| Owner | Filings | Most Recent |
|---|---|---|
| 14 So Williamsport Holding | 687 | 03/22/2026 |
| Circle Realty Group | 370 | 10/16/2026 |
| Pennyslvania Building Company | 245 | 03/21/2026 |
| 14 Penn Plaza | 38 | 03/21/2026 |
| The New York Hotel Trades Council | 22 | 07/08/2026 |
| 14 Pennsylvania Plaza | 6 | 03/21/2026 |
| Balmer Parc | 3 | 03/21/2026 |
| 114 Fifth Avenue Associates C/O Balm | 2 | 03/21/2026 |
| Preserv Building Restoration Management | 1 | 10/13/2026 |
| Dakota Realty Group | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MKNH Architects | 27 | 10/15/2026 |
| M. Chetrit Consulting Engineers | 33 | 09/29/2026 |
| Soni Engineering Consulting | 3 | 09/17/2026 |
| Always Fast Services | 7 | 08/26/2026 |
| Paul Perdek, Prof. Engineering | 2 | 07/31/2026 |
| Socotec | 1 | 03/31/2026 |
| Moloney | 3 | 03/11/2026 |
| M. Chetrit Consulting Engineers | 44 | 08/13/2025 |
| Richard Kornblau | 5 | 11/21/2024 |
| Ashraf | 1 | 12/11/2018 |
| Lighthouse | 2 | 06/21/2018 |
| MCRB Service | 1 | 05/09/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| EA Design Group | 126 | 03/21/2026 |
| Rethy Associates | 24 | 03/21/2026 |
| Municipal Building Consultants | 5 | 03/21/2026 |
| HH Building Consulting & Architectu | 8 | 03/21/2026 |
| KM Associates of New York | 5 | 03/21/2026 |
| K & M Associates | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Rinnovo Construction | General Contractor | 20 | 07/08/2026 |
| D.B.J. Contracting | General Contractor | 15 | 07/08/2026 |
| Monumental Construction * | General Contractor | 11 | 09/16/2026 |
| A.W. & S. Construction Co | General Contractor | 11 | 09/12/2026 |
| Pratt Construction & Restoration | Scaffold | 10 | 07/08/2026 |
| Darby Construction Service | General Contractor | 7 | 10/06/2026 |
| Aqueduct Mechanical | Fire Protection | 6 | 07/08/2026 |
| Theodore Williams Construction | General Contractor | 6 | 03/21/2026 |
| Unisol | General Contractor | 6 | 07/08/2026 |
| William C. Gerakaris P&H | Plumbing | 6 | 09/18/2026 |
| All Tech Mechanical | specialty_contractor | 6 | 07/08/2026 |
| Aqueduct Mechanical | Plumbing | 5 | 07/08/2026 |
| Denko Mechanical | Fire Protection | 4 | 07/08/2026 |
| Andamio Scaffolding | Scaffold | 4 | 09/12/2026 |
| A&A Plumbing | Plumbing | 4 | 07/08/2026 |
| A Plus Plumbing | Fire Protection | 3 | 10/06/2026 |
| Taurino Management | General Contractor | 3 | 03/21/2026 |
| Authentic Plumbing | Plumbing | 3 | 08/25/2026 |
| Firequest | Fire Protection | 3 | 07/08/2026 |
| Frank Torrone & Sons | Electrical | 3 | 03/21/2026 |
| JLC Electrical Contracting | Electrical | 2 | 03/22/2026 |
| Gregg NY Plumbing | Plumbing | 2 | 07/08/2026 |
| Phase 3 Interiors | General Contractor | 2 | 04/09/2026 |
| Dependable Mechanical | Fire Protection | 2 | 07/08/2026 |
| JLC Electrical Contracting | Electrical | 2 | 03/21/2026 |
| Asco Sprinkler Co | Fire Protection | 2 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 2 | 07/08/2026 |
| Reem Plumbing & Heating | Fire Protection | 2 | 07/08/2026 |
| Reem Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| Preserv BLD Restoration Management | Scaffold | 2 | 08/26/2026 |
| Five Borough NYC | Fire Protection | 2 | 07/08/2026 |
| Orbit Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Infiniti Electric | Electrical | 1 | 03/22/2026 |
| Tuxedo Electrical Contracting | Electrical | 1 | 03/21/2026 |
| John Michael Electrical Contg | Electrical | 1 | 03/22/2026 |
| Lenox, JR, Joseph | Electrical | 1 | 03/21/2026 |
| MLS Electric | Electrical | 1 | 03/22/2026 |
| Omd Electrical | Electrical | 1 | 03/22/2026 |
| Valentis Electric | Electrical | 1 | 03/21/2026 |
| Malic | General Contractor | 1 | 07/08/2026 |
| Preserv BLD Restoration Management | General Contractor | 1 | 07/01/2026 |
| Access Plumbing | Plumbing | 1 | 07/08/2026 |
| Aggressive Fire Protection | Fire Protection | 1 | 07/08/2026 |
| A&H Express Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| A + Sprinkler | Fire Protection | 1 | 07/08/2026 |
