← Back
Elevator cooperative
234 8 AVENUE
MANHATTAN · BIN 1014098
💬 Discuss this project
1960Year Built
7Stories
D4Building Class
C1-6AZoning
12,888 sfGross Floor Area
12Units
Rent Stabilized3 Open Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: ZADA REALTY LLC · 1,836 sf lot · 7.02 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralGeneral
Roof3p · 1 filing · 6 docs
Floor 12p · 2 filings · 12 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ZADAS REALTY LLC4204/09/2026
ZADA REALTY LLC NEJAT MGM103/22/2026
GLS ENTERPRISES103/22/2026
DELI103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GAD ASHOORI PE605/20/2025
KMB DESIGN GROUP, LLC202/16/2023
BAILEYS ENGINEERING PC102/20/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SITE SAFETY BSD603/21/2026
CONSTRUCTION PERMIT SERVICES203/21/2026
AE DESIGN SOLUTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
POWERS BRIDGING & SCAFFOLDINGGeneral Contractor307/08/2026
NICHOLAS LEONEElectrical203/21/2026
FM95 NYScaffold207/08/2026
CHETRAM, RISHIRAMElectrical103/21/2026
TRISTRUX LLCGeneral Contractor107/08/2026
YAFE MEOD CORPGeneral Contractor104/09/2026
YOUNG CHOEElectrical103/21/2026
FINTAN MURRAYElectrical103/21/2026
QUINTANA, DAVIDElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CL ENGINEERING P.C.6781104/02/2025
KMB DESIGN GROUP, LLC513202/16/2023
Building Lifecycle
All (110)Filed (9)Permit Issued (6)Signed Off (1)Facade (FISP) (15)Violation (60)Objection (16)Special Inspection (3)
05/27/2026
Violation issued (HPD, closed)
C
05/27/2026
Violation issued (HPD, closed)
C
05/27/2026
Violation issued (HPD, closed)
A
04/29/2026
Violation issued (HPD, closed)
B
06/09/2025
Objection resolved — Addressed
06/09/2025
Objection resolved — Addressed
06/09/2025
Objection resolved — Addressed
06/09/2025
Objection resolved — Addressed
06/06/2025
Objection raised — Other
06/06/2025
Objection raised — Admin
06/06/2025
Objection resolved — Addressed
06/06/2025
Objection raised — Scope
06/06/2025
Objection resolved — Addressed
06/06/2025
Objection raised — Other
06/06/2025
Objection raised — Other
06/06/2025
Objection raised — Zoning
05/20/2025
Filed — Alteration
REMOVAL OF ILLUMINATED BUSINESS SIGN"HIGH SOCIETY" IN FRONT OF THE STORE FACING 8TH AVE. ADDRESS ECB & DOB VIOLATIONS. AND INSTALL NEW SIGN AS PER ATTACHED REVISED PLAN.
M01201925-P1
05/20/2025
Filed — Alteration
REMOVAL OF ILLUMINATED BUSINESS SIGN"HIGH SOCIETY" IN FRONT OF THE STORE FACING W 22ND ST. ADDRESS ECB & DOB VIOLATIONS. AND INSTALL NEW SIGN AS PER ATTACHED REVISED PLAN.
M01201758-P1
05/12/2025
Permit issued — Sign
M01201925-I1-SG
05/09/2025
Permit issued — General Construction
M01201959-I1-GC
05/06/2025
Filed — Alteration
GENERAL CARPENTRY WORK TO REMOVE PARTITIONS, RAISED FLOOR AND ADDRESS VIOLATIONS. REMOVE FULL STOP WORK ORDER. FENCE & PLUMBING WORK UNDER SEPARATE APPLICATION. NO CHANGE IN OCCUPANCY OR EGRESS.
M01201959-S1
05/06/2025
Permit issued — Sign
M01201758-I1-SG
04/02/2025
Filed — Alteration
GENERAL CARPENTRY WORK TO REMOVE PARTITIONS, RAISED FLOOR AND ADDRESS VIOLATIONS. REMOVE FULL STOP WORK ORDER. FENCE & PLUMBING WORK UNDER SEPARATE APPLICATION. NO CHANGE IN OCCUPANCY OR EGRESS.
M01201959-I1
03/28/2025
Filed — Alteration
REMOVAL OF ILLUMINATED BUSINESS SIGN"HIGH SOCIETY" IN FRONT OF THE STORE FACING 8TH AVE. ADDRESS ECB & DOB VIOLATIONS. AND INSTALL NEW SIGN AS PER ATTACHED REVISED PLAN.
M01201925-I1
03/28/2025
Filed — Alteration
REMOVAL OF ILLUMINATED BUSINESS SIGN"HIGH SOCIETY" IN FRONT OF THE STORE FACING W 22ND ST. ADDRESS ECB & DOB VIOLATIONS. AND INSTALL NEW SIGN AS PER ATTACHED REVISED PLAN.
M01201758-I1
03/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHRISTIAN LOZADA
03/27/2025
Special inspection requirement — Tenant Protection Plan Compliance
CHRISTIAN LOZADA
03/27/2025
Special inspection requirement — Final
Andrew Inga
02/19/2025
Violation issued (HPD, closed)
C
02/19/2025
Violation issued (HPD, closed)
C
05/17/2024
Cycle 9 facade report signed — SWARMP
02/14/2024
Cycle 9 facade report submitted
02/09/2024
Cycle 9 facade inspection completed
10/04/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/31/2023
Violation issued (ECB, closed)
Construction
03/20/2023
Signed off — Alteration
Installation of new Dish site including the installation of 3 new sectors with 6 RRH units, 1 new GPS unit, and 1 new equipment cabinets on steel platform on roof. Related conduit run from cellar to OSP to roof. All in conformance with TPPN 5/98.
