| Owner | Filings | Most Recent |
|---|---|---|
| EURO TECH DEVELOPERS | 53 | 07/08/2026 |
| MORRIS WALTON OWNERS LLC | 3 | 03/22/2026 |
| GREEN CASTLE & MGMT CORP | 1 | 03/22/2026 |
| SELCA CONSTRUCTION | 2 | 03/22/2026 |
| THE OWNER OF | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BADALY ARCHITECTS | 9 | 01/15/2024 |
| MOHAMMAD AHEAD, PE | 3 | 06/30/2023 |
| FL&M ENGINEERING DESIGN &INSPECTION | 2 | 06/10/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| KC EXPEDITING INC | 3 | 03/21/2026 |
| KC EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SELCA CONSTRUCTION INC | General Contractor | 19 | 07/08/2026 |
| DYNAMIC INSTALLATION CORP. | General Contractor | 6 | 03/21/2026 |
| KODRA CONSTRUCTION CORP | General Contractor | 5 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 4 | 07/08/2026 |
| DYNAMIX SCAFFOLD GROUP LL | General Contractor | 4 | 07/08/2026 |
| P & D MECHANICAL CORP | Fire Protection | 3 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| LLOYD G DRUMMOND PLBG&GEN | Fire Protection | 1 | 07/08/2026 |
| NOBLE MECHANICAL CORP | Plumbing | 1 | 03/22/2026 |
| PIPE SOLUTIONS ADVIS INC | Plumbing | 1 | 07/08/2026 |
| FUSED ELECTRIC CONTNG COR | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CONCRETE SOLUTIONS LAB CO | 5344 | 8 | 01/15/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Standpipe | Signed-off | A M B MECHANICAL INC | 08/15/2024 |
| DOB NOW | Sprinklers | Signed-off | P & D MECHANICAL CORP | 06/21/2024 |
| DOB NOW | Construction Fence | Signed-off | SELCA CONSTRUCTION | 04/19/2024 |
| DOB NOW | Construction Fence | Signed-off | SELCA CONSTRUCTION | 04/08/2024 |
| DOB NOW | Plumbing | Signed-off | P & D MECHANICAL CORP | 09/26/2023 |
| DOB NOW | Plumbing | Signed-off | P & D MECHANICAL CORP | 09/22/2023 |
| DOB NOW | Standpipe | Signed-off | PIPE SOLUTIONS ADVIS INC | 08/22/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | DYNAMIX SCAFFOLD GROUP LL | 06/30/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIX SCAFFOLD GROUP LL | 03/15/2023 |
| DOB NOW | Supported Scaffold | Signed-off | DYNAMIX SCAFFOLD GROUP LL | 03/08/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 10/17/2022 |
| DOB NOW | Construction Fence | Signed-off | SELCA CONSTRUCTION | 09/30/2022 |
| DOB NOW | Plumbing | Signed-off | A M B MECHANICAL INC | 09/08/2022 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 09/06/2022 |
| DOB NOW | Standpipe | Signed-off | PRIME PIPING & HEATING IN | 09/06/2022 |
| DOB NOW | Standpipe | Signed-off | A M B MECHANICAL INC | 08/15/2022 |
| DOB NOW | Standpipe | Signed-off | LLOYD G. DRUMMOND | 06/03/2022 |
| DOB NOW | Construction Fence | Signed-off | KODRA CONSTRUCTION CORP | 04/05/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 10/14/2021 |
| BIS | — | ISSUED | GREEN CASTLE A MGMT CORP | 09/30/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/12/2024 | Complete | FUSED ELECTRIC CONTNG COR | 1 meters, 1 new_meters |
| 06/19/2024 | Complete | FUSED ELECTRIC CONTNG COR | General Wiring |
| 05/30/2023 | Complete | JAM ELECTRICAL CORP | — |
| 10/27/2021 | Complete | HIGH QUALITY ELECTRIC OF | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/06/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/30/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 08/25/2024 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 08/25/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 07/10/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 07/08/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/14/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/12/2024 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 12/21/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/01/2023 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 09/28/2023 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/17/2024 | Sprinkler Systems | MINA HANNA | special |
| 01/17/2024 | HVAC-R and service water piping design and insulation | MINA HANNA | energy_progress |
| 01/17/2024 | Post-installed Anchors | MINA HANNA | special |
| 01/17/2024 | Standpipe Systems | MINA HANNA | special |
| 01/17/2024 | Seismic Isolation Systems | MINA HANNA | special |
| 01/17/2024 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 01/17/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MINA HANNA | special |
| 01/15/2024 | HVAC-R and service water piping design and insulation | MINA HANNA | energy_progress |
| 01/15/2024 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 01/15/2024 | Post-installed Anchors | MINA HANNA | special |
| 01/15/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MINA HANNA | special |
| 01/15/2024 | Seismic Isolation Systems | MINA HANNA | special |
| 01/15/2024 | Sprinkler Systems | MINA HANNA | special |
| 01/15/2024 | Standpipe Systems | MINA HANNA | special |
| 01/10/2024 | Standpipe Systems | MINA HANNA | special |
| 01/10/2024 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 01/10/2024 | Post-installed Anchors | MINA HANNA | special |
| 01/10/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MINA HANNA | special |
| 01/10/2024 | Seismic Isolation Systems | MINA HANNA | special |
| 01/10/2024 | Sprinkler Systems | MINA HANNA | special |
| 01/10/2024 | HVAC-R and service water piping design and insulation | MINA HANNA | energy_progress |
| 10/26/2023 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 10/26/2023 | HVAC-R and service water piping design and insulation | MINA HANNA | energy_progress |
| 10/26/2023 | Standpipe Systems | MINA HANNA | special |
| 10/26/2023 | Sprinkler Systems | MINA HANNA | special |