| DV Plumbing | Plumbing | 1 | 07/08/2026 |
| Frankie Plumbing & Heating | Plumbing | 1 | 06/28/2026 |
| G&B Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Grushinsky Pipng & Heating | Fire Protection | 1 | 07/08/2026 |
| Metrotech Mechanical | Plumbing | 1 | 10/10/2026 |
| Nonstop Plumbers | Fire Protection | 1 | 07/08/2026 |
| Orbit Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Par Fire Protection | Fire Protection | 1 | 07/08/2026 |
| PFL Mechanical | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Assure Professional Engineering | 6962 | 25 | 09/29/2026 |
| Soni Engineering Consulting | 9819 | 3 | 09/17/2026 |
| Crosscheck Inspection Services | 544 | 9 | 04/07/2026 |
| Socotec | 301 | 1 | 03/31/2026 |
| Joseph Martines PE | 1428 | 59 | 08/13/2025 |
| Richard B. Kornblau, AIA | 3208 | 3 | 11/21/2024 |
| Richard H. Balser Engineering | 3028 | 1 | 09/05/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | Metrotech Mechanical | 10/09/2026 |
| DOB NOW | Sprinklers | Permit Issued | A Plus Plumbing | 10/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Darby Construction Service | 10/05/2026 |
| DOB NOW | General Construction | Permit Issued | Darby Construction Service | 10/01/2026 |
| DOB NOW | Plumbing | Permit Issued | William C. Gerakaris P&H | 09/17/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Monumental Construction * | 09/15/2026 |
| DOB NOW | Plumbing | Permit Issued | William C. Gerakaris P&H | 09/15/2026 |
| DOB NOW | General Construction | Permit Issued | Monumental Construction * | 09/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | A.W. & S. Construction Co | 09/10/2026 |
| DOB NOW | General Construction | Permit Issued | A.W. & S. Construction Co | 09/10/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Andamio Scaffolding | 09/10/2026 |
| DOB NOW | Plumbing | Permit Issued | William C. Gerakaris P&H | 08/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | Authentic Plumbing | 08/24/2026 |
| DOB NOW | Sprinklers | Permit Issued | A Plus Plumbing | 08/17/2026 |
| DOB NOW | Plumbing | Permit Issued | Authentic Plumbing | 08/14/2026 |
| DOB NOW | Plumbing | Permit Issued | William C. Gerakaris P&H | 08/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | A.W. & S. Construction Co | 08/05/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Preserv BLD Restoration Management | 08/03/2026 |
| DOB NOW | General Construction | Permit Issued | A.W. & S. Construction Co | 08/03/2026 |
| DOB NOW | Sprinklers | Permit Issued | A Plus Plumbing | 07/31/2026 |
| DOB NOW | Plumbing | Permit Issued | William C. Gerakaris P&H | 07/23/2026 |
| DOB NOW | General Construction | Permit Issued | A.W. & S. Construction Co | 07/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | A.W. & S. Construction Co | 07/22/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Preserv BLD Restoration Management | 07/21/2026 |
| DOB NOW | General Construction | Permit Issued | Preserv BLD Restoration Management | 06/29/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Andamio Scaffolding | 06/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Darby Construction Service | 06/09/2026 |
| DOB NOW | Sprinklers | Permit Issued | Five Borough NYC | 06/05/2026 |
| DOB NOW | General Construction | Permit Issued | Darby Construction Service | 05/29/2026 |
| DOB NOW | Plumbing | Signed-off | Orbit Plumbing & Heating | 05/08/2026 |
| DOB NOW | Sprinklers | Signed-off | Orbit Sprinkler | 05/07/2026 |
| DOB NOW | Plumbing | Signed-off | Authentic Plumbing | 04/14/2026 |
| DOB NOW | Sprinklers | Signed-off | Nonstop Plumbers | 04/14/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | Preserv Building Restoration | 04/07/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Andamio Scaffolding | 03/26/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | Andamio Scaffolding | 03/24/2026 |
