← Back
Elevator apt, semi-fireproof with stores
Maven Mott Haven
2413 THIRD AVENUE · BIN 2130650
💬 Discuss this project
2021Year Built
27Stories
D7Building Class
M1-3/R8Zoning
218,695 sfGross Floor Area
201Units
LL97 CoveredRent Stabilized20 Open Violations ▸
Elevator apt, semi-fireproof with stores · Owner of record: RXR 2413 THIRD OWNER LLC · 27,730 sf lot · 7.89 FAR built · Flood zone AE
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneralOther
Roof6p · 5 filings · 20 docs
Bulkhead2p · 2 filings · 20 docs
Floor 321p · 1 filing · 20 docs
Floor 31
Floor 30
Floor 29
Floor 28
Floor 275p · 3 filings · 20 docs
Floor 265p · 3 filings · 20 docs
Floor 255p · 3 filings · 20 docs
Floor 244p · 2 filings · 20 docs
Floor 234p · 3 filings · 20 docs
Floor 225p · 3 filings · 20 docs
Floor 215p · 3 filings · 20 docs
Floor 205p · 3 filings · 20 docs
Floor 195p · 3 filings · 20 docs
Floor 185p · 3 filings · 20 docs
Floor 175p · 2 filings · 20 docs
Floor 164p · 2 filings · 20 docs
Floor 158p · 3 filings · 20 docs
Floor 148p · 3 filings · 20 docs
Floor 137p · 2 filings · 20 docs
Floor 127p · 3 filings · 20 docs
Floor 117p · 3 filings · 20 docs
Floor 105p · 2 filings · 20 docs
Floor 96p · 3 filings · 20 docs
Floor 85p · 2 filings · 20 docs
Floor 77p · 2 filings · 20 docs
Floor 610p · 4 filings · 20 docs
Floor 57p · 4 filings · 20 docs
Floor 48p · 4 filings · 20 docs
Floor 38p · 4 filings · 20 docs
Floor 27p · 4 filings · 20 docs
Floor 14p · 4 filings · 20 docs
Cellar6p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PLATINUM SERVICES NY2607/08/2026
RXR4907/08/2026
SKYLINE SCAFFOLDING GROUP607/08/2026
AO CONSULTING AND DRAFTING607/08/2026
VIK XS SERVICES603/22/2026
RXR 2413 THIRD OWNER603/22/2026
LRC CONSTRUCTION2503/22/2026
ASF CONSTRUCTION EXCAVA203/22/2026
STATE CONSTRUCTING CORP N103/22/2026
STATE CONTRACTING CORP NY203/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAM CONSULTANTS, INC.4803/21/2026
A1 EXPEDITING SERVICE803/21/2026
GREEN STUDIO203/21/2026
A1 EXPEDITING SERVICE CORP.203/21/2026
KD DESIGNS203/21/2026
AO CONSULTING AND DRAFTING203/21/2026
VS CREATIVE DESIGNS103/21/2026
Rigid Structural Design, LLC303/21/2026
JME BUILDING CONSULTING, LLC103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LRC CONSTRUCTION LLCGeneral Contractor1907/08/2026
PLATINUM SERVICES NY LLCGeneral Contractor1707/08/2026
TT MECHANICAL CORPPlumbing707/08/2026
VIK XS SERVICES INCGeneral Contractor507/08/2026
SKYLINE SCAFFOLDING GROUPGeneral Contractor407/08/2026
TTM GROUP CORPFire Protection207/08/2026
JIMENEZ LUISElectrical203/21/2026
LUIS JIMENEZElectrical203/21/2026
BUA, JAMESElectrical103/21/2026
ENDRULAT, EDMUNDElectrical103/21/2026
PLUMB-IT MECHANICAL INCPlumbing107/08/2026
JOE ZAGOElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ATLANTIC ENGINEERINGLABOR13812401/04/2024
ATLAS ATC ENGINEERING INC8011201/04/2024
DESIMONE CONSULTING ENGIN5942606/02/2022
JZN ENGINEERING, PC.363207/23/2021
H & O ENGINEERING, DPC5595102/03/2021
Building Lifecycle
All (286)Filed (42)Permit Issued (33)Signed Off (22)Violation (60)Inspection (19)Objection (80)Special Inspection (30)
05/11/2026
Violation issued (HPD, open)
A
03/04/2026
Violation issued (HPD, open)
B
03/04/2026
Violation issued (HPD, open)
B
03/04/2026
Violation issued (HPD, open)
B
03/04/2026
Violation issued (HPD, open)
B
03/04/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
A
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
03/01/2026
Violation issued (HPD, open)
B
06/24/2025
Signed off — Alteration
FILING FOR PLUMING WORK OF 2 COMPARTMENT SINK AND EMPLOYEE SINK. NO CHANGE IN USE EGRESS OR OCCUPANCY.
