| Owner | Filings | Most Recent |
|---|---|---|
| ARCHSTONE BUILDERS | 6 | 07/08/2026 |
| RUSHITA | 23 | 03/22/2026 |
| VENUS CONSTRUCTION | 3 | 03/22/2026 |
| ACGC 242 LLC | 1 | 03/22/2026 |
| BERNSTERIN REAL ESTATE | 11 | 03/22/2026 |
| BRADLEY ASSOC. LLC C/O BE | 1 | 03/22/2026 |
| BEMNSTEIN REAL ESTATE | 1 | 03/22/2026 |
| FURCRAFT ASSOCIATES | 9 | 03/22/2026 |
| BERNSTEIN MANAGEMENT | 1 | 03/22/2026 |
| 150 HABERN LLC ET AL C/O BERNSTEIN REALTY | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/06/2015 | $117K | — | AASTHA LIMITED A BVI COMPANY → RUSHITA LLC | $1/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| THOMAS VELTRE P.E., P.C. | 2 | 08/17/2026 |
| DAVID CHAGNON ARCHITECTURAL DESIGN | 3 | 08/07/2026 |
| URBAN INTEGRATIONS | 11 | 04/01/2025 |
| ALL CITY ENGINEERING PC | 1 | 03/05/2024 |
| ELEMENTAL ARCHITECTURE LLC | 1 | 01/10/2024 |
| MQ CONSULTING | 6 | 12/19/2023 |
| ENTHINK ENGINEERS LLC | 2 | 11/23/2022 |
| WILLIAM LENART, ARCHITEC PLLC | 4 | 10/03/2022 |
| ZH ARCHITECTS | 1 | 09/01/2022 |
| A. CAPRIO ARCHITECT, PLLC | 1 | 07/26/2022 |
| CES ENGINEERING LLC | 4 | 09/09/2021 |
| NICHOLAS DERAMO ARCHITECT | 1 | 06/14/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| UNITED SAFETY CONSULTANTS | 10 | 03/21/2026 |
| PREEMPTIVE SOLUTIONS & CONSULTING L | 2 | 03/21/2026 |
| EA DESIGN GROUP | 28 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 5 | 03/21/2026 |
| METROPOLIS GROUP INC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANDAMIO SCAFFOLDING LLC | General Contractor | 29 | 07/08/2026 |
| RINNOVO CONSTRUCTION, LLC | General Contractor | 16 | 07/08/2026 |
| BRACE CONSTRUCTION LLC ** | General Contractor | 12 | 09/25/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 5 | 07/08/2026 |
| HIGHLINE CONSTRUCTION GR | General Contractor | 4 | 07/08/2026 |
| SAFEWAY INDUSTRIES INC | General Contractor | 3 | 03/21/2026 |
| HIGH BEAM ELECTRIC CORP. | Electrical | 3 | 03/22/2026 |
| REEM PLBG & HTG CORP | Plumbing | 3 | 08/21/2026 |
| ARCHSTONE BUILDERS LLC | General Contractor | 3 | 07/08/2026 |
| REEM PLBG & HTG CORP | Fire Protection | 2 | 07/08/2026 |
| SUPERIOR PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| FRAGNITO, G | Electrical | 1 | 03/21/2026 |
| GALLETTI, MICHAEL | Electrical | 1 | 03/21/2026 |
| TEAM ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| FORTE EXPRESS P & H INC | Fire Protection | 1 | 07/08/2026 |
| MOREAIR MECHANICAL SERVIC | General Contractor | 1 | 09/26/2026 |
| DONATO PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| DV PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| EMPIRE I ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| THOMAS VELTRE, P.E, P.C. | 459 | 13 | 08/17/2026 |
| PSI AGENCY INC. | 254 | 1 | 07/26/2022 |
| CES ENGINEERING LLC | 1277 | 5 | 09/09/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | MOREAIR MECHANICAL SERVIC | 09/25/2026 |
| DOB NOW | General Construction | Permit Issued | BRACE CONSTRUCTION LLC ** | 09/24/2026 |
| DOB NOW | Plumbing | Permit Issued | REEM PLBG & HTG CORP | 08/20/2026 |
| DOB NOW | General Construction | Permit Issued | BRACE CONSTRUCTION LLC ** | 08/11/2026 |
| DOB NOW | Plumbing | Permit Issued | REEM PLBG & HTG CORP | 07/07/2026 |
| DOB NOW | General Construction | Permit Issued | BRACE CONSTRUCTION LLC ** | 04/27/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | ANDAMIO SCAFFOLDING LLC | 04/01/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | ANDAMIO SCAFFOLDING LLC | 04/01/2026 |
| DOB NOW | General Construction | Permit Issued | BRACE CONSTRUCTION LLC ** | 02/23/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | ANDAMIO SCAFFOLDING LLC | 04/02/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | ANDAMIO SCAFFOLDING LLC | 04/02/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/09/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ANDAMIO SCAFFOLDING LLC | 07/29/2024 |
| DOB NOW | General Construction | Permit Issued | ARCHSTONE BUILDERS LLC | 06/12/2024 |
| DOB NOW | Sprinklers | Signed-off | REEM PLBG & HTG CORP | 04/19/2024 |
| DOB NOW | General Construction | Signed-off | BRACE CONSTRUCTION LLC ** | 02/23/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 01/22/2024 |
| DOB NOW | General Construction | Signed-off | RINNOVO CONSTRUCTION, LLC | 12/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | RINNOVO CONSTRUCTION, LLC | 12/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BRACE CONSTRUCTION LLC ** | 12/20/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ANDAMIO SCAFFOLDING LLC | 11/17/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/16/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/02/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/01/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 01/23/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ANDAMIO SCAFFOLDING LLC | 11/26/2022 |
| DOB NOW | Sprinklers | Permit Issued | REEM PLBG & HTG CORP | 11/10/2022 |
| DOB NOW | Plumbing | Permit Issued | REEM PLBG & HTG CORP | 11/10/2022 |
| DOB NOW | Mechanical Systems | Signed-off | RINNOVO CONSTRUCTION, LLC | 10/28/2022 |
