← Back
Office with commercial, 7-19 stories
235 Park Ave So
235 PARK AVENUE SOUTH · Gramercy · BIN 1017906
💬 Discuss this project
1921Year Built
12Stories
O6Building Class
C6-4AZoning
67,376 sfGross Floor Area
13Units
LL97 Covered15 Open Violations 13 unresolved · 2 paperwork only ▸FISP: SWARMP
Office with commercial, 7-19 stories · Owner of record: 235 PARK AVENUE SOUTH, LLC · 6,900 sf lot · 9.76 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
Floor 102p · 2 filings · 7 docs
Floor 9
Floor 8
Floor 7
Floor 6Under Construction6p · 2 filings · 13 docs
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Cellar1p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
235 PARK AVE SOUTH ASS17809/13/2026
CEPRINE CONSTR INC303/22/2026
235 PARK AVENUE ASSOCIATES703/22/2026
235 PARK AVE SO. ASSOC203/22/2026
CAFE IGUANA INC.103/22/2026
JL 235 PARK AVE SOUTH, LL103/22/2026
CAPITAL PROPERTIES203/21/2026
1431 BROADWAY ASSOCIATES, LLC203/21/2026
CEPRINE SCAFFOLDING SERVICES203/21/2026
PALIN ENTERPRISES103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SYNERGY BUILDING CONSULTANTS203/21/2026
STUDIO JS2 ARCHITECT1403/21/2026
KIT MIDDLETON ARCHITECT P C1203/21/2026
JENNY FLORES EXPEDITING103/21/2026
HLZAE103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEPRINE CONSTRUCTION INCGeneral Contractor508/13/2026
GMA AIR COOLING & HEATINGGeneral Contractor507/08/2026
VINCENT DURYEEElectrical403/21/2026
CROSS CONSULTING INCGeneral Contractor307/08/2026
S TERRANOVA LLCGeneral Contractor303/21/2026
CERINA GENERAL CONTR INCGeneral Contractor308/20/2026
PACE PLUMBING CORPPlumbing207/08/2026
PACE PLUMBING CORPFire Protection207/08/2026
I.U.O.EElectrical203/21/2026
VILLAGE P & H NY INCFire Protection207/08/2026
STRUCTURE VENTURES LLCGeneral Contractor207/08/2026
PIETANZA, JOSEPHElectrical203/21/2026
ROSARIO, EDWINElectrical203/21/2026
VILLAGE P & H NY INCPlumbing107/08/2026
JAVIER VALERA ACEROElectrical103/21/2026
MAYO, EUGENEElectrical103/21/2026
REEM PLBG & HTG CORPFire Protection107/08/2026
ELEGANT MECHANICAL INCGeneral Contractor104/09/2026
ALEXANDER EUGENEElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GROUP-S LLC5216506/26/2025
HOWARD L ZIMMERMAN ARCHIT1712109/17/2024
RYAN SPECIAL ENGINEERING2018403/22/2023
Building Lifecycle
All (158)Filed (20)Permit Issued (25)Signed Off (4)Facade (FISP) (13)Violation (60)Inspection (10)Objection (6)Special Inspection (20)
08/19/2026
Permit issued — General Construction
M01082326-I1-GC
08/18/2026
Permit issued — Suspended Scaffold
M01271446-I1-SC
08/12/2026
Permit issued — Sidewalk Shed
M01269798-I1-SH
06/30/2026
Filed — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01421326-I1
06/30/2026
Permit issued — Supported Scaffold
M01421326-I1-SF
04/08/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/07/2026
Permit issued — Sprinklers
M01198970-I1-EW-SP
03/12/2026
Permit issued — General Construction
M01319693-I1-GC
02/13/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
02/09/2026
Permit issued — General Construction
M01319693-I1-GC
12/16/2025
Filed — Alteration
M01319693-I1
08/25/2025
Permit issued — Suspended Scaffold
M01271446-I1-SC
08/20/2025
Filed — Alteration
M01269798-I1
08/20/2025
Permit issued — Sidewalk Shed
M01269798-I1-SH
08/18/2025
Permit issued — General Construction
M01082326-I1-GC
08/14/2025
Filed — Alteration
M01271446-I1
08/01/2025
Permit issued — Mechanical Systems
M01189005-S1-MS
06/26/2025
Filed — Alteration
Addition and removal of ductwork. No new HVAC equipment
M01189005-S1
06/26/2025
Filed — Alteration
INSTALLATION OF NEW SPRINKLERS AT NEW OFFICES.