X01168433-I1
05/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/02/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/22/2025
Permit issued — Plumbing
X01168433-I1-PL
01/17/2025
Filed — Alteration
FILING FOR PLUMING WORK OF 2 COMPARTMENT SINK AND EMPLOYEE SINK. NO CHANGE IN USE EGRESS OR OCCUPANCY.
X01168433-I1
09/11/2024
Signed off — Alteration
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR A SALES OFFICE INCLUDING MODEL APARTMENTS PURSUANT TO SECTION AC-28-111 AND BUILDINGS BULLETIN 2010-002.APPLICATION FILED IN CONJUNCTION WITH NB# 210181202.
X00444808-I1
02/16/2024
Signed off — Alteration
INSTALLATION OF SPRINKLER / STANDPIPE SYSTEM IN CONJUNCTION WITH NB CONSTRUCTION #210181202.
X00520180-I1
01/18/2024
Special inspection requirement — Standpipe Systems
Christopher O'Malley
01/18/2024
Special inspection requirement — Sprinkler Systems
Christopher O'Malley
01/08/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
GIORGI KHARDZEISHVILI
01/04/2024
Filed — Alteration
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR A SALES OFFICE INCLUDING MODEL APARTMENTS PURSUANT TO SECTION AC-28-111 AND BUILDINGS BULLETIN 2010-002.APPLICATION FILED IN CONJUNCTION WITH NB# 210181202.
X00444808-P5
01/04/2024
Filed — Alteration
INSTALLATION OF SPRINKLER / STANDPIPE SYSTEM IN CONJUNCTION WITH NB CONSTRUCTION #210181202.
X00520180-P3
12/14/2023
Special inspection requirement — Sprinkler Systems
Christopher O'Malley
12/14/2023
Special inspection requirement — Standpipe Systems
Christopher O'Malley
12/14/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
GIORGI KHARDZEISHVILI
11/16/2023
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
X00783411-I1
11/14/2023
Signed off — Alteration
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR A SALES OFFICE INCLUDING MODEL APARTMENTS PURSUANT TO SECTION AC-28-111 AND BUILDINGS BULLETIN 2010-002.APPLICATION FILED IN CONJUNCTION WITH NB# 210181202.
X00444808-S1
11/14/2023
Signed off — Alteration
Mechanical work filed in conjunction with NB Construction (210181202). NYCECC Compliance reviewed under related NB application filed in BIS.
X00444794-I1
11/09/2023
Signed off — Alteration
Installation of 8' curb cut with 1.5" splays on each side (12.0 total) on East 134th St. Application filed in conjunction with NB# 210181202, BPP# 240301758 & CC# X00667165.
X00667167-I1
11/09/2023
Signed off — Alteration
Installation of 12.8' curb cut with 1.5" splays on each side (15.8' total) on Third Avenue. Application filed in conjunction with NB# 210181202, BPP# 240301758 & CC# X00667167.
X00667165-I1
11/08/2023
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
11/01/2023
Signed off — Alteration
Suspended Hanging Scaffold Installation as per plans filed herewith. No change in use, egress or occupancy
X00856522-I1
11/01/2023
Signed off — Alteration
X00676759-I1
10/30/2023
Signed off — Alteration
INSTALLATION OF CONSTRUCTION FENCE AS PER PLANS. CONSTRUCTION FENCE SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE. NO CHANGE INUSE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00559174-I1
10/30/2023
Signed off — Alteration
INSTALLATION OF 300 psf SIDEWALK SHED, OVERHEAD PROTECTION AND ROOF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE. NO CHANGE INUSE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00613266-I1
10/10/2023
Inspection — Pass-Final SD - Fire Pump
Pass
View inspection ↗
09/27/2023
Filed — Alteration
INSTALLATION OF SPRINKLER / STANDPIPE SYSTEM IN CONJUNCTION WITH NB CONSTRUCTION #210181202.
