← Back
Elevator apt, semi-fireproof with stores
The 210 Clarkson Avenue Condominium
218 CLARKSON AVENUE · East Flatbush-Erasmus · BIN 3427328
💬 Discuss this project
2021Year Built
—Stories
D7Building Class
—Zoning
185,926 sfGross Floor Area
167Units
Rent Stabilized2 Open Violations ▸FDNY Report ↗
Elevator apt, semi-fireproof with stores · Owner of record: 210 CLARKSON PROPCO LLC · 27,000 sf lot · 6.89 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Roof1p · 3 filings · 13 docs
Floor 81 filing
Floor 71 filing
Floor 61 filing
Floor 51 filing
Floor 41p · 3 filings
Floor 31p · 3 filings
Floor 21p · 3 filings · 13 docs
Floor 12p · 4 filings · 19 docs
Cellar1p · 1 filing · 13 docs
Site & exterior4 filings · 10 docs
Filed — no permit issued1 filing
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OWNERS REP2607/08/2026
ALLIAH MANAGEMENT1607/08/2026
INTERNATIONAL CONCRETE307/08/2026
NY DEVELOPERS303/22/2026
210 CLARKSON PROPCO LLC203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/13/2019$20.5M—CLARKSON 210 LLC → 210 CLARKSON OWNER LLC— not available
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SYNERGY BUILDING CONSULTANTS103/21/2026
AE DESIGN SOLUTION2403/21/2026
JM ZONING, LLC.2603/21/2026
A&A BUILDING CONSULTANTS INC.1003/21/2026
LOMBARDO BUILDING CONSULTANTS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CORE SCAFFOLD SYSTEMS INC.General Contractor2707/08/2026
NY DEVELOPERS & MANAGEMENTGeneral Contractor2007/08/2026
TRISTATE FIRE SPRINK INCFire Protection607/08/2026
XOLLE DEMO LLCGeneral Contractor507/08/2026
MAMC CONSULTING REPS LLCGeneral Contractor407/08/2026
ELIEZER ROSENBERGElectrical403/21/2026
EP ELECTRIC NY LLC 005507General Contractor303/22/2026
FQE ELECTRIC LLCElectrical303/22/2026
MARQUIS P HGeneral Contractor303/22/2026
P.H. WORKS INCPlumbing207/08/2026
S & J INDUSTRIAL CORPFire Protection207/08/2026
MPI PLUMBING CORPPlumbing207/08/2026
MARQUIS P & H CO., INCPlumbing107/08/2026
A&A BUILDING CONSULTANTSGeneral Contractor107/08/2026
INTERNATIONAL CONCRETE C*General Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ARCALHEK PC3340112/30/2024
AA BUILDING & INSPECTION1519309/05/2024
BIG APPLE GROUP NY A RMA91681003/21/2024
MCNAMARA/SALVIA OF NEW YO4970212/21/2022
LEO Y LEE ASSOCIATES2481212/05/2022
M. INT'L ENGINEERING PLLC3129112/09/2019
Building Lifecycle
All (187)Filed (31)Permit Issued (41)Signed Off (19)Violation (42)Inspection (18)Objection (6)Special Inspection (30)
03/19/2026
Violation issued (FDNY_ORDER, closed)
03/19/2026
Violation issued (FDNY_ORDER, closed)
07/01/2025
Violation issued (ECB, closed)
Elevators
07/01/2025
Violation issued (ECB, closed)
Elevators
04/09/2025
Signed off — Alteration
Propose 15 Plubming fixtures 1 steam table, 1 Floor drain 2 Grease traps and 5 non residential cooking equipment in existing Fresh Food supermarket.
B01004988-S1
03/26/2025
Violation issued (HPD, closed)
A
03/10/2025
Violation issued (HPD, closed)
A
03/10/2025
Violation issued (HPD, closed)
C
03/10/2025
Violation issued (HPD, closed)
C
03/10/2025
Violation issued (HPD, closed)
B
03/10/2025
Violation issued (HPD, closed)
B
03/06/2025
Signed off — Alteration
Propose installation of Commercial cooking hood & exhaust system on first floor
B01161129-I1
02/27/2025
Permit issued — Mechanical Systems
B01161129-I1-GC-CX
12/30/2024
Filed — Alteration
Propose installation of Commercial cooking hood & exhaust system on first floor
B01161129-I1
12/30/2024
Special inspection requirement — Final
RICHARD JIMENEZ
12/30/2024
Special inspection requirement — Mechanical Systems
RAYMOND CALAMARI
12/30/2024
Special inspection requirement — Tenant Protection Plan Compliance
RAYMOND CALAMARI
12/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
RAYMOND CALAMARI
12/02/2024
Violation issued (ECB, closed)
Construction
10/09/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/13/2024
Signed off — Alteration
Propose 15 Plubming fixtures 1 steam table, 1 Floor drain 2 Grease traps and 5 non residential cooking equipment in existing Fresh Food supermarket.
B01004988-I1
09/06/2024
Special inspection requirement — Tenant Protection Plan Compliance
Younes Abouyaala
09/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
09/05/2024
Filed — Alteration
Propose 15 Plubming fixtures 1 steam table, 1 Floor drain 2 Grease traps and 5 non residential cooking equipment in existing Fresh Food supermarket.
B01004988-P1
08/28/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/21/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/21/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/23/2024
Signed off — Alteration
B00286884-I1
05/15/2024
Violation issued (ECB, closed)
Unknown
04/04/2024
Special inspection requirement — Electrical motors
Soorjbally Harilall
04/04/2024
Special inspection requirement — Maintenance information
Soorjbally Harilall
04/04/2024
Special inspection requirement — Electrical energy consumption
Soorjbally Harilall
04/04/2024
Special inspection requirement — Maintenance information
Soorjbally Harilall
04/04/2024
Special inspection requirement — Electrical energy consumption
Soorjbally Harilall
04/04/2024
Special inspection requirement — HVAC insulation and sealing
Soorjbally Harilall
04/04/2024
Special inspection requirement — Final
Soorjbally Harilall
04/04/2024
Special inspection requirement — Final
Soorjbally Harilall
04/04/2024
Special inspection requirement — HVAC insulation and sealing
Soorjbally Harilall
04/04/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
04/04/2024
Special inspection requirement — Mechanical Systems
SOORJBALLY HARILALL
04/04/2024
Special inspection requirement — HVAC and service water heating system controls
Soorjbally Harilall
04/04/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
04/04/2024
Special inspection requirement — Shutoff dampers
Soorjbally Harilall
04/04/2024
Special inspection requirement — HVAC and service water heating system controls
Soorjbally Harilall
04/04/2024
Special inspection requirement — HVAC and service water heating equipment
Soorjbally Harilall
04/04/2024
Special inspection requirement — Mechanical Systems
SOORJBALLY HARILALL
04/04/2024
Special inspection requirement — HVAC and service water heating equipment
Soorjbally Harilall
04/04/2024
Special inspection requirement — Shutoff dampers
Soorjbally Harilall
04/04/2024
Special inspection requirement — Electrical motors
Soorjbally Harilall
03/21/2024
Filed — Alteration
B00286884-P3
03/11/2024
Permit issued — Plumbing
B01004988-S1-PL
03/04/2024
Permit issued — Mechanical Systems
B01004988-I1-MS
02/26/2024
Permit issued — Mechanical Systems
B01004988-I1-GC
02/21/2024
Filed — Alteration
Propose 15 Plubming fixtures 1 steam table, 1 Floor drain 2 Grease traps and 5 non residential cooking equipment in existing Fresh Food supermarket.
B01004988-S1
02/16/2024
Filed — Alteration
Propose 15 Plubming fixtures 1 steam table, 1 Floor drain 2 Grease traps and 5 non residential cooking equipment in existing Fresh Food supermarket.
B01004988-I1
02/16/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
02/16/2024
Special inspection requirement — Tenant Protection Plan Compliance
Younes Abouyaala
02/16/2024
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
02/13/2024
Special inspection requirement — Mechanical Systems
Younes Abouyaala
12/27/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00708824-I1
Latest 60 of 187 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offA&A BUILDING CONSULTANTS02/27/2025
DOB NOWPlumbingSigned-offMARQUIS P & H CO., INC03/11/2024
DOB NOWMechanical SystemsSigned-offMAMC CONSULTING REPS LLC03/04/2024
DOB NOWMechanical SystemsSigned-offMAMC CONSULTING REPS LLC02/26/2024
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC10/16/2023
DOB NOWConstruction FenceSigned-offNY DEVELOPERS & MANAGEMEN08/21/2023
DOB NOWSprinklersSigned-offTRISTATE FIRE SPRINK INC07/28/2023
DOB NOWStandpipeSigned-offTRISTATE FIRE SPRINK INC07/28/2023
DOB NOWPlumbingSigned-offYG SERVICES INC07/14/2023
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC06/27/2023
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC06/26/2023
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC06/26/2023
DOB NOWSprinklersSigned-offS & J INDUSTRIAL CORP05/18/2023
DOB NOWSprinklersSigned-offP.H. WORKS INC05/17/2023
DOB NOWMechanical SystemsSigned-offNY DEVELOPERS & MANAGEMEN04/25/2023
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC03/31/2023
DOB NOWStandpipeSigned-offTRISTATE FIRE SPRINK INC01/03/2023
DOB NOWConstruction FenceSigned-offNY DEVELOPERS & MANAGEMEN12/15/2022
DOB NOWConstruction FenceSigned-offNY DEVELOPERS & MANAGEMEN11/22/2022
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC10/27/2022
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC10/18/2022
DOB NOWProtection and Mechanical MethodsSigned-offINTERNATIONAL CONCRETE C*09/08/2022
DOB NOWStandpipeSigned-offTRISTATE FIRE SPRINK INC07/29/2022
DOB NOWSprinklersSigned-offTRISTATE FIRE SPRINK INC07/29/2022
DOB NOWPlumbingSigned-offYG SERVICES INC07/12/2022
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC07/01/2022
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC06/28/2022
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC06/28/2022
DOB NOWCurb CutSigned-offNY DEVELOPERS & MANAGEMEN05/13/2022
DOB NOWMechanical SystemsSigned-offNY DEVELOPERS & MANAGEMEN05/12/2022
DOB NOWStructuralSigned-offNY DEVELOPERS & MANAGEMEN04/26/2022
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC04/04/2022
DOB NOWStandpipeSigned-offTRISTATE FIRE SPRINK INC01/07/2022
DOB NOWConstruction FenceSigned-offNY DEVELOPERS & MANAGEMEN12/03/2021
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC07/02/2021
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC07/02/2021
DOB NOWConstruction FenceSigned-offXOLLE DEMO LLC06/15/2021
DOB NOWPlumbingSigned-offP.H. WORKS INC09/18/2020
DOB NOWSprinklersSigned-offS & J INDUSTRIAL CORP09/18/2020
DOB NOWConstruction FenceSigned-offXOLLE DEMO LLC03/09/2020
+ 7 more permits on file
11 projects · most recent 11/04/2025
General Wiring
FiledStatusContractorScope
11/04/2025CompleteEP ELECTRIC NY LLCGeneral Wiring
09/24/2024CompleteJP & SON ELECTRIC CORPGeneral Wiring
03/28/2024CompletePOWER DIRECT ELECTRIC INC—
02/20/2024CompleteFQE ELECTRIC LLCGeneral Wiring
01/02/2024CompleteFQE ELECTRIC LLC5 meters, 5 new_meters
06/22/2023CompleteFQE ELECTRIC LLCGeneral Wiring
03/10/2023CompletePOWER DIRECT ELECTRIC INC—
12/15/2022CompleteFQE ELECTRIC LLC1 meters, 1 new_meters
06/25/2022CompleteSOLAS ELECTRICAL CORP—
07/06/2021CompleteV. VASS ELECTRIC CORP—
04/30/2019CompleteT.M.T ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 18
DateTypeResultReport
10/09/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/28/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/21/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/21/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/17/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
08/24/2023Pass-Final SD - Fire PumpPassView ↗
08/24/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
08/14/2023Pass-Final SD - More than 10 Requested FloorsPassView ↗
08/14/2023Pass-Final SP - More than 10 Requested FloorsPassView ↗
08/08/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/08/2023Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
05/04/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
03/21/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
02/01/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
10/21/2022Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
10/18/2022Pass-Final General Construction Non-Directive 14PassView ↗
08/03/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/18/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 81
DateRequirementInspectorRole
12/30/2024Mechanical SystemsRAYMOND CALAMARIspecial
12/30/2024FinalRICHARD JIMENEZprogress
12/30/2024Tenant Protection Plan ComplianceRAYMOND CALAMARIspecial
12/30/2024Fire-Resistant Penetrations and JointsRAYMOND CALAMARIspecial
09/06/2024Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
09/06/2024Tenant Protection Plan ComplianceYounes Abouyaalaspecial
04/04/2024Maintenance informationSoorjbally Harilallenergy_progress
04/04/2024HVAC insulation and sealing Soorjbally Harilallenergy_progress
04/04/2024Shutoff dampersSoorjbally Harilallenergy_progress
04/04/2024HVAC and service water heating system controls Soorjbally Harilallenergy_progress
04/04/2024HVAC and service water heating equipment Soorjbally Harilallenergy_progress
04/04/2024Electrical energy consumptionSoorjbally Harilallenergy_progress
04/04/2024Electrical motorsSoorjbally Harilallenergy_progress
04/04/2024FinalSoorjbally Harilallprogress
04/04/2024Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
04/04/2024Mechanical SystemsSOORJBALLY HARILALLspecial
04/04/2024Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
04/04/2024FinalSoorjbally Harilallprogress
04/04/2024Shutoff dampersSoorjbally Harilallenergy_progress
04/04/2024HVAC and service water heating system controls Soorjbally Harilallenergy_progress
04/04/2024HVAC and service water heating equipment Soorjbally Harilallenergy_progress
04/04/2024Maintenance informationSoorjbally Harilallenergy_progress
04/04/2024Electrical energy consumptionSoorjbally Harilallenergy_progress
04/04/2024Electrical motorsSoorjbally Harilallenergy_progress
04/04/2024HVAC insulation and sealing Soorjbally Harilallenergy_progress
Latest 25 of 81.
▾Documents — 271 on file (BIS + DOB NOW)
▸Plans & Drawings36
▸DOB NOWPlans/Sketch18
09/01/2026B00551016-P1Request digital key ↗
09/01/2026B00551016-I1Request digital key ↗
09/01/2026B00551016-P2Request digital key ↗
Showing 3 of 18 on file for this type
▸DOB NOWPlans/Sketch - Plumbing4
09/02/2026B00267424-I1Request digital key ↗
09/02/2026B00287050-P1Request digital key ↗
09/02/2026B00287050-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems4
09/02/2026B00286884-I1Request digital key ↗
09/02/2026B00286884-P3Request digital key ↗
09/02/2026B00286884-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Standpipe3
09/02/2026B00287131-I1Request digital key ↗
09/02/2026B00287108-P1Request digital key ↗
09/02/2026B00287108-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler3
09/02/2026B00267424-I1Request digital key ↗
09/02/2026B00287108-P1Request digital key ↗
09/02/2026B00287108-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural2
09/02/2026B00286805-I1Request digital key ↗
08/15/2026B00286805-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Curb Cut1
09/02/2026B00343622-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00252459-I1Request digital key ↗
▸Applications & Permits37
▸BISPLAN / WORK APPROVAL APPLICATION27
05/20/2025322121155Open ↗
10/24/2024321596484Open ↗
09/11/2024321596484Open ↗
Showing 3 of 27 on file for this type
▸BISWORK PERMIT APPLICATION5
10/11/2022321596484Open ↗
09/29/2022321596484Open ↗
08/06/2022321596484Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
01/26/2021340723337Open ↗
06/18/2020321596484Open ↗
06/18/2020321596484Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
05/25/2023321596484Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
01/22/2021340723337Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISZONING DIAGRAM2
02/23/2023321596484Open ↗
06/23/2020321596484Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
06/15/2020321596484Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
06/15/2020321596484Open ↗
▸BISRESTRICTION: RESTRICTIVE DECLARATION1
06/15/2020321596484Open ↗
▸BISVERIFY TAX LOT1
09/10/2024321596484Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
06/15/2020321596484Open ↗
▸Seals & Professional Certifications81
▸DOB NOWDPL-1: Design Professional Seal & Signature33
09/02/2026B00286884-P3Open ↗
09/02/2026B00286884-P2Open ↗
09/02/2026B00286884-P1Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature31
09/01/2026B08008772-I1Open ↗
09/01/2026B00286805-I1Open ↗