M01198970-I1
05/27/2025
Permit issued — General Construction
M01189005-I1-GC
04/04/2025
Filed — Alteration
Addition and removal of ductwork. No new HVAC equipment
M01189005-I1
03/21/2025
Special inspection requirement — Sprinkler Systems
MICHAEL SCORRANO
03/19/2025
Special inspection requirement — Final
MICHAEL SCORRANO
03/19/2025
Special inspection requirement — Mechanical Systems
MICHAEL SCORRANO
03/03/2025
Special inspection requirement — Final
James Schelkle
09/17/2024
Filed — Alteration
REPAIRS TO BUILDING AS CITED IN THE 9TH CYCLE FISP REPORT. REPAIRS TO INCLUDE LINTEL REPLACEMENT, BRICK REPLACEMENT, WINDOWSILL REPAIR AND REPLACEMENT, AND SEALANT REPLACEMENT. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
M01082326-I1
07/03/2024
Violation issued (ECB, open)
Construction
06/09/2023
Signed off — Alteration
INTERIOR RENOVATION OF AN EXISTING OFFICE SPACE. NO CHANGE IN USE, OCCUPANCY OR EGRESS. PLUMBING WORK FILED SEPARATELY UNDER APP M00687288-I1
M00720499-I1
05/30/2023
Signed off — Alteration
INSTALLATION OF FOUR (4) HEADS, REPLACEMENT OF TWENTY-TWO (22) HEADS AND RELOCATION OF TWELVE (12) SPRINKLER HEADS.
M00687288-I1
05/30/2023
Signed off — Alteration
INSTALLATION OF FOUR (4) HEADS, REPLACEMENT OF TWENTY-TWO (22) HEADS AND RELOCATION OF TWELVE (12) SPRINKLER HEADS.
M00687288-S1
05/23/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/23/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/23/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/04/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
04/21/2023
Violation issued (ECB, open)
Construction
03/22/2023
Filed — Alteration
INSTALLATION OF FOUR (4) HEADS, REPLACEMENT OF TWENTY-TWO (22) HEADS AND RELOCATION OF TWELVE (12) SPRINKLER HEADS.
M00687288-P2
03/13/2023
Special inspection requirement — Sprinkler Systems
William Ryan
03/10/2023
Permit issued — Sprinklers
M00687288-S1-EW-SP
02/28/2023
Special inspection requirement — Lighting controls
William Ryan
02/28/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
William Ryan
02/28/2023
Special inspection requirement — Energy Code Compliance Inspections
William Ryan
02/28/2023
Special inspection requirement — Final
Christopher Middleton
02/28/2023
Special inspection requirement — Interior lighting power
William Ryan
02/22/2023
Filed — Alteration
INTERIOR RENOVATION OF AN EXISTING OFFICE SPACE. NO CHANGE IN USE, OCCUPANCY OR EGRESS. PLUMBING WORK FILED SEPARATELY UNDER APP M00687288-I1
M00720499-P1
02/16/2023
Filed — Alteration
INSTALLATION OF FOUR (4) HEADS, REPLACEMENT OF TWENTY-TWO (22) HEADS AND RELOCATION OF TWELVE (12) SPRINKLER HEADS.
M00687288-P1
01/31/2023
Signed off — Alteration
Addition and removal of ductwork. No new HVAC equipment
M00684135-I1
01/27/2023
Filed — Alteration
Addition and removal of ductwork. No new HVAC equipment
M00684135-P1
01/07/2023
Permit issued — General Construction
M00720499-I1-GC
12/09/2022
Permit issued — Sprinklers
M00687288-S1-EW-SP
10/21/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/18/2022
Permit issued — Plumbing
M00687288-I1-PL
08/17/2022
Permit issued — General Construction
M00684135-I1-GC
06/27/2022
Filed — Alteration
INSTALLATION OF FOUR (4) HEADS, REPLACEMENT OF TWENTY-TWO (22) HEADS AND RELOCATION OF TWELVE (12) SPRINKLER HEADS.