X00520180-P2
09/27/2023
Permit issued — Sidewalk Shed
X00613266-I1-SH
09/15/2023
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
09/08/2023
Violation issued (ECB, closed)
Construction
08/28/2023
Signed off — Alteration
Structural work filed in conjunction with NB construction - NB# 210181202.
X00444867-I1
08/23/2023
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
08/22/2023
Signed off — Alteration
INSTALLATION OF 6000 LB DUAL CAR PERSONNEL/MATERIAL HOIST AS PER PLANS DURING CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00660504-I1
08/15/2023
Signed off — Alteration
Support of Excavation work in conjunction with soil remediation.
X00521884-I1
08/15/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
08/14/2023
Inspection — Pass-Final SP - More than 10 Requested Floors
Pass
View inspection ↗
08/09/2023
Signed off — Alteration
X00598217-I1
08/08/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/04/2023
Special inspection requirement — Mechanical Systems
Christopher O'Malley
08/04/2023
Special inspection requirement — Heating Systems
Christopher O'Malley
Latest 60 of 286 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offJVR PLBG AND HEATING INC01/22/2025
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC09/27/2023
DOB NOWGeneral ConstructionSigned-offLRC CONSTRUCTION LLC07/24/2023
DOB NOWCurb CutSigned-offLRC CONSTRUCTION LLC06/30/2023
DOB NOWCurb CutSigned-offLRC CONSTRUCTION LLC06/30/2023
DOB NOWConstruction FenceSigned-offPLATINUM SERVICES NY LLC06/13/2023
DOB NOWSupported ScaffoldSigned-offSKYLINE SCAFFOLDING GROUP05/12/2023
DOB NOWProtection and Mechanical MethodsSigned-offVIK XS SERVICES INC04/18/2023
DOB NOWProtection and Mechanical MethodsSigned-offVIK XS SERVICES INC04/07/2023
DOB NOWStructuralSigned-offLRC CONSTRUCTION LLC02/24/2023
DOB NOWStandpipeSigned-offTTM GROUP CORP02/06/2023
DOB NOWProtection and Mechanical MethodsSigned-offPLATINUM SERVICES NY LLC01/04/2023
DOB NOWStandpipeSigned-offTT MECHANICAL CORP12/16/2022
DOB NOWStandpipeSigned-offTTM GROUP CORP12/15/2022
DOB NOWPlumbingSigned-offTT MECHANICAL CORP12/07/2022
DOB NOWStandpipeSigned-offTT MECHANICAL CORP12/06/2022
DOB NOWMechanical SystemsSigned-offLRC CONSTRUCTION LLC11/15/2022
DOB NOWSupport of ExcavationSigned-offLRC CONSTRUCTION LLC11/09/2022
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC09/30/2022
DOB NOWSupported ScaffoldSigned-offSKYLINE SCAFFOLDING GROUP08/01/2022
DOB NOWConstruction FenceSigned-offPLATINUM SERVICES NY LLC07/05/2022
DOB NOWProtection and Mechanical MethodsSigned-offVIK XS SERVICES INC06/30/2022
DOB NOWStructuralSigned-offLRC CONSTRUCTION LLC02/10/2022
DOB NOWProtection and Mechanical MethodsSigned-offPLATINUM SERVICES NY LLC01/11/2022
DOB NOWStandpipeSigned-offTT MECHANICAL CORP12/08/2021
DOB NOWPlumbingSigned-offTT MECHANICAL CORP12/03/2021
DOB NOWMechanical SystemsSigned-offLRC CONSTRUCTION LLC11/05/2021
DOB NOWStructuralSigned-offLRC CONSTRUCTION LLC11/03/2021
DOB NOWPlumbingSigned-offTT MECHANICAL CORP11/03/2021
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC10/25/2021
DOB NOWSupport of ExcavationSigned-offLRC CONSTRUCTION LLC10/25/2021
DOB NOWStandpipeSigned-offTT MECHANICAL CORP10/14/2021
DOB NOWSupport of ExcavationSigned-offLRC CONSTRUCTION LLC07/22/2021
BIS—ISSUEDLRC CONSTRUCTION LLC05/25/2023
BIS—ISSUEDLRC CONSTRUCTION LLC05/25/2023
BIS—ISSUEDLRC CONSTRUCTION LLC05/25/2023
BISOTISSUEDLRC CONSTRUCTION LLC05/01/2023
BIS—ISSUEDLRC CONSTRUCTION LLC02/13/2023