| DOB NOW | General Construction | Permit Issued | Darby Construction Service | 03/20/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Darby Construction Service | 03/20/2026 |
| DOB NOW | Plumbing | Permit Issued | Frankie Plumbing & Heating | 03/20/2026 |
| DOB NOW | Structural | Signed-off | Darby Construction Service | 03/19/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/15/2026 | — | — | Heating and Air Conditioning Systems, Ventilation Systems | |
| 09/29/2026 | Permit Issued | Darby Construction Service | Heating and Air Conditioning Systems, Ventilation Systems | |
| 09/01/2026 | Permit Issued | A.W. & S. Construction Co | Heating and Air Conditioning Systems, Ventilation Systems | |
| 08/05/2026 | Permit Issued | Monumental Construction * | Ventilation Systems | Ventilation Greenheck SP-A510-VG 200 CFM · Exhaust Fan ×1 |
| 07/23/2026 | Permit Issued | A.W. & S. Construction Co | Heating and Air Conditioning Systems, Ventilation Systems | |
| 06/01/2026 | Permit Issued | Darby Construction Service | Air Conditioning Systems | Cooling Trane GEHK036 38,360 BTU · Wshp ×1 |
| 06/17/2025 | Signed-off | Unisol | Ventilation Systems | Ventilation Greenheck CSP-A710-VG 300 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | — | — | 223 heads |
| 09/29/2026 | — | — | 111 heads |
| 09/01/2026 | Permit Issued | A Plus Plumbing | 53 heads |
| 08/05/2026 | — | — | 71 heads |
| 07/23/2026 | Permit Issued | A Plus Plumbing | 38 heads |
| 06/01/2026 | Permit Issued | Five Borough NYC | — |
| 04/07/2026 | Signed-off | Orbit Sprinkler | 139 heads |
| 03/11/2026 | Permit Issued | Five Borough NYC | 113 heads |
| 01/16/2026 | Signed-off | Nonstop Plumbers | 33 heads |
| 06/17/2025 | Signed-off | Firequest | 15 heads |
| 09/05/2023 | Signed-off | Par Fire Protection | — |
| 11/13/2019 | Signed-off | Aqueduct Mechanical | 35 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | — | — | Water/Sanitary |
| 09/29/2026 | Permit Issued | Metrotech Mechanical | Water/Sanitary |
| 09/01/2026 | Permit Issued | William C. Gerakaris P&H | Water/Sanitary |
| 08/05/2026 | Permit Issued | Nonstop Plumbers | Water/Sanitary |
| 07/23/2026 | Permit Issued | William C. Gerakaris P&H | Water/Sanitary |
| 07/21/2026 | Permit Issued | William C. Gerakaris P&H | Water/Sanitary |
| 03/11/2026 | Permit Issued | Frankie Plumbing & Heating | Water/Sanitary |
| 01/16/2026 | Signed-off | Nonstop Plumbers | Water/Sanitary |
| 11/21/2024 | Permit Issued | Access Plumbing | Water/Sanitary |
| 09/05/2023 | Signed-off | Par Plumbing Co | Water/Sanitary |
| 11/13/2019 | Signed-off | Aqueduct Mechanical | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2026 | Permit Issued | Valentis Electric | General Wiring |
| 09/17/2026 | Permit Issued | A2K Electric | General Wiring |
| 09/16/2026 | Complete | Valentis Electric | General Wiring |
| 09/09/2026 | Permit Issued | Valentis Electric | General Wiring |
| 09/09/2026 | Permit Issued | Valentis Electric | General Wiring |
| 06/10/2026 | Permit Issued | Valentis Electric | General Wiring |
| 03/23/2026 | Permit Issued | Borowide Elect'l Contractors | — |
| 03/20/2026 | Permit Issued | Valentis Electric | General Wiring |
| 06/30/2025 | Permit Issued | GMC Electrical | General Wiring |
| 06/25/2025 | Complete | Top Notch Electric | General Wiring |
| 12/02/2024 | Complete | Empire State Electl | General Wiring |
| 10/01/2024 | Permit Issued | Omd Electrical | 1 meters, 1 new_meters |
| 07/26/2024 | Complete | Valentis Electric | General Wiring |
| 04/23/2024 | Complete | Valentis Electric | General Wiring |
| 03/04/2024 | Permit Issued | Allstate Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | Permit Issued | Andamio Scaffolding | Scaffold |
| 08/01/2026 | Permit Issued | Andamio Scaffolding | Sidewalk Shed |