M00687288-S1
06/23/2022
Permit issued — General Construction
M00720499-I1-GC
06/13/2022
Special inspection requirement — Final
James Schelkle
06/08/2022
Filed — Alteration
Addition and removal of ductwork. No new HVAC equipment
M00684135-S1
06/01/2022
Objection resolved — Addressed
06/01/2022
Objection resolved — Addressed
06/01/2022
Objection resolved — Addressed
05/23/2022
Objection raised — Scope
Latest 60 of 158 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedCERINA GENERAL CONTR INC08/19/2026
DOB NOWSuspended ScaffoldPermit IssuedCERINA GENERAL CONTR. INC08/18/2026
DOB NOWSidewalk ShedPermit IssuedCEPRINE CONSTRUCTION INC08/12/2026
DOB NOWSupported ScaffoldPermit IssuedCEPRINE CONSTRUCTION INC06/30/2026
DOB NOWSprinklersPermit IssuedREEM PLBG & HTG CORP04/07/2026
DOB NOWGeneral ConstructionSigned-offCHARLES TROIANO03/12/2026
DOB NOWGeneral ConstructionSigned-offCHARLES TROIANO02/09/2026
DOB NOWSuspended ScaffoldPermit IssuedCERINA GENERAL CONTR. INC08/25/2025
DOB NOWSidewalk ShedPermit IssuedCEPRINE CONSTRUCTION INC08/20/2025
DOB NOWGeneral ConstructionPermit IssuedCERINA GENERAL CONTR INC08/18/2025
DOB NOWMechanical SystemsPermit IssuedELEGANT MECHANICAL INC08/01/2025
DOB NOWGeneral ConstructionPermit IssuedCHARLES TROIANO05/27/2025
DOB NOWSprinklersSigned-offVILLAGE P & H NY INC03/10/2023
DOB NOWGeneral ConstructionSigned-offSTRUCTURE VENTURES LLC01/07/2023
DOB NOWSprinklersSigned-offVILLAGE P & H NY INC12/09/2022
DOB NOWPlumbingSigned-offVILLAGE P & H NY INC10/18/2022
DOB NOWGeneral ConstructionSigned-offS TERRANOVA LLC08/17/2022
DOB NOWGeneral ConstructionSigned-offSTRUCTURE VENTURES LLC06/23/2022
DOB NOWSprinklersPermit IssuedMANENGEERING BUREAU, INC07/13/2021
DOB NOWSprinklersPermit IssuedPACE PLUMBING CORP07/13/2021
DOB NOWMechanical SystemsPermit IssuedGMA AIR COOLING & HEATING06/23/2021
DOB NOWMechanical SystemsPermit IssuedGMA AIR COOLING & HEATING05/03/2021
DOB NOWSprinklersPermit IssuedMANENGEERING BUREAU, INC01/03/2020
DOB NOWPlumbingPermit IssuedPACE PLUMBING CORP01/02/2020
DOB NOWMechanical SystemsPermit IssuedGMA AIR COOLING & HEATING12/23/2019
BISOTISSUEDL.I. NEWMAN CONSULTING LL09/29/2021
BISOTISSUEDFIVE TOWN NEON SIGN CO.,I12/20/2016
BISOTISSUEDFIVE TOWN NEON SIGN CO.,I12/20/2016
BISOTISSUEDFIVE TOWN NEON SIGN CO.,I12/01/2016
BISFPISSUEDFIREMASTERS11/15/2016
BISOTISSUEDSHAWMUT WOODWORKING & SUPPLY10/27/2016
BISOTISSUEDSHAWMUT WOODWORKING & SUPPLY10/27/2016
BISEQISSUEDSHAWMUT WOODWORKING & SUPPLY10/27/2016
BISMHISSUEDSHAWMUT WOODWORKING & SUPPLY10/27/2016
BISOTISSUEDSHAWMUT WOODWORKING & SUPPLY10/24/2016
BISMHISSUEDSHAWMUT WOODWORKING & SUPPLY10/24/2016
BISOTISSUEDSHAWMUT WOODWORKING & SUPPLY10/24/2016
BISSPISSUEDALLSTATE SPRINKLER LLC07/01/2016
BISPLISSUEDTRISTATE PLBG SVCS CORP06/01/2016
BISMHISSUEDSHAWMUT WOODWORKING & SUPPLY05/24/2016
+ 35 more permits on file
1 project · most recent 12/06/2019
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
12/06/2019Permit IssuedGMA AIR COOLING & HEATINGAir Conditioning Systems
Cooling
United Cool Air VA10G3AHA-A 4,000 CFM · Rooftop Unit ×2
1 project · most recent 06/26/2025
FiledStatusContractorScope
06/26/2025Permit IssuedREEM PLBG & HTG CORP19 heads
1 project · most recent 06/26/2025
FiledStatusContractorScope
06/26/2025———
7 projects · most recent 03/26/2026
General Wiring
FiledStatusContractorScope
03/26/2026CompleteRAL-BAR ELECTRIC INC—
10/16/2025Permit IssuedHIGH QUALITY ELEC.OF NYC—
08/29/2024Permit IssuedJAM ELECTRICAL CORP—
04/08/2022CompleteBP ELECTRIC & COOLING INCGeneral Wiring
12/06/2021CompleteCRESCO ELECTRICAL CORPGeneral Wiring
04/14/2021Permit IssuedKENNETH FISK ELECTRIC COR—
01/03/2020CompletePOWER SURGE ELECTRIC, INCGeneral Wiring
1 project · most recent 06/30/2026
Scaffold
FiledStatusContractorScope
06/30/2026Permit IssuedCEPRINE CONSTRUCTION INCScaffold
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
