| Owner | Filings | Most Recent |
|---|---|---|
| 227 EAST 19 STREET OWNER LLC | 64 | 03/21/2026 |
| DOUGLAS ELLIMAN PROPERTY MANAGEMENT | 28 | 09/14/2026 |
| RENNON CONSTRUCTION | 8 | 07/08/2026 |
| DORIA | 7 | 07/08/2026 |
| 225 WEST 17TH STREET | 6 | 07/08/2026 |
| J G GNRL CONTRACT | 6 | 03/21/2026 |
| CLIPPER EQUITY | 2 | 03/22/2026 |
| 227 E19TH STREET OWNER | 2 | 03/21/2026 |
| 227 E 19TH OWENERS | 2 | 03/21/2026 |
| SKI REALTY | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ENDA DONAGHER ARCHITECT PC | 3 | 07/09/2026 |
| VAS | 3 | 05/02/2026 |
| EUGENE KHANANOV AIA | 1 | 02/05/2026 |
| WILLIAM F. RYAN, JR. P.E. PC | 1 | 09/16/2025 |
| AMIE SACHS ARCHITECTS | 1 | 09/08/2025 |
| SKYLINE RIGGING | 1 | 08/21/2024 |
| 2LS CONSULTING ENGINEERING, DPC | 8 | 02/28/2024 |
| MATHESON ARCHITECTURE + DESIGN | 1 | 01/19/2024 |
| RESOLUTION: 4 ARCHITECTURE | 3 | 12/11/2023 |
| FURMAN & FURMAN ARCHITECTS | 1 | 10/31/2023 |
| PLUS GROUP CONSULTING ENGG, PLLC | 6 | 08/08/2023 |
| ARRA ARCHITECTURE | 1 | 04/21/2022 |
| GERTLER & WENTE ARCHITECTS | 1 | 09/13/2021 |
| BEST PROFESSIONALS NY CORP | 2 | 10/11/2019 |
| IKRA CONSULTING LLC | 2 | 12/12/2018 |
| SCALAR ARCHITECTURE PC | 1 | 08/20/2018 |
| BAILEYS ENGINEERING PC | 1 | 08/20/2018 |
| ASHRAF CORP | 1 | 08/03/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| METROPOLIS GROUP INC | 14 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| CODE | 4 | 03/21/2026 |
| BELFIORE CONSUTLANTS | 1 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 11 | 03/21/2026 |
| AK CONSULTING SERVICES | 6 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 4 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 4 | 03/21/2026 |
| JM ZONING, LLC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SPRING SCAFFOLDING LLC | General Contractor | 16 | 07/08/2026 |
| RENNON CONSTRUCTION CORP | General Contractor | 6 | 07/08/2026 |
| BUILTECH ASSOCIATES INC | General Contractor | 5 | 07/08/2026 |
| INFINITY KITCHEN & BATH I | General Contractor | 4 | 07/08/2026 |
| RUGOVA GROUP LLC | Plumbing | 3 | 07/08/2026 |
| I & H CONSTRUCTION LLC | General Contractor | 3 | 07/08/2026 |
| MOMENTAS INC | General Contractor | 2 | 07/08/2026 |
| FQE ELECTRIC LLC | Electrical | 2 | 03/22/2026 |
| MARATHON MECHANICAL LLC | Plumbing | 2 | 07/08/2026 |
| WINDHAM RESTORATION CORP | General Contractor | 2 | 03/21/2026 |
| AA CAPRI CONSTRUCTION | General Contractor | 2 | 07/08/2026 |
| 2A MECHANICAL, INC | General Contractor | 1 | 07/08/2026 |
| VERTEX ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| AQUEDUCT MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| GANIC PLUMBING & HTG INC | Plumbing | 1 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| AQUEDUCT MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| DESIGN2M LLC | General Contractor | 1 | 07/08/2026 |
| DORIA SCAFFOLDING LLC | General Contractor | 1 | 07/08/2026 |
| E.M.P. FIRE SPRINKLER LLC | Fire Protection | 1 | 07/08/2026 |
| ORION CONSTRUCTION & PAINTING | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HAMANN ENGINEERING, PLLC | 4949 | 1 | 02/05/2026 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 09/16/2025 |
| SKYLINE RIGGING | 7880 | 1 | 08/21/2024 |
| O'ROURKE ENGINEERING, LLC | 5873 | 6 | 02/28/2024 |
| EUGENE KHANANOV ARCHITECT | 2816 | 1 | 10/31/2023 |
| PSI AGENCY INC. | 254 | 7 | 08/08/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | AA CAPRI CONSTRUCTION | 06/24/2026 |
| DOB NOW | General Construction | Signed-off | AA CAPRI CONSTRUCTION | 04/08/2026 |
| DOB NOW | Plumbing | Signed-off | ORBIT PLBG & HTG INC | 03/26/2026 |
| DOB NOW | General Construction | Signed-off | ORION CONSTRUCTION & PAIN | 03/06/2026 |