| DOB NOW | General Construction | Signed-off | RINNOVO CONSTRUCTION, LLC | 10/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | BRACE CONSTRUCTION LLC ** | 10/20/2022 |
| DOB NOW | General Construction | Permit Issued | BRACE CONSTRUCTION LLC ** | 10/14/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/10/2022 |
| DOB NOW | General Construction | Permit Issued | ARCHSTONE BUILDERS LLC | 08/10/2022 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/10/2022 |
| DOB NOW | General Construction | Signed-off | SAFEWAY INDUSTRIES INC | 02/21/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 01/26/2022 |
| DOB NOW | Plumbing | Signed-off | DV PLUMBING INC | 11/22/2021 |
| DOB NOW | General Construction | Signed-off | RINNOVO CONSTRUCTION, LLC | 11/03/2021 |
| DOB NOW | General Construction | Signed-off | RINNOVO CONSTRUCTION, LLC | 11/03/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/18/2022 | Signed-off | BRACE CONSTRUCTION LLC ** | Associated Ducts and Piping, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/05/2024 | Signed-off | REEM PLBG & HTG CORP | — |
| 10/18/2022 | Permit Issued | REEM PLBG & HTG CORP | — |
| 06/11/2021 | Signed-off | FORTE EXPRESS P & H INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/18/2022 | Permit Issued | REEM PLBG & HTG CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/23/2026 | Permit Issued | EMPIRE I ELECTRICAL CORP | General Wiring |
| 11/13/2024 | Cancelled | TEAM ELECTRIC, INC | General Wiring |
| 07/03/2024 | Permit Issued | TEAM ELECTRIC, INC | General Wiring |
| 06/17/2024 | Permit Issued | EMPIRE I ELECTRICAL CORP | General Wiring |
| 06/27/2023 | Complete | CITYWIDE ELEC'L WIRING IN | General Wiring |
| 02/19/2023 | Complete | EMPIRE I ELECTRICAL CORP | General Wiring |
| 07/27/2021 | Permit Issued | ECO ELECTRICAL SERVCS LLC | General Wiring, Lighting |
| 04/17/2019 | Complete | PREMIER ELECTRIC, INC | General Wiring |
| 03/14/2019 | Complete | HIGH BEAM ELECTRIC CORP. | General Wiring |
| 09/11/2018 | Complete | EMPIRE 1 ELECTRICAL CORP | General Wiring |
| 01/04/2018 | Complete | PAUL VERARDI | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | Permit Issued | ANDAMIO SCAFFOLDING LLC | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/28/2025 | Fail-Final Antenna Withdrawal | Fail | View ↗ |
| 12/23/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/21/2024 | Pass-Final Antenna Withdrawal | Pass | View ↗ |
| 09/16/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/12/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/30/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/23/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/24/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/21/2021 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/15/2021 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/07/2021 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 09/20/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/13/2026 | Fire-Resistant Penetrations and Joints | Thomas Veltre | special |
| 08/06/2026 | Interior lighting power | Thomas Veltre | energy_progress |
| 08/06/2026 | Fire-Resistance Rated Construction | Thomas Veltre | progress |
| 08/06/2026 | Energy Code Compliance Inspections | Thomas Veltre | progress |
| 08/06/2026 | Fire-Resistant Penetrations and Joints | Thomas Veltre | special |
| 08/06/2026 | Lighting controls | Thomas Veltre | energy_progress |
| 07/21/2026 | Final | DAVID CHAGNON | progress |
| 04/22/2026 | Fire-Resistant Penetrations and Joints | Thomas Veltre | special |
| 04/13/2026 | Fire-Resistance Rated Construction | Thomas Veltre | progress |
| 04/13/2026 | Fire-Resistant Penetrations and Joints | Thomas Veltre | special |
| 04/07/2026 | Final | DAVID CHAGNON | progress |
| 04/07/2026 | Lighting controls | Thomas Veltre | energy_progress |
| 04/07/2026 | Interior lighting power | Thomas Veltre | energy_progress |
| 04/07/2026 | Energy Code Compliance Inspections | Thomas Veltre | progress |
| 02/12/2026 | Fire-Resistant Penetrations and Joints | Thomas Veltre | special |
| 01/14/2026 | Final | DAVID CHAGNON | progress |
| 02/23/2024 | Sprinkler Systems | Thomas Veltre | special |
| 02/23/2024 | Fire-Resistant Penetrations and Joints | Thomas Veltre | special |
| 10/18/2022 | Maintenance information | Thomas Veltre | energy_progress |
| 10/18/2022 | HVAC-R and service water piping design and insulation | Thomas Veltre | energy_progress |
| 10/18/2022 | Energy Code Compliance Inspections | Thomas Veltre | progress |
| 10/18/2022 | Duct leakage testing, insulation and design | Thomas Veltre | energy_progress |
| 10/18/2022 | HVAC-R and service water heating system controls | Thomas Veltre | energy_progress |
| 10/18/2022 | HVAC-R and service water heating equipment | Thomas Veltre | energy_progress |
| 09/28/2022 | Lighting controls | Thomas Veltre | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| The Drawing Room | Office | Floor 7 | Project M01434252 |
| Highline Construction Group | Office | Floor 9 | Project M00494591 |