04/08/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/13/2026Fail-Final General Construction Non-Directive 14FailView ↗
05/23/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/23/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/23/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/04/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/21/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/20/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/27/2021Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/22/2021Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
03/21/2025Sprinkler SystemsMICHAEL SCORRANOspecial
03/19/2025FinalMICHAEL SCORRANOprogress
03/19/2025Mechanical SystemsMICHAEL SCORRANOspecial
03/03/2025FinalJames Schelkleprogress
03/13/2023Sprinkler SystemsWilliam Ryanspecial
02/28/2023Lighting controlsWilliam Ryanenergy_progress
02/28/2023Fire-Resistant Penetrations and JointsWilliam Ryanspecial
02/28/2023Energy Code Compliance InspectionsWilliam Ryanprogress
02/28/2023FinalChristopher Middletonprogress
02/28/2023Interior lighting powerWilliam Ryanenergy_progress
06/13/2022FinalJames Schelkleprogress
04/05/2022FinalMICHAEL SCORRANOprogress
04/05/2022Mechanical SystemsMICHAEL SCORRANOspecial
03/11/2020Final—progress
03/11/2020Maintenance information—energy_progress
03/11/2020HVAC insulation and sealing —energy_progress
03/11/2020HVAC and service water heating equipment —energy_progress
03/11/2020HVAC and service water heating system controls —energy_progress
03/11/2020Mechanical Systems—special
03/11/2020Energy Code Compliance Inspections—progress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Union SquarecafeRestaurant / Food Service—
Project M00331140 Alteration · Approved · 03/19/2020
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 696 on file (BIS + DOB NOW)
▸Plans & Drawings21
▸DOB NOWPlans/Sketch17
09/02/2026M00684135-S1Request digital key ↗
09/02/2026M00684135-P1Request digital key ↗
09/02/2026M00684135-I1Request digital key ↗
Showing 3 of 17 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/05/2026M00331140-I1Request digital key ↗
08/15/2026M00270425-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/05/2026M00270526-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/05/2026M00270526-I1Request digital key ↗
▸Applications & Permits138
▸BISWORK PERMIT APPLICATION72
09/29/2021140878511Open ↗
12/13/2019140878511Open ↗
12/27/2016122970053Open ↗
Showing 3 of 72 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION63
11/07/2025122889632Open ↗
03/29/2023140878511Open ↗
03/09/2023140878511Open ↗
Showing 3 of 63 on file for this type
▸BISPLACE OF ASSEMBLY3
10/23/2025122889632Open ↗
10/22/2025122889632Open ↗
09/26/2016122889632Open ↗
▸Seals & Professional Certifications211
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION65
10/17/2017122970044Open ↗
10/17/2017122929411Open ↗
10/17/2017122970053Open ↗
Showing 3 of 65 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM29
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 29 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST28
12/20/2016122970053Open ↗
12/20/2016122970044Open ↗
11/17/2016122929411Open ↗
Showing 3 of 28 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT25
11/22/2019140878511Open ↗
12/20/2016122970053Open ↗
12/20/2016122970044Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature20
09/05/2026M00270425-I1Open ↗
09/05/2026M00270526-I1Open ↗
09/02/2026M00684135-S1Open ↗
Showing 3 of 20 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION14
11/22/2019140878511Open ↗
11/02/2016140570816Open ↗
10/25/2016140567410Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY14
11/22/2019140878511Open ↗
11/02/2016140570816Open ↗
10/25/2016140567410Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/03/2026M00720499-I1Open ↗
09/03/2026M00720499-I1Open ↗
09/03/2026M00720499-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/23/2026M01198970-I1Open ↗
