09/2026 |
| YANG ENGINEERING LLC | 8376 | 1 | 06/18/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | STEEL TONE CONSTRUCTION | 11/26/2025 |
| DOB NOW | Plumbing | Permit Issued | AMERICAN STANDARD P&H CORORP. | 09/05/2025 |
| DOB NOW | General Construction | Permit Issued | STEEL TONE CONSTRUCTION | 08/27/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/09/2026 | Permit Issued | AMERICAN STANDARD P&H COR | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/15/2025 | Complete | A.C. MORGAN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/09/2026 | Permit Issued | STEEL TONE CONSTRUCTION | Steel, Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/09/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/26/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/16/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/06/2026 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 03/06/2026 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 03/06/2026 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 03/06/2026 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 03/06/2026 | Maintenance information | JIAN DENG | energy_progress |
| 03/06/2026 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 02/09/2026 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 02/09/2026 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 02/09/2026 | Maintenance information | JIAN DENG | energy_progress |
| 02/09/2026 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 02/09/2026 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 02/09/2026 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 01/12/2026 | Maintenance information | JIAN DENG | energy_progress |
| 01/12/2026 | Fenestration areas | JIAN DENG | energy_progress |
| 01/12/2026 | Metering | JIAN DENG | energy_progress |
| 01/12/2026 | Permanent certificate | JIAN DENG | energy_progress |
| 01/12/2026 | Concrete - Cast-In-Place | JIAN DENG | special |
| 01/12/2026 | Exterior Insulation and Finish Systems (EIFS) | JIAN DENG | special |
| 01/12/2026 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 01/12/2026 | Structural Stability – Alterations of existing buildings | JIAN DENG | special |
| 01/12/2026 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 01/12/2026 | Fire-Resistance Rated Construction | JIAN DENG | progress |
| 01/12/2026 | Fenestration air leakage | JIAN DENG | energy_progress |
| 01/12/2026 | Fenestration and door U-factor and product ratings | JIAN DENG | energy_progress |
| 01/12/2026 | Air barrier - visual inspection | JIAN DENG | energy_progress |