BIS—ISSUEDLRC CONSTRUCTION LLC02/13/2023
BIS—ISSUEDLRC CONSTRUCTION LLC02/13/2023
+ 15 more permits on file
10 projects · most recent 06/15/2026
General Wiring
FiledStatusContractorScope
06/15/2026CompleteS. J. ELECTRIC INC.1 meters, 1 new_meters
06/15/2026CompleteS. J. ELECTRIC INC.General Wiring
06/15/2026CompleteS. J. ELECTRIC INC.General Wiring
06/15/2026CompleteS. J. ELECTRIC INC.General Wiring
03/17/2026CompleteLIPPOLIS ELECTRIC, INC.General Wiring
09/14/2022CompleteLIPPOLIS ELECTRIC, INC.1 meters, 1 new_meters
06/24/2022CompleteCORPORATE ELEC. GROUP INC—
06/24/2022CompleteCORPORATE ELEC. GROUP INC—
01/13/2022CompleteILLUMINOUS ELECTRIC CORP.—
10/27/2021CompleteILLUMINOUS ELECTRIC CORP.—
▾Field Inspections (DOB CAP) — 19
DateTypeResultReport
05/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/02/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/08/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
10/10/2023Pass-Final SD - Fire PumpPassView ↗
09/15/2023Pass-Final SP - Up to 9 Requested FloorsPassView ↗
08/23/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
08/15/2023Pass-Final General Construction Non-Directive 14PassView ↗
08/14/2023Pass-Final SP - More than 10 Requested FloorsPassView ↗
08/08/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/03/2023Pass-Final SP - More than 10 Requested FloorsPassView ↗
05/24/2023Pass-Final SD - Fire PumpPassView ↗
05/17/2023Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
05/24/2022Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
05/24/2022Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
03/16/2022Pass-Final PL - UndergroundPassView ↗
02/24/2022Pass-Final PL - UndergroundPassView ↗
02/11/2022Pass-Final PL - UndergroundPassView ↗
01/28/2022Pass-Final PL - UndergroundPassView ↗
12/20/2021Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 80
DateRequirementInspectorRole
01/18/2024Sprinkler SystemsChristopher O'Malleyspecial
01/18/2024Standpipe SystemsChristopher O'Malleyspecial
01/08/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationGIORGI KHARDZEISHVILIspecial
12/14/2023Sprinkler SystemsChristopher O'Malleyspecial
12/14/2023Standpipe SystemsChristopher O'Malleyspecial
12/14/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationGIORGI KHARDZEISHVILIspecial
08/04/2023Heating SystemsChristopher O'Malleyspecial
08/04/2023FinalChristopher O'Malleyprogress
08/04/2023Chimneys and ventsChristopher O'Malleyspecial
08/04/2023Emergency and Standby Power Systems (Generator)Christopher O'Malleyspecial
08/04/2023Mechanical SystemsChristopher O'Malleyspecial
08/04/2023Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Christopher O'Malleyspecial
08/01/2023Emergency and Standby Power Systems (Generator)Christopher O'Malleyspecial
08/01/2023Heating SystemsChristopher O'Malleyspecial
08/01/2023FinalChristopher O'Malleyprogress
08/01/2023Mechanical SystemsChristopher O'Malleyspecial
08/01/2023Chimneys and ventsChristopher O'Malleyspecial
08/01/2023Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Christopher O'Malleyspecial
06/28/2023MasonryChristopher O'Malleyspecial
06/28/2023Concrete - Cast-In-PlaceStephen DeSimonespecial
06/28/2023Structural Steel - WeldingChristopher O'Malleyspecial
06/28/2023FinalChristopher O'Malleyprogress
06/28/2023Structural Steel - High Strength BoltingChristopher O'Malleyspecial
06/28/2023Structural Steel - DetailsChristopher O'Malleyspecial
06/28/2023Post-installed AnchorsChristopher O'Malleyspecial
Latest 25 of 80.