| 06/21/2018 | Permit Issued | Pratt Construction & Restoration | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2026 | Permit Issued | Preserv Building Restoration | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/19/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/19/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/11/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/30/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/24/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/15/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/09/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/18/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/16/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/12/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/13/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/13/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/16/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/11/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/11/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/23/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/25/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/28/2026 | Fire-Resistance Rated Construction | — | progress |
| 09/28/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 09/28/2026 | Final | MICHAEL KAZAZIS | progress |
| 09/23/2026 | Sprinkler Systems | GUNJAN KHANDWALA | special |
| 09/16/2026 | Fire-Resistant Penetrations and Joints | GUNJAN KHANDWALA | special |
| 09/16/2026 | Fire-Resistance Rated Construction | GUNJAN KHANDWALA | progress |
| 09/14/2026 | Alternative Materials - OTCR Buildings Bulletin Number | nayan soni | special |
| 09/14/2026 | Structural Stability – Alterations of existing buildings | nayan soni | special |
| 09/14/2026 | Post-installed Anchors | nayan soni | special |
| 09/10/2026 | Final | MICHAEL KAZAZIS | progress |
| 08/21/2026 | Fire-Resistant Penetrations and Joints | GUNJAN KHANDWALA | special |
| 08/06/2026 | Maintenance information | GUNJAN KHANDWALA | energy_progress |
| 08/06/2026 | Final | GUNJAN KHANDWALA | progress |
| 08/06/2026 | Lighting controls | GUNJAN KHANDWALA | energy_progress |
| 08/06/2026 | Post-installed Anchors | GUNJAN KHANDWALA | special |
| 08/06/2026 | Shutoff dampers | GUNJAN KHANDWALA | energy_progress |
| 08/06/2026 | HVAC-R and service water heating equipment | GUNJAN KHANDWALA | energy_progress |
| 08/06/2026 | HVAC-R and service water piping design and insulation | GUNJAN KHANDWALA | energy_progress |
| 08/06/2026 | Final | MICHAEL KAZAZIS | progress |
| 08/06/2026 | HVAC-R and service water heating system controls | GUNJAN KHANDWALA | energy_progress |
| 08/06/2026 | Interior lighting power | GUNJAN KHANDWALA | energy_progress |
| 08/06/2026 | Sprinkler Systems | GUNJAN KHANDWALA | special |
| 08/06/2026 | Energy Code Compliance Inspections | GUNJAN KHANDWALA | progress |
| 08/06/2026 | Mechanical Systems | GUNJAN KHANDWALA | special |
| 08/06/2026 | Metering | GUNJAN KHANDWALA | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Roux | Office | Floor 17 | Project M01458268 |
| M Topros | Office | Floor 21 | Project M01436852 |
| Calibre | Office | Floor 20 | Project M01429487 |
| Preserv | Office | — | Project M01437669 |
| Jan Brown Law | Office | Floor 13 | Project M01424080 |
| SCL Law | Office | Floor 19 | Project M01399089 |
| K-Force | Office | Floor 16 | Project M01229169 Project M00305026 Project M00305033 |
| Chelsea Lighting | Office | Floor 15 | Project M01203596 |
| CSG/EMCOR | Office | Floor 3, Roof | Project M01149453 |
| Regus | Office | Floors 9, 10 | Project M01053844 |
| VM Ware | Office | Floor 7 | Project M00954261 Project M00954264 Project M00954233 |
| CBMS | Office | Floor 8 | Project M00954839 |
| KM Associates Realty | Office | Floor 16 | Project M00783905 Project M00784141 Project M00784157 Project M00784177 |
| Bohler Engineering | Office | Floor 11 | Project M00401988 Project M00402029 Project M00454296 |
| JCRC | Office | Floor 16 | Project M00429478 Project M00429614 |
| LAC Group | Office | Floor 4 | Project M00262919 Project M00262924 |
| Prager Metis | Office | Floor 18, Roof | Project M00256877 Project M00256889 |