← Back
Primarily 3 family with 1 store or office
225 1 AVENUE
MANHATTAN · East Village · BIN 1006527
💬 Discuss this project
1920Year Built
4Stories
S3Building Class
C1-7AZoning
4,180 sfGross Floor Area
4Units
Rent Stabilized3 Open Violations ▸
Primarily 3 family with 1 store or office · Owner of record: SOSOCAM LLC · 1,620 sf lot · 2.58 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingCivil
Permit Issued — active, not yet Signed-off
Roof31p · 1 filing · 12 docs
Floor 1Under Construction33p · 2 filings · 20 docs
CellarUnder Construction34p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SOSOCAM LLC203/22/2026
JABAYS203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PETER CHO ARCHITECTS, PLLC202/09/2026
SALVATOR A. CARADONNA JR.107/27/2023
ZELTA DESIGN206/14/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
WM ARCH403/21/2026
EPAC BUILDING CONSULTING INC403/21/2026
ALL IN PERMIT CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ALL AMERICAN CONSTRUCTIONGeneral Contractor403/21/2026
HARARI DAVIDElectrical103/21/2026
TORRES IVANElectrical103/21/2026
PROTON CCM LLCGeneral Contractor104/09/2026
TRI CITY MECHANICAL GROUP CORPPlumbing107/08/2026
NATIONAL MAINTENANCEScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244102/09/2026
ZELTA INSPECT LLC7764106/14/2023
Building Lifecycle
All (37)Filed (5)Permit Issued (5)Signed Off (2)Violation (4)Special Inspection (21)
04/29/2026
Violation issued (HPD, open)
A
02/17/2026
Permit issued — Plumbing
M01351509-S1-PL
02/13/2026
Permit issued — General Construction
M01351509-I1-GC
02/09/2026
Filed — Alteration
M01351509-I1
02/09/2026
Filed — Alteration
M01351509-S1
01/27/2026
Special inspection requirement — Lighting controls
PETER CHO
01/27/2026
Special inspection requirement — Fire-Resistance Rated Construction
PETER CHO
01/27/2026
Special inspection requirement — Metering
PETER CHO
01/27/2026
Special inspection requirement — Energy Code Compliance Inspections
PETER CHO
01/27/2026
Special inspection requirement — Interior lighting power
PETER CHO
01/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
01/26/2026
Special inspection requirement — Final
PETER CHO
06/04/2025
Violation issued (HPD, open)
A
11/13/2023
Signed off — Alteration
M00903303-I1
09/12/2023
Signed off — Alteration
M00875139-I1
08/01/2023
Permit issued — Sign
M00903303-I1-SG
07/27/2023
Filed — Alteration
M00903303-I1
06/15/2023
Permit issued — General Construction
M00887860-I1-GC-CX
06/14/2023
Filed — Alteration
PROPOSED EATING & DRINKING ESTABLISHMENT ON FIRST & CELLAR FLOOR LEVEL. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
M00887860-I1
06/08/2023
Special inspection requirement — Interior lighting power
ERIK LIEPINS
06/08/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
ERIK LIEPINS
06/08/2023
Special inspection requirement — Exterior lighting power
ERIK LIEPINS
06/08/2023
Special inspection requirement — HVAC-R and service water heating system controls
ERIK LIEPINS
06/08/2023
Special inspection requirement — Insulation placement and R values
ERIK LIEPINS
06/08/2023
Special inspection requirement — Lighting controls
ERIK LIEPINS
06/08/2023
Special inspection requirement — Maintenance information
ERIK LIEPINS
06/08/2023
Special inspection requirement — Shutoff dampers
ERIK LIEPINS
06/08/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
ERIK LIEPINS
06/08/2023
Special inspection requirement — Mechanical Systems
ERIK LIEPINS
06/08/2023
Special inspection requirement — Energy Code Compliance Inspections
ERIK LIEPINS
06/08/2023
Special inspection requirement — Final
ERIK LIEPINS
06/08/2023
Special inspection requirement — Duct leakage testing, insulation and design
ERIK LIEPINS
06/08/2023
Special inspection requirement — HVAC-R and service water heating equipment
ERIK LIEPINS
05/24/2023
Permit issued — Construction Fence
M00875139-I1-FN
05/22/2023
Filed — Alteration
M00875139-I1
07/08/2003
Violation issued (ECB, closed)
Construction
04/26/1990
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedFLAVIO MECHANICAL CORP02/17/2026
DOB NOWGeneral ConstructionPermit IssuedPROTON CCM LLC02/13/2026
DOB NOWSignSigned-offNATIONAL MAINTENANCE, INC08/01/2023
DOB NOWGeneral ConstructionPermit IssuedALL AMERICAN CONSTRUCTION06/15/2023
DOB NOWConstruction FenceSigned-offALL AMERICAN CONSTRUCTION05/24/2023
BISFPISSUEDCITYWIDE FIRE SYS PLBG EN11/19/2014
BISPLISSUEDINFINITI ESC PLUMBING COR08/20/2014
BISOTISSUEDARP HOME IMPROVEMENT CORP08/19/2014
BISEQISSUEDARP HOME IMPROVEMENT CORP08/19/2014
BIS—ISSUEDLETTERA SIGN & ELECTRIC CO09/23/1996
BISPLISSUEDI.M.P. PLBG. & HTG. CORP05/13/1993
BISMHISSUEDUS MECHANICAL04/28/1993
1 project · most recent 06/14/2023
Air Conditioning Systems
FiledStatusContractorScope
06/14/2023Permit IssuedALL AMERICAN CONSTRUCTIONAir Conditioning Systems
2 projects · most recent 02/03/2026
FiledStatusContractorScope
02/03/2026CompleteCL ELECTRICAL CORP—
08/17/2023CompleteRAINBOW ELECTRIC CO., INC—
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
01/27/2026Lighting controlsPETER CHOenergy_progress
01/27/2026Fire-Resistance Rated ConstructionPETER CHOprogress
01/27/2026MeteringPETER CHOenergy_progress
01/27/2026Energy Code Compliance InspectionsPETER CHOprogress
01/27/2026Interior lighting powerPETER CHOenergy_progress
01/27/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
01/26/2026FinalPETER CHOprogress
06/08/2023Interior lighting powerERIK LIEPINSenergy_progress
06/08/2023HVAC-R and service water piping design and insulationERIK LIEPINSenergy_progress
06/08/2023Exterior lighting powerERIK LIEPINSenergy_progress
06/08/2023HVAC-R and service water heating system controlsERIK LIEPINSenergy_progress
06/08/2023Insulation placement and R valuesERIK LIEPINSenergy_progress
06/08/2023Lighting controlsERIK LIEPINSenergy_progress
06/08/2023Maintenance informationERIK LIEPINSenergy_progress
06/08/2023Shutoff dampersERIK LIEPINSenergy_progress
06/08/2023Fire-Resistant Penetrations and JointsERIK LIEPINSspecial
06/08/2023Mechanical SystemsERIK LIEPINSspecial
06/08/2023Energy Code Compliance InspectionsERIK LIEPINSprogress
06/08/2023FinalERIK LIEPINSprogress
06/08/2023Duct leakage testing, insulation and designERIK LIEPINSenergy_progress
06/08/2023HVAC-R and service water heating equipmentERIK LIEPINSenergy_progress
▾Documents — 61 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/31/2026M00875139-I1Request digital key ↗
08/30/2026M00887860-P1Request digital key ↗
08/30/2026M00887860-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits8
▸BISWORK PERMIT APPLICATION4
08/25/2014121783276Open ↗
08/21/2014121783276Open ↗
08/21/2014121783276Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION4
11/20/2014121783276Open ↗
11/11/2014122123371Open ↗
09/04/2014121783276Open ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/31/2026M00875139-I1Open ↗
08/30/2026M00887860-P1Open ↗
08/30/2026M00887860-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
08/28/2026M01351509-I1Open ↗
08/28/2026M01351509-I1Open ↗
08/27/2026M00887860-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/28/2026M01351509-I1Open ↗
08/27/2026M00887860-P1Open ↗
08/26/2026M00887860-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY-CERTIFICATION2
08/16/2014121783276Open ↗
08/21/2014121783276Open ↗
▸Trade Schedules & Equipment7
▸BISSELF-CERT PLUMBING NOTICE3
01/20/2015121783276Open ↗
01/05/2015121783276Open ↗
12/10/2014121783276Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
11/20/2014121783276Open ↗
09/04/2014121783276Open ↗
▸BISSCHEDULE B - PLUMBING2
09/26/2014121783276Open ↗
08/16/2014121783276Open ↗
▸Safety & Tenant Protection4
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE3
08/21/2014121783276Open ↗
08/21/2014121783276Open ↗
08/21/2014121783276Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
08/21/2014121783276Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/30/2026M00887860-I1Open ↗
08/30/2026M00887860-P1Open ↗
08/29/2026M00903303-I1Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS-CERTIFICATION (DEP ACP5)2
08/16/2014121783276Open ↗
11/11/2014122123371Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
08/21/2014121783276Open ↗
▸BISTR8: Energy Code Progress Inspections1
08/16/2014121783276Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
08/16/2014121783276Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
11/11/2014122123371Open ↗
08/16/2014121783276Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION2
12/04/2014121783276Open ↗
10/15/2014121783276Open ↗
▸BISEFILING COVER SHEET2
11/11/2014122123371Open ↗
08/16/2014121783276Open ↗