M08000686-I1
03/01/2023
Objection resolved — Addressed
02/27/2023
Objection resolved — Addressed
02/23/2023
Objection raised — Zoning
02/23/2023
Objection raised — Scope
02/16/2023
Filed — Alteration
Installation of new Dish site including the installation of 3 new sectors with 6 RRH units, 1 new GPS unit, and 1 new equipment cabinets on steel platform on roof. Related conduit run from cellar to OSP to roof. All in conformance with TPPN 5/98.
M08000686-P1
10/28/2022
Permit issued — Antenna
M08000686-I1-AN
09/28/2022
Filed — Alteration
Installation of new Dish site including the installation of 3 new sectors with 6 RRH units, 1 new GPS unit, and 1 new equipment cabinets on steel platform on roof. Related conduit run from cellar to OSP to roof. All in conformance with TPPN 5/98.
M08000686-I1
05/17/2022
Violation issued (ECB, closed)
Construction
09/11/2020
Violation issued (HPD, closed)
A
09/11/2020
Violation issued (HPD, closed)
A
09/11/2020
Violation issued (HPD, closed)
A
09/11/2020
Violation issued (HPD, closed)
B
09/11/2020
Violation issued (HPD, closed)
A
09/11/2020
Violation issued (HPD, closed)
A
02/20/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/08/2019
Violation issued (HPD, closed)
C
03/08/2019
Violation issued (HPD, closed)
C
03/08/2019
Violation issued (HPD, closed)
C
10/20/2018
Cycle 8 facade report signed — SAFE
09/17/2018
Cycle 8 facade inspection completed
09/02/2018
Violation issued (HPD, closed)
B
07/12/2018
Violation issued (ECB, closed)
Construction
06/06/2018
Violation issued (ECB, closed)
Construction
06/04/2018
Cycle 8 facade report submitted
Latest 60 of 110 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSignPermit IssuedRED HOOK SIGN AND ELECT05/12/2025
DOB NOWGeneral ConstructionPermit IssuedYAFE MEOD CORP05/09/2025
DOB NOWSignPermit IssuedRED HOOK SIGN AND ELECT05/06/2025
DOB NOWAntennaSigned-offTRISTRUX LLC10/28/2022
DOB NOWSidewalk ShedPermit IssuedPOWERS BRIDGING & SCAFFOL03/29/2018
DOB NOWSidewalk ShedPermit IssuedPOWERS BRIDGING & SCAFFOL02/20/2018
BISOTISSUEDSDG CONSTRUCTION INC04/12/2018
BISEQISSUEDPROSPECT BUILDERS CORP05/01/2006
BISOTISSUEDPROSPECT BUILDERS CORP05/01/2006
BISEQISSUEDCLARK & WILKINS INDUSTRIES, INC.10/29/2002
BISPLISSUEDWADE PLUMBING & HEATING07/17/2002
BIS—ISSUEDR AND S CONSTRUCTION CORP05/29/2002
BISOTISSUEDSPACE SIGN CO INC11/05/2001
BISOTISSUEDSPACE SIGN CO., INC.11/05/2001
2 projects · most recent 08/22/2023
FiledStatusContractorScope
08/22/2023CompleteLEONE ELECTRIC CO. LLC15 meters, 1 new_meters
02/12/2018CompleteOPTIMAL ELECTRIC, INC—
2 projects · most recent 05/06/2025
Fence Sidewalk Shed
FiledStatusContractorScope
05/06/2025Permit IssuedYAFE MEOD CORPFence
02/20/2018Permit IssuedPOWERS BRIDGING & SCAFFOLSidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
03/27/2025Fire-Resistant Penetrations and JointsCHRISTIAN LOZADAspecial
03/27/2025Tenant Protection Plan ComplianceCHRISTIAN LOZADAspecial
03/27/2025FinalAndrew Ingaprogress
▾Documents — 39 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
09/06/2026M00017274-I1Request digital key ↗
08/31/2026M08000686-I1Request digital key ↗
08/23/2026M01201959-S1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits2
▸BISWORK PERMIT APPLICATION1
04/12/2018123275883Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
12/20/2017123275883Open ↗
▸Seals & Professional Certifications14
▸DOB NOWDPL-1: Design Professional Seal & Signature9
09/06/2026M00017274-I1Open ↗
08/23/2026M01201959-S1Open ↗
08/23/2026M01201959-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
05/11/2018123275883Open ↗
12/20/2017123275883Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/23/2026M01201959-I1Open ↗
08/23/2026M01201959-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/23/2026M01201959-I1Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
12/20/2017123275883Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/23/2026M01201959-I1Open ↗
08/13/2026M08000686-I1Open ↗
08/13/2026M08000686-P1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
12/20/2017123275883Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
05/11/2018123275883Open ↗
12/20/2017123275883Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/11/2018123275883Open ↗
▸Inspections & Test Reports1
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
05/11/2018123275883Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/11/2018123275883Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
05/11/2018123275883Open ↗
12/20/2017123275883Open ↗
▸Filing & Intake Forms2
▸BISBOROUGH INTAKE FORM1
05/11/2018123275883Open ↗
▸BISEFILING COVER SHEET1
12/20/2017123275883Open ↗