09/03/2026M00720499-I1Open ↗
09/01/2026M01189005-S1Open ↗
Showing 3 of 5 on file for this type
▸BISProfessional and Owner Certification (POC3)3
05/26/2016122737244Open ↗
05/26/2016122737244Open ↗
05/26/2016122737244Open ↗
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment33
▸BISSCHEDULE B - PLUMBING12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE10
12/15/2016122737244Open ↗
12/14/2016122737244Open ↗
11/29/2016122716551Open ↗
Showing 3 of 10 on file for this type
▸BISSELF-CERT PLUMBING NOTICE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
03/27/2017140351651Open ↗
12/20/2016140351651Open ↗
Showing 2 of 3 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
08/22/2017122815882Open ↗
12/08/2016140570816Open ↗
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
08/08/2016122815882Open ↗
▸Safety & Tenant Protection2
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos57
▸BISASBESTOS: CERTIFICATION (DEP ACP5)25
11/22/2019140878511Open ↗
12/20/2016122970053Open ↗
12/20/2016122970044Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report17
09/05/2026M00270425-I1Open ↗
09/05/2026M00270526-I1Open ↗
09/02/2026M00684135-S1Open ↗
Showing 3 of 17 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance22
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
05/22/2017140351651Open ↗
Showing 1 of 3 on file for this type
▸BISNYCECC ANALYSIS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
05/22/2017140351651Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026M00720499-I1Open ↗
▸Inspections & Test Reports20
▸BISTECHNICAL REPORT: RESPONSIBILITY13
12/13/2019140878511Open ↗
11/22/2019140878511Open ↗
Showing 2 of 13 on file for this type
▸BIS2008 CODE TR1 REQUIRED2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
06/01/2016122737244Open ↗
05/31/2016122737244Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
06/01/2016122737244Open ↗
05/31/2016122737244Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs46
▸BISADMINISTRATIVE OBJECTIONS18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST14
03/31/2023140878511Open ↗
10/17/2017122970044Open ↗
10/17/2017122929411Open ↗
Showing 3 of 14 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION8
05/22/2017140351651Open ↗
Showing 1 of 8 on file for this type
▸BISLANDMARKS APPROVAL3
05/26/2016122737244Open ↗
03/22/2016122709239Open ↗
Showing 2 of 3 on file for this type
▸BISFINAL1
03/29/2023140878511Open ↗
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSUPERSEDING LETTER1
10/01/2021140878511Open ↗
▸Cost, Insurance & Ownership55
▸BISCOST AFFIDAVIT51
11/22/2019140878511Open ↗
10/17/2017122970044Open ↗
10/17/2017122929411Open ↗
Showing 3 of 51 on file for this type
▸BISCIVIL PENALTY AFFADAVIT/REQUEST3
11/10/2016140570816Open ↗
Showing 1 of 3 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
03/31/2023140878511Open ↗
▸Filing & Intake Forms73
▸BISEFILING COVER SHEET33
12/20/2016122970053Open ↗
12/20/2016122970044Open ↗
11/17/2016122929411Open ↗
Showing 3 of 33 on file for this type
▸BISADDITIONAL INFORMATION23
11/07/2025122889632Open ↗
03/29/2023140878511Open ↗
04/29/2022140878511Open ↗
Showing 3 of 23 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET14
11/22/2019140878511Open ↗
11/02/2016140570816Open ↗
10/25/2016140567410Open ↗
Showing 3 of 14 on file for this type
▸BISBOROUGH INTAKE FORM3
10/17/2017122970044Open ↗
10/17/2017122929411Open ↗
10/17/2017122970053Open ↗
▸Other Documents18
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION7
11/02/2016140570816Open ↗
11/02/2016140570816Open ↗
10/25/2016140567410Open ↗
Showing 3 of 7 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸DOB NOWProof of Historic Building2
09/02/2026M00684135-P1Open ↗
09/02/2026M00684135-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M01271446-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01271446-I1Open ↗