Locations of Work
Architecture
Floor 11 filing · 20 docs
Cellar1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CITYSQUASH706/02/2026
▾Design Consultants (Architect / Engineer of Record)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ANDAMIO SCAFFOLDING LLCGeneral Contractor306/02/2026
LOCUS CONSTRUCTION INCGeneral Contractor206/02/2026
F.S. WORKS INCFire Protection106/02/2026
JEM CONTRACTING CORPGeneral Contractor106/02/2026
P.H. WORKS INCPlumbing106/02/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUREAU VERITAS NA69021603/11/2026
AECOM USA, INC.4580102/18/2025
BLUE SKY DESIGN, INC.1908110/26/2022
Building Lifecycle
All (185)Filed (26)Permit Issued (28)Signed Off (13)Inspection (9)Objection (79)Special Inspection (30)
07/07/2026
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-I1
03/23/2026
Special inspection requirement — Fenestration areas
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Energy Code Compliance Inspections
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Interior lighting power
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Fenestration air leakage
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Air barrier — testing
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Maintenance information
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Exterior lighting power
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Electrical motors and elevators
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Insulation placement and R values
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Lighting controls
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Fire-Resistance Rated Construction
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Air barrier - visual inspection
IBRAHIM MOURAD
03/23/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
IBRAHIM MOURAD
03/11/2026
Filed — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-A1
03/11/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Fenestration air leakage
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Insulation placement and R values
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Interior lighting power
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Air barrier — testing
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Electrical motors and elevators
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Fire-Resistance Rated Construction
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Air barrier - visual inspection
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Energy Code Compliance Inspections
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Lighting controls
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Fenestration areas
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Exterior lighting power
IBRAHIM MOURAD
03/11/2026
Special inspection requirement — Maintenance information
IBRAHIM MOURAD
02/25/2026
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-S1
01/06/2026
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-S4
01/06/2026
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-S7
12/18/2025
Signed off — Alteration
X00586346-I1
12/16/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
11/28/2025
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
11/21/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/20/2025
Permit issued — Curb Cut
X00795971-S7-CC
11/19/2025
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-S5
11/19/2025
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-S3
11/19/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
X00868193-I1
11/19/2025
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-S6
11/19/2025
Signed off — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-S2
10/22/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/25/2025
Objection raised — Admin
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/22/2025
Filed — No Work
X01290676-I1
09/04/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
09/03/2025
Permit issued — Mechanical Systems
X00795971-S4-MS
09/02/2025
Objection raised — Admin
08/29/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/26/2025
Filed — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-P9
08/21/2025
Objection resolved — Addressed
08/15/2025
Objection raised — Scope
08/08/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
X00900289-I1
08/06/2025
Filed — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-P8
08/06/2025
Filed — New Building
FOUNDATION AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB # X00795971
X00795971-P7
Latest 60 of 185 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offLOCUS CONSTRUCTION INC11/20/2025
DOB NOWMechanical SystemsSigned-offLOCUS CONSTRUCTION INC09/03/2025
DOB NOWPlumbingSigned-offP.H. WORKS INC08/01/2025
DOB NOWGeneral ConstructionPermit IssuedLOCUS CONSTRUCTION INC07/16/2025
DOB NOWSprinklersSigned-offF.S. WORKS INC07/08/2025
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC06/26/2025
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC06/26/2025
DOB NOWConstruction FenceSigned-offANDAMIO SCAFFOLDING LLC04/24/2025
DOB NOWSupported ScaffoldSigned-offJEM CONTRACTING CORP12/12/2024
DOB NOWMechanical SystemsSigned-offLOCUS CONSTRUCTION INC08/29/2024
DOB NOWPlumbingSigned-offP.H. WORKS INC08/02/2024
DOB NOWStructuralSigned-offLOCUS CONSTRUCTION INC07/15/2024
DOB NOWGeneral ConstructionPermit IssuedLOCUS CONSTRUCTION INC07/15/2024