▾Documents — 365 on file (BIS + DOB NOW)
▸Plans & Drawings44
▸DOB NOWPlans/Sketch26
08/25/2026X00497495-I1Request digital key ↗
08/25/2026X00498425-I1Request digital key ↗
08/25/2026X00498422-I1Request digital key ↗
Showing 3 of 26 on file for this type
▸DOB NOWPlans/Sketch - Plumbing6
08/21/2026X00444808-P3Request digital key ↗
08/21/2026X00444808-P2Request digital key ↗
08/21/2026X00444808-P5Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Structural6
08/24/2026X00444867-P1Request digital key ↗
08/24/2026X00444867-P5Request digital key ↗
08/24/2026X00444867-P3Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
08/22/2026X00444794-P2Request digital key ↗
08/22/2026X00444794-I1Request digital key ↗
08/15/2026X00444794-P1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction2
08/25/2026X00459371-I1Request digital key ↗
08/25/2026X00461781-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/26/2026X00385043-I1Request digital key ↗
▸Applications & Permits18
▸BISPLAN / WORK APPROVAL APPLICATION14
09/20/2023240346960Open ↗
09/19/2023240346960Open ↗
08/24/2023240346960Open ↗
Showing 3 of 14 on file for this type
▸BISWORK PERMIT APPLICATION3
05/01/2023240346960Open ↗
02/24/2021240301384Open ↗
12/18/2020240297852Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
10/28/2022240301758Open ↗
▸Zoning, Tax Lot & Property Records10
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
08/09/2022240301758Open ↗
08/16/2021210181202Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/16/2021210181202Open ↗
▸BISFLOOD ZONE COMPLIANCE1
06/14/2023210181202Open ↗
▸BISVERIFY TAX LOT1
04/09/2024210181202Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
08/16/2021210181202Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
04/08/2024210181202Open ↗
▸BISZONING DIAGRAM1
08/16/2021210181202Open ↗
▸BISFLOOD ZONE DESIGN CERTIFICATION1
04/24/2023240346960Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
08/16/2021210181202Open ↗
▸Seals & Professional Certifications121
▸DOB NOWSpecial Inspector Seal & Signature54
09/23/2026X00520180-I1Open ↗
09/21/2026X00444867-P1Open ↗
09/21/2026X00444867-P1Open ↗
Showing 3 of 54 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature42
08/26/2026X00385043-I1Open ↗
08/25/2026X00459371-I1Open ↗
08/25/2026X00461781-I1Open ↗
Showing 3 of 42 on file for this type
▸DOB NOWProgress Inspector Seal & Signature14
09/21/2026X00444867-P1Open ↗
09/19/2026X00444867-P3Open ↗
09/01/2026X00444794-P2Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
04/24/2023240346960Open ↗
02/23/2021240301384Open ↗
12/16/2020240297852Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
04/24/2023240346960Open ↗
02/23/2021240301384Open ↗
12/16/2020240297852Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
04/24/2023240346960Open ↗
02/23/2021240301384Open ↗
12/16/2020240297852Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
09/17/2021210181202Open ↗
09/17/2021210181202Open ↗
▸Trade Schedules & Equipment3
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
09/29/2023210181202Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
05/03/2024210181202Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
08/16/2021210181202Open ↗
▸Safety & Tenant Protection2
▸BISBPP: STREET TREES SITE PLAN1
10/28/2022240301758Open ↗
▸BISSTREET TREE CHECKLIST1
10/28/2022240301758Open ↗
▸Environmental & Asbestos37
▸DOB NOWOER: Notice to Proceed22
08/24/2026X00444867-I1Open ↗
08/24/2026X00444867-P3Open ↗
08/24/2026X00444867-P2Open ↗
Showing 3 of 22 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION5
09/16/2024240346960Open ↗
02/22/2024240301758Open ↗
08/08/2023210181202Open ↗
Showing 3 of 5 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED5
04/24/2023240346960Open ↗
08/09/2022240301758Open ↗
08/16/2021210181202Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWOER: Notice of Satisfaction4
