| Owner | Filings | Most Recent |
|---|---|---|
| SKY BLU HOLDINGS | 61 | 07/08/2026 |
| RELIABLE ENTERPRISES | 17 | 03/22/2026 |
| RVMIM LLC | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/25/2022 | $5.0M | — | — → — | — not available |
| 05/13/2014 | $2.0M | — | 2481 CORTONA REALTY CO. INC. → SKY BLU HOLDINGS LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| MARIN ARCHITECTS, P.C. | 13 | 04/27/2026 |
| CHOSEN MEP, CORP. | 4 | 06/05/2024 |
| STEE LLC | 1 | 03/29/2024 |
| MJE PROFESSIONAL SERVICES | 1 | 01/09/2024 |
| ETTINGER ENGINEERING ASSOCIATES | 7 | 12/28/2023 |
| ENTHINK ENGINEERS LLC | 7 | 05/12/2023 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 1 | 11/01/2022 |
| SOUTH BAY ENGINEERING PLLC | 1 | 02/02/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 23 | 03/21/2026 |
| CANAS SOLUTIONS | 10 | 03/21/2026 |
| EXPEDITE DEM | 2 | 03/21/2026 |
| MARIN ARCHITECTS, P.C. | 2 | 03/21/2026 |
| INSHA BUILDING CONSULTANTS | 2 | 03/21/2026 |
| XPDITE GROUP LLC 104 | 6 | 03/21/2026 |
| XPDITE GROUP 103 | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| REAL LAND GROUP LLC | General Contractor | 8 | 07/08/2026 |
| HIVOLTS ELECTRICAL INC 004090 | General Contractor | 6 | 03/22/2026 |
| MKSSKR CONSULTING SERVICE | General Contractor | 3 | 03/21/2026 |
| METFLOW FIRE CONTROL LLC | Fire Protection | 1 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| WALTER MARIN | Electrical | 1 | 03/21/2026 |
| CREATIVE PLUMBING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TROLYDIA TESTING & INSPEC | 4422 | 19 | 04/27/2026 |
| MJE CONSULTING ENGINEERIN | 8522 | 1 | 01/09/2024 |
| ENTHINK ENGINEERS LLC | 6247 | 1 | 02/23/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | REAL LAND GROUP LLC | 05/30/2024 |
| DOB NOW | Sprinklers | Signed-off | METFLOW FIRE CONTROL LLC | 05/29/2024 |
| DOB NOW | Plumