| Owner | Filings | Most Recent |
|---|---|---|
| FIT | 64 | 07/15/2026 |
| North Shore Architectural Stone | 4 | 10/14/2026 |
| Phoenix | 3 | 03/21/2026 |
| NYC Department of Education | 1 | 03/22/2026 |
| Pagan | 1 | 03/22/2026 |
| Bigman Brothers | 1 | 03/22/2026 |
| Cube Construction Services | 1 | 03/22/2026 |
| F&G Associates | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DLR Group | 7 | 10/14/2026 |
| James A Clancy | 1 | 08/03/2026 |
| David Smotrich & Partners | 2 | 04/22/2026 |
| MG Engineering | 3 | 12/10/2025 |
| Project Tactical Solutions | 5 | 08/12/2025 |
| Shop Architects | 9 | 07/30/2025 |
| Mje Professional Services | 1 | 06/13/2025 |
| Buro Happold | 2 | 05/27/2025 |
| Urban Integrations | 1 | 04/25/2025 |
| JFK Associates | 6 | 11/18/2024 |
| Darius Toraby Architects | 2 | 08/01/2024 |
| MSM Engineering Services | 3 | 05/15/2024 |
| Philip Habib & Associates | 1 | 02/07/2024 |
| Tohfaz Uddin PE | 5 | 06/30/2023 |
| MPS Engineering | 1 | 05/27/2022 |
| Halsey McCormack Helmer | 1 | 05/25/2022 |
| Ryan Soames Engineering | 1 | 05/25/2022 |
| Universal Builders Supply | 1 | 04/15/2022 |
| Dseny Engineering Services | 2 | 11/23/2021 |
| Safway Atlantic | 1 | 04/14/2021 |
| Nce Consulting Engineers | 1 | 02/04/2021 |
| Railroad Construction Company | 1 | 01/20/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Milrose Consultants | 17 | 03/21/2026 |
| Municipal Expediting | 28 | 03/21/2026 |
| BSGNY | 10 | 03/21/2026 |
| Dseny Engineering Services | 4 | 03/21/2026 |
| Grand Expediters NYC | 1 | 03/21/2026 |
| Eurocelt Expediting | 12 | 03/21/2026 |
| A1 Expediting Service | 2 | 03/21/2026 |
| SNR Expediting Design | 2 | 03/21/2026 |
| Conapac Services Dba | 1 | 03/21/2026 |
| Orion Plumbing & Heating | 2 | 03/21/2026 |
| RPO | 2 | 03/21/2026 |
| Municipal Building Consultants | 1 | 03/21/2026 |
| Conapac Services | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Starr Industries | Scaffold | 14 | 07/08/2026 |
| Hellman Construction Co | General Contractor | 7 | 07/15/2026 |
| Spieler & Ricca Electrical Co | Electrical | 6 | 03/21/2026 |
| Carlitos Contracting | Scaffold | 6 | 03/21/2026 |
| E.e.cruz & Co | General Contractor | 6 | 07/08/2026 |
| Forte Construction | General Contractor | 5 | 07/08/2026 |
| Vikrant Contracting & Builder | Scaffold | 5 | 07/08/2026 |
| Forte Construction | Scaffold | 4 | 04/09/2026 |
| Jasco | Scaffold | 4 | 04/09/2026 |
| T.J. Piping & Heating | Fire Protection | 4 | 07/08/2026 |
| Probuildero | General Contractor | 3 | 07/08/2026 |
| North Shore Arch Stone | General Contractor | 2 | 10/14/2026 |
| Tuxedo Electrical Contracting | Electrical | 2 | 03/21/2026 |
| JRM Construction Management | General Contractor | 2 | 04/09/2026 |
| R.A.M.S. Mechanical | specialty_contractor | 2 | 07/08/2026 |
| Spectrum Wide Productions | General Contractor | 2 | 07/25/2026 |
| Safway Atlantic | Scaffold | 2 | 03/21/2026 |
| Universal Builders Supply | Scaffold | 2 | 07/08/2026 |
| Eastern Plumbing & Mechanical Contracting | Plumbing | 2 | 07/08/2026 |
| M&D Fire Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Harrand Electrical Contractors | Electrical | 1 | 03/22/2026 |
| M&T Plumbing and Heating Co | Plumbing | 1 | 07/08/2026 |
| Precision Electrical Cont | Electrical | 1 | 03/21/2026 |
| Luna NYC Electric | Electrical | 1 | 03/21/2026 |
| LCJ Electrical Contractors | Electrical | 1 | 03/22/2026 |
| Lemx | Scaffold | 1 | 07/08/2026 |
| Mac Felder | Plumbing | 1 | 07/08/2026 |
| Massaro Electric | Electrical | 1 | 03/21/2026 |
| Boris Mechanical | specialty_contractor | 1 | 07/08/2026 |
| Zena Electric | Electrical | 1 | 03/22/2026 |
| Hobo Construction Co | General Contractor | 1 | 07/08/2026 |
| Cedar Electrical Contractors | Electrical | 1 | 03/22/2026 |
| Bigman Brothers | Electrical | 1 | 03/22/2026 |
| Piece Management | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Alan Margolin & Associates | 423 | 9 | 10/14/2026 |
| James A Clancy | 9176 | 1 | 08/03/2026 |
| Future Tech Consultants O | 589 | 10 | 05/27/2025 |
| Darius Toraby Architects | 116 | 1 | 08/01/2024 |
| Socotec Engineering | 4983 | 1 | 09/01/2022 |
| Mancini Duffy Architectur | 2985 | 1 | 05/25/2022 |
| Project Tactical Solution | 5859 | 3 | 04/01/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | North Shore Arch Stone | 10/13/2026 |
| DOB NOW | General Construction | Permit Issued | Spectrum Wide Productions | 07/23/2026 |
| DOB NOW | Foundation | Signed-off | Hellman Construction Co | 07/14/2026 |
| DOB NOW | Structural | Signed-off | Probuildero | 07/06/2026 |
| DOB NOW | General Construction | Signed-off | Probuildero | 07/06/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | R.A.M.S. Mechanical | 04/01/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | Jasco | 01/28/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | R.A.M.S. Mechanical | 12/05/2025 |
| DOB NOW | Standpipe | Signed-off | M&D Fire Sprinkler | 10/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Forte Construction | 09/05/2025 |
| DOB NOW | General Construction | Permit Issued | Forte Construction | 09/04/2025 |
| DOB NOW | General Construction | Permit Issued | North Shore Arch Stone | 09/03/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM Construction Management | 08/05/2025 |
| DOB NOW | Plumbing | Signed-off | Mac Felder | 07/28/2025 |
| DOB NOW | General Construction | Permit Issued | JRM Construction Management | 07/25/2025 |
| DOB NOW | General Construction | Signed-off | Probuildero | 07/11/2025 |
| DOB NOW | Structural | Signed-off | Forte Construction | 07/03/2025 |
| DOB NOW | Supported Scaffold | Signed-off | Jasco | 06/16/2025 |
| DOB NOW | General Construction | Signed-off | Hellman Construction Co | 05/20/2025 |
| DOB NOW | General Construction | Permit Issued | Spectrum Wide Productions | 04/30/2025 |
| DOB NOW | Curb Cut | Signed-off | Forte Construction | 02/25/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Forte Construction | 02/20/2025 |
| DOB NOW | Plumbing | Signed-off | Eastern Plumbing & Mechanical Contracting | 01/21/2025 |
| DOB NOW | Foundation | Signed-off | Hellman Construction Co | 01/09/2025 |
| DOB NOW | General Construction | Signed-off | Hobo Construction Co | 08/02/2024 |
| DOB NOW | Supported Scaffold | Signed-off | Starr Industries | 07/09/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Starr Industries | 07/09/2024 |
| DOB NOW | Sprinklers | Signed-off | M&D Fire Sprinkler | 05/29/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Lemx | 04/23/2024 |
| DOB NOW | Standpipe | Signed-off | T.J. Piping & Heating | 04/04/2024 |
| DOB NOW | Standpipe | Signed-off | T.J. Piping & Heating | 03/04/2024 |
| DOB NOW | Foundation | Signed-off | Hellman Construction Co | 11/14/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Starr Industries | 07/10/2023 |
| DOB NOW | Supported Scaffold | Signed-off | Starr Industries | 07/10/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Vikrant Contracting & Builders | 06/06/2023 |
| DOB NOW | Plumbing | Signed-off | Eastern Plumbing & Mechanical Contracting | 04/27/2023 |
| DOB NOW | Construction Fence | Signed-off | Forte Construction | 04/15/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Universal Build Supp | 04/14/2023 |
| DOB NOW | Standpipe | Signed-off | T.J. Piping & Heating | 03/13/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Starr Industries | 07/19/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/13/2025 | Permit Issued | JRM Construction Management | Air Conditioning Systems, Ventilation Systems | Cooling Daikin CU-1: 2MXM18; CU-2: RKF24AXVJU 2 tons · Condensing Unit ×2 FTXV12AVJU 8,600 BTU · Fan Coil Indoor ×2 FTKF24AXVJU 22,400 BTU · Split System ×1 Ventilation Loren Cook ACE-D VF 1 CFM · Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2025 | Signed-off | Mac Felder | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2026 | Permit Issued | Eldor Electric | — |
| 12/26/2025 | Complete | Luna NYC Electric | — |
| 10/28/2025 | Permit Issued | Precision Electrical Cont | General Wiring |
| 09/11/2025 | Permit Issued | Mid City Electrical | — |
| 06/17/2025 | Complete | Erne Valley Electrical | General Wiring |
| 06/17/2025 | Permit Issued | Richard Neu | — |