| DOB NOW | Plumbing | Signed-off | GANIC PLUMBING & HTG INC | 03/05/2026 |
| DOB NOW | Mechanical Systems | Signed-off | MOMENTAS INC | 01/09/2026 |
| DOB NOW | General Construction | Signed-off | MOMENTAS INC | 10/24/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | DORIA SCAFFOLDING | 06/10/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | WINDHAM RESTORATION CORP | 04/01/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | DORIA, INC | 08/21/2024 |
| DOB NOW | Plumbing | Permit Issued | RUGOVA GROUP LLC | 07/24/2024 |
| DOB NOW | General Construction | Signed-off | DESIGN2M LLC | 03/01/2024 |
| DOB NOW | General Construction | Signed-off | INFINITY KITCHEN & BATH I | 01/22/2024 |
| DOB NOW | General Construction | Signed-off | INFINITY KITCHEN & BATH I | 12/20/2023 |
| DOB NOW | Sprinklers | Signed-off | AQUEDUCT MECHANICAL CORP | 08/11/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BUILTECH ASSOCIATES | 08/02/2023 |
| DOB NOW | General Construction | Signed-off | BUILTECH ASSOCIATES | 08/02/2023 |
| DOB NOW | Plumbing | Signed-off | AQUEDUCT MECHANICAL CORP | 08/01/2023 |
| DOB NOW | Plumbing | Permit Issued | RUGOVA GROUP LLC | 12/30/2022 |
| DOB NOW | Plumbing | Permit Issued | MARATHON MECHANICAL LLC | 07/15/2022 |
| DOB NOW | Mechanical Systems | Signed-off | 2A MECHANICAL, INC | 06/23/2022 |
| DOB NOW | Plumbing | Permit Issued | RUGOVA GROUP LLC | 06/22/2022 |
| DOB NOW | General Construction | Signed-off | I H CONSTRUCTION | 06/21/2022 |
| DOB NOW | Plumbing | Permit Issued | MARATHON MECHANICAL LLC | 06/14/2022 |
| DOB NOW | Sprinklers | Signed-off | E.M.P. FIRE SPRINKLER LLC | 06/09/2022 |
| DOB NOW | General Construction | Signed-off | I H CONSTRUCTION | 05/19/2022 |
| DOB NOW | General Construction | Signed-off | BUILTECH ASSOCIATES | 01/04/2022 |
| DOB NOW | General Construction | Signed-off | BUILTECH ASSOCIATES | 09/16/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 03/03/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 03/02/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 12/20/2019 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 12/16/2019 |
| DOB NOW | Supported Scaffold | Signed-off | RENNON CONSTRUCTION CORP | 12/11/2019 |
| DOB NOW | Construction Fence | Signed-off | RENNON CONSTRUCTION CORP | 10/15/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | RENNON CONSTRUCTION CORP | 10/15/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 12/27/2018 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 12/26/2018 |
| DOB NOW | Supported Scaffold | Signed-off | RENNON CONSTRUCTION CORP | 11/02/2018 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 10/12/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 09/05/2018 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/16/2025 | Signed-off | MOMENTAS INC | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/09/2026 | Signed-off | GANIC PLUMBING & HTG INC | Gas, Water/Sanitary |
| 08/04/2023 | Permit Issued | RUGOVA GROUP LLC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2026 | Complete | DELTA PHASE ELEC'L CORP. | General Wiring |
| 08/06/2025 | Complete | S.E. ELECTL CONTNG CORP | — |
| 05/19/2024 | Complete | ATTRACTIVE LIGHTING ELECL | General Wiring |
| 04/18/2024 | Complete | VERTEX ELECTRIC CORP. | — |
| 01/10/2024 | Complete | SHUIR ELEC'L CONTR'S CORP | General Wiring |
| 08/14/2023 | Complete | JUMPER ELECTRIC CORP | — |
| 08/07/2023 | Complete | ETECH ELECTRICAL LLC | General Wiring |
| 05/15/2023 | Complete | HILINE ELECT & DATA CORP | General Wiring |
| 05/11/2023 | Cancelled | HILINE ELECT & DATA CORP | General Wiring |
| 01/03/2023 | Complete | FQE ELECTRIC LLC | General Wiring |