08/22/2026X00444794-I1Open ↗
08/14/2026X00444808-I1Open ↗
08/13/2026X00521884-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/25/2026X00459371-I1Open ↗
▸Energy Compliance17
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
08/07/2023210181202Open ↗
06/27/2023210181202Open ↗
06/27/2023210181202Open ↗
Showing 3 of 4 on file for this type
▸BISPRELIMINARY COMMISSIONING REPORT CERTIFICATION3
06/10/2024210181202Open ↗
05/29/2024210181202Open ↗
05/29/2024210181202Open ↗
▸BISFENESTRATION AREAS1
07/27/2023210181202Open ↗
▸BISAIR SEALING AND INSULATION - TESTING1
07/24/2023210181202Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
07/27/2023210181202Open ↗
▸BISLIGHTING IN DWELLING UNITS1
09/14/2023210181202Open ↗
▸BISELECTRIC MOTORS1
07/24/2023210181202Open ↗
▸BISLIGHTING CONTROLS1
09/29/2023210181202Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/23/2023210181202Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
09/17/2021210181202Open ↗
▸BISELECTRICAL ENERGY CONSUMPTION1
08/04/2023210181202Open ↗
▸BISEXTERIOR LIGHTING POWER1
09/29/2023210181202Open ↗
▸Inspections & Test Reports28
▸BISTECHNICAL REPORT: RESPONSIBILITY17
03/25/2024210181202Open ↗
11/14/2023210181202Open ↗
08/04/2023210181202Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX4
09/17/2021210181202Open ↗
09/17/2021210181202Open ↗
09/17/2021210181202Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
07/18/2023210181202Open ↗
09/17/2021210181202Open ↗
08/30/2021210181202Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
03/31/2023210181202Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
04/25/2023240346960Open ↗
▸BISSOIL REPORT1
08/16/2021210181202Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
08/16/2021210181202Open ↗
▸Approvals, Objections & Sign-offs29
▸BISSUPERSEDING LETTER12
05/30/2023210181202Open ↗
05/30/2023210181202Open ↗
05/30/2023210181202Open ↗
Showing 3 of 12 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE7
02/26/2025210181202Open ↗
10/08/2024210181202Open ↗
11/24/2021210181202Open ↗
Showing 3 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
10/05/2021210181202Open ↗
10/05/2021210181202Open ↗
09/17/2021210181202Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
09/17/2024240346960Open ↗
09/17/2021240301384Open ↗
08/20/2021240297852Open ↗
▸BISNYS DEC TIDAL WETLANDS APPROVAL2
10/28/2022240301758Open ↗
08/30/2021210181202Open ↗
▸BISFINAL1
09/16/2024240346960Open ↗
▸Cost, Insurance & Ownership2
▸BISPROJECT-SPECIFIC GL INSURANCE2
10/28/2021210181202Open ↗
09/17/2021210181202Open ↗
▸Filing & Intake Forms22
▸BISADDITIONAL INFORMATION16
03/11/2025210181202Open ↗
09/20/2023240346960Open ↗
08/24/2023240346960Open ↗
Showing 3 of 16 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
04/24/2023240346960Open ↗
03/17/2021240301758Open ↗
02/23/2021240301384Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET1
10/30/2015220482902Open ↗
▸BISAI1 APPROVED ON 02.26.20251
03/11/2025210181202Open ↗
▸Other Documents16
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
10/28/2021210181202Open ↗
10/28/2021210181202Open ↗
08/16/2021210181202Open ↗
▸DOB NOWFlood Plan Emergency Temporary Flood Shields3
08/22/2026X00444794-P2Open ↗
08/22/2026X00444794-I1Open ↗
08/15/2026X00444794-P1Open ↗
▸BISNYS DEC TIDAL WETLANDS MAP2
10/28/2022240301758Open ↗
08/30/2021210181202Open ↗
▸BISVESTIBULES1
09/29/2023210181202Open ↗
▸BISMAINTENANCE INFORMATION1
07/24/2023210181202Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
07/27/2023210181202Open ↗
▸BISPLOT DIAGRAM1
08/16/2021210181202Open ↗
▸BISFEMA FORM (81-31): ELEVATION CERTIFICATE1
11/02/2023210181202Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026X00521884-I1Open ↗
▸DOB NOWLowest Floor Elevation Plan1
08/22/2026X00444794-I1Open ↗
▸DOB NOWFEMA Elevation Certificate (086-0-33)/Flood Proofing Certificate (086-0-34)1
08/22/2026X00444794-I1Open ↗