DOB NOWSprinklersSigned-offF.S. WORKS INC07/11/2024
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC07/08/2024
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC07/08/2024
DOB NOWConstruction FenceSigned-offANDAMIO SCAFFOLDING LLC04/29/2024
DOB NOWSupported ScaffoldSigned-offJEM CONTRACTING CORP04/29/2024
DOB NOWMechanical SystemsSigned-offLOCUS CONSTRUCTION INC08/31/2023
DOB NOWPlumbingSigned-offP.H. WORKS INC08/07/2023
DOB NOWSupport of ExcavationSigned-offLOCUS CONSTRUCTION INC07/24/2023
DOB NOWStructuralSigned-offLOCUS CONSTRUCTION INC07/24/2023
DOB NOWFoundationSigned-offLOCUS CONSTRUCTION INC07/24/2023
DOB NOWGeneral ConstructionPermit IssuedLOCUS CONSTRUCTION INC07/22/2023
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC07/12/2023
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC07/12/2023
DOB NOWConstruction FenceSigned-offANDAMIO SCAFFOLDING LLC05/05/2023
DOB NOWConstruction FenceSigned-offGREEN CASTLE A MGMT CORP10/01/2021
1 project · most recent 03/11/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
03/11/2026Signed-offLOCUS CONSTRUCTION INCHeating and Air Conditioning Systems
Heat / Cool
Lg ARUM168BTE5 180,000 BTU · Vrf Outdoor ×4
ARUM216BTE5 230,000 BTU · Vrf Outdoor ×2
1 project · most recent 03/11/2026
Sprinkler System
FiledStatusContractorScope
03/11/2026Signed-offF.S. WORKS INCSprinkler System
1 project · most recent 03/11/2026
Storm Water/Sanitary
FiledStatusContractorScope
03/11/2026Signed-offP.H. WORKS INCStorm, Water/Sanitary
3 projects · most recent 02/03/2025
General Wiring
FiledStatusContractorScope
02/03/2025CompleteS & D ELECTRIC NY CORPGeneral Wiring
09/04/2024CompleteKWONG MING ELECTRIC INC—
09/27/2023CompleteBOROWIDE ELECT'L CONTR'S—
1 project · most recent 03/11/2026
Steel Concrete Masonry
FiledStatusContractorScope
03/11/2026Signed-offLOCUS CONSTRUCTION INCSteel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
12/16/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
11/28/2025Fail-Final Curb Cut Non-Directive 14FailView ↗
11/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/22/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/04/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/29/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/05/2024Pass-Final PL - UndergroundPassView ↗
12/19/2023Pass-Final PL - UndergroundPassView ↗
11/01/2023Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 93
DateRequirementInspectorRole
03/23/2026Fire-Resistance Rated ConstructionIBRAHIM MOURADprogress
03/23/2026Air barrier - visual inspectionIBRAHIM MOURADenergy_progress
03/23/2026Energy Code Compliance InspectionsIBRAHIM MOURADprogress
03/23/2026Fire-Resistant Penetrations and JointsIBRAHIM MOURADspecial
03/23/2026Exterior Insulation and Finish Systems (EIFS)IBRAHIM MOURADspecial
03/23/2026Fenestration and door U-factor and product ratingsIBRAHIM MOURADenergy_progress
03/23/2026Air barrier — testing IBRAHIM MOURADenergy_progress
03/23/2026Maintenance informationIBRAHIM MOURADenergy_progress
03/23/2026Fenestration air leakageIBRAHIM MOURADenergy_progress
03/23/2026Fenestration areasIBRAHIM MOURADenergy_progress
03/23/2026Insulation placement and R valuesIBRAHIM MOURADenergy_progress
03/23/2026Electrical motors and elevatorsIBRAHIM MOURADenergy_progress
03/23/2026Exterior lighting powerIBRAHIM MOURADenergy_progress
03/23/2026Interior lighting powerIBRAHIM MOURADenergy_progress
03/23/2026Lighting controlsIBRAHIM MOURADenergy_progress
03/11/2026Lighting controlsIBRAHIM MOURADenergy_progress
03/11/2026Maintenance informationIBRAHIM MOURADenergy_progress
03/11/2026Electrical motors and elevatorsIBRAHIM MOURADenergy_progress
03/11/2026Insulation placement and R valuesIBRAHIM MOURADenergy_progress
03/11/2026Fenestration and door U-factor and product ratingsIBRAHIM MOURADenergy_progress
03/11/2026Fenestration air leakageIBRAHIM MOURADenergy_progress
03/11/2026Air barrier — testing IBRAHIM MOURADenergy_progress
03/11/2026Interior lighting powerIBRAHIM MOURADenergy_progress
03/11/2026Fenestration areasIBRAHIM MOURADenergy_progress
03/11/2026Exterior lighting powerIBRAHIM MOURADenergy_progress
Latest 25 of 93.
▾Documents — 97 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch25
08/25/2026X00586346-I1Request digital key ↗
08/23/2026X00900309-I1Request digital key ↗
08/23/2026X00900309-P1Request digital key ↗
Showing 3 of 25 on file for this type
▸Seals & Professional Certifications64
▸DOB NOWDPL-1: Design Professional Seal & Signature26
08/25/2026X00586346-I1Open ↗
08/23/2026X00900309-I1Open ↗
08/23/2026X00900309-P1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature20
09/20/2026X00795971-A1Open ↗
09/20/2026X00795971-A1Open ↗
09/01/2026X00795971-P1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWProgress Inspector Seal & Signature18
09/20/2026X00795971-A1Open ↗
09/20/2026X00795971-A1Open ↗
09/20/2026X00795971-A1Open ↗
Showing 3 of 18 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWStreet Trees Site Plan1
08/18/2026X00795971-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/18/2026X00795971-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/18/2026X00795971-I1Open ↗
▸Other Documents5
▸DOB NOWProperty Ownership Certification3
08/18/2026X00795971-A1Open ↗
08/18/2026X00795971-P6Open ↗
08/18/2026X00795971-I1Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll1
08/13/2026X01290676-I1Open ↗
▸DOB NOWFinal Survey1
08/18/2026X00795971-I1Open ↗