| 01/07/2025 | Complete | Zena Electric | General Wiring |
| 10/22/2024 | Complete | LCJ Electrical Contractors | General Wiring |
| 06/17/2024 | Complete | Core Electric MEP Inds | Lighting |
| 04/23/2024 | Complete | Richard Neu | — |
| 12/12/2023 | Complete | Cedar Electrical Contractors | General Wiring |
| 10/17/2023 | Complete | Interphase Electric | General Wiring |
| 09/21/2023 | Complete | LCJ Electrical Contractors | General Wiring |
| 07/12/2023 | Permit Issued | Tuxedo Electrical Contracting | — |
| 11/02/2022 | Permit Issued | Tuxedo Electrical Contracting | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/14/2026 | Signed-off | Probuildero | Steel |
| 11/07/2023 | Signed-off | Hellman Construction Co | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/14/2026 | Signed-off | Probuildero | 276 panels, 157.4 kw, 10,400 roof_area_sqft |
| 08/03/2026 | — | — | 60 panels, 29.4 kw, 12,454 roof_area_sqft |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Water Test | Certified | View ↗ |
| 05/28/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/04/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/30/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/04/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 04/03/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/03/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/21/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/21/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Water Test | Certified | View ↗ |
| 11/28/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/29/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/22/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/13/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/30/2026 | Post-installed Anchors | Young Suh | special |
| 09/30/2026 | Air barrier - visual inspection | Young Suh | energy_progress |
| 09/30/2026 | Final | Young Suh | progress |
| 09/30/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 09/30/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| 07/06/2026 | Air barrier - visual inspection | James Clancy | energy_progress |
| 07/06/2026 | Final | James Clancy | progress |
| 07/06/2026 | Fire-Resistant Penetrations and Joints | James Clancy | special |
| 07/06/2026 | Structural Stability – Alterations of existing buildings | James Clancy | special |
| 07/06/2026 | Energy Code Compliance Inspections | James Clancy | progress |
| 12/08/2025 | Energy Code Compliance Inspections | — | progress |
| 12/08/2025 | Mechanical Systems | — | special |
| 12/08/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 12/08/2025 | Final | — | progress |
| 07/09/2025 | Final | Max Lee | progress |
| 06/24/2025 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 06/24/2025 | Post-installed Anchors | Young Suh | special |
| 05/30/2025 | Post-installed Anchors | Stephen Marchese | special |
| 05/30/2025 | Structural Steel - High Strength Bolting | Stephen Marchese | special |
| 05/30/2025 | Structural Steel - Welding | Stephen Marchese | special |
| 05/30/2025 | Structural Stability – Alterations of existing buildings | Stephen Marchese | special |
| 05/30/2025 | Structural Steel - Details | Stephen Marchese | special |
| 05/30/2025 | Concrete - Cast-In-Place | Stephen Marchese | special |
| 05/30/2025 | Final | CRAIG SCHWITTER | progress |
| 05/15/2025 | Structural Stability – Alterations of existing buildings | Stephen Marchese | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Fashion Institute of Technology | Education | Cellar, Floors 1–8, Roof | Project M01330655 Project M01221073 Project M01253614 Project M01178952 Project M01138990 Project M00773496 Project M00773565 Project M00772349 Project M00773580 Project M00775650 Project M00480836 Project M00590739 |
| F.I.T | Education | Floors 1, 9 | Project M00998095 Project M00775665 |
| Marvin Feldman Center | Education | — | Project M00888724 |
| F.I.T. N.A.B | Education | Cellar, Floors 1–10, Roof | Project M00739346 |
| Starbucks | Restaurant / Food Service | Floor 1 | Project M00731619 Project M00731641 |