| 07/07/2022 | Permit Issued | SAFETECH ELECL CONTNG COR | General Wiring |
| 06/14/2022 | Complete | HILINE ELECT & DATA CORP | — |
| 06/08/2022 | Complete | MAGNA ELECTRIC CORP | General Wiring |
| 03/31/2022 | Complete | FQE ELECTRIC LLC | General Wiring |
| 01/03/2022 | Complete | FQE ELECTRIC LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2018 | — | — | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2025 | Signed-off | MOMENTAS INC | Tenant Protection Plan 72 Hour |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2026 | — | — | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/21/2026 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 07/15/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/08/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/03/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/03/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/17/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/08/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 10/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/25/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/09/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/23/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/15/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 04/11/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/28/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/13/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/31/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/07/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/01/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/01/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/21/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/21/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/17/2026 | Energy Code Compliance Inspections | ENDA DONAGHER | progress |
| 07/17/2026 | Lighting in dwelling units | ENDA DONAGHER | energy_progress |
| 07/17/2026 | Final | ENDA DONAGHER | progress |
| 04/30/2026 | Final | Violeta Fiorino Schwartz | progress |
| 04/07/2026 | Final | Violeta Fiorino Schwartz | progress |
| 08/05/2025 | Exterior lighting power | William Ryan | energy_progress |
| 08/05/2025 | Lighting controls | William Ryan | energy_progress |
| 08/05/2025 | Interior lighting power | William Ryan | energy_progress |
| 08/05/2025 | Lighting in dwelling units | William Ryan | energy_progress |
| 07/14/2025 | HVAC-R and service water heating equipment | William Ryan | energy_progress |
| 07/14/2025 | HVAC-R and service water piping design and insulation | William Ryan | energy_progress |
| 07/14/2025 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 07/14/2025 | Tenant Protection Plan Compliance | William Ryan | special |
| 07/14/2025 | Mechanical Systems | William Ryan | special |
| 07/14/2025 | Final | William Ryan | progress |
| 07/14/2025 | HVAC-R and service water heating system controls | William Ryan | energy_progress |
| 03/04/2024 | Fire-Resistant Penetrations and Joints | BRIAN O'ROURKE | special |
| 03/04/2024 | Mechanical Systems | BRIAN O'ROURKE | special |
| 03/04/2024 | Final | Jeremy Latterman | progress |
| 03/04/2024 | HVAC-R and service water piping design and insulation | BRIAN O'ROURKE | energy_progress |
| 03/04/2024 | HVAC-R and service water heating system controls | BRIAN O'ROURKE | energy_progress |
| 03/04/2024 | HVAC-R and service water heating equipment | BRIAN O'ROURKE | energy_progress |
| 01/10/2024 | Sprinkler Systems | BRIAN O'ROURKE | special |
| 12/21/2023 | Final | Susan Matheson | progress |
| 12/21/2023 | Lighting in dwelling units | Susan Matheson | energy_progress |