09/01/2026B00286805-I1Open ↗
Showing 3 of 31 on file for this type
▸DOB NOWProgress Inspector Seal & Signature12
09/02/2026B00286884-P1Open ↗
09/01/2026B00286805-I1Open ↗
08/28/2026B00286884-P3Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
12/17/2021321596484Open ↗
12/17/2021321596484Open ↗
12/17/2021321596484Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
03/26/2020340723337Open ↗
▸Trade Schedules & Equipment4
▸BISSTANDPIPE WORK PERMIT1
01/15/2022321596484Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
03/03/2025321596484Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
05/09/2025321596484Open ↗
▸DOB NOWFDNY: Letter of No Objection1
08/13/2026B00267424-I1Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST3
08/17/2020340723337Open ↗
08/17/2020340723337Open ↗
06/15/2020321596484Open ↗
▸BISSTREET TREE SIGNOFF2
05/12/2025321596484Open ↗
05/11/2025321596484Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
09/10/2020321596484Open ↗
▸BISSTREET TREE SUPPORTING DOCUMENT1
05/09/2025321596484Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B00267424-I1Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
11/06/2023321596484Open ↗
06/18/2020321596484Open ↗
06/18/2020321596484Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
12/17/2021321596484Open ↗
12/17/2021321596484Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
10/16/2023321596484Open ↗
▸BISFENESTRATION AIR LEAKAGE1
10/16/2023321596484Open ↗
▸BISINTERIOR LIGHTING POWER1
08/24/2023321596484Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
10/16/2023321596484Open ↗
▸BISFENESTRATION AREAS1
10/16/2023321596484Open ↗
▸BISEXTERIOR LIGHTING POWER1
09/06/2023321596484Open ↗
▸BISPRELIMINARY COMMISSIONING REPORT CERTIFICATION1
04/17/2024321596484Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
10/16/2023321596484Open ↗
▸BISLIGHTING IN DWELLING UNITS1
08/24/2023321596484Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B00286884-I1Open ↗
▸Inspections & Test Reports24
▸BISTECHNICAL REPORT: RESPONSIBILITY9
10/16/2023321596484Open ↗
07/24/2023321596484Open ↗
07/17/2023321596484Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX3
01/15/2022321596484Open ↗
12/17/2021321596484Open ↗
12/17/2021321596484Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
10/17/2023321596484Open ↗
12/17/2021321596484Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION2
10/16/2023321596484Open ↗
06/15/2020321596484Open ↗
▸BISSUBSURFACE / SOILS-FILL PLACEMENT IN-PLACE DENSITY1
05/14/2023321596484Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
07/06/2023321596484Open ↗
▸BISSUBSURFACE / SOILS INVESTIGATION (BORINGS/TEST PITS)1
10/17/2023321596484Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
12/17/2021321596484Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
05/14/2023321596484Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
09/07/2023321596484Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
08/24/2023321596484Open ↗
▸BISMASONRY1
08/24/2023321596484Open ↗
▸Approvals, Objections & Sign-offs14
▸BISSCHEDULE A - OCCUPANCY / USE12
10/24/2024321596484Open ↗
11/02/2023321596484Open ↗
10/24/2023321596484Open ↗
Showing 3 of 12 on file for this type
▸BISSUPERSEDING LETTER1
10/11/2022321596484Open ↗
▸BISBSA/CPC APPROVAL1
09/19/2023321596484Open ↗
▸Cost, Insurance & Ownership2
▸BISPROJECT-SPECIFIC GL INSURANCE2
01/15/2022321596484Open ↗
12/17/2021321596484Open ↗
▸Filing & Intake Forms21
▸BISADDITIONAL INFORMATION14
10/17/2023321596484Open ↗
10/17/2023321596484Open ↗
10/03/2023321596484Open ↗
Showing 3 of 14 on file for this type
▸BISEFILING COVER SHEET3
05/20/2025322121155Open ↗
12/26/2019321596484Open ↗
12/26/2019321596484Open ↗
▸BISBOROUGH INTAKE FORM3
10/11/2022321596484Open ↗
08/06/2022321596484Open ↗
12/17/2021321596484Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
03/26/2020340723337Open ↗
▸Other Documents11
▸BISALTERNATIVE MATERIALS - OTCR BUILDINGS BULLETIN2
10/16/2023321596484Open ↗
10/16/2023321596484Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
06/16/2025322121155Open ↗
06/16/2025322121155Open ↗
▸BISBPP-PARKS: PLANT NEW TREE1
05/12/2025321596484Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
06/18/2020321596484Open ↗
▸BISEXTERIOR INSULATION AND FINISH SYSTEMS (EIFS) (2014)1
10/16/2023321596484Open ↗
▸BISUNDERPINNING (2014)1
05/14/2023321596484Open ↗
▸BISVESTIBULES1
11/06/2023321596484Open ↗
▸BISTCO - Supporting Documents1
10/26/2023321596484Open ↗
▸BISPLOT DIAGRAM1
06/15/2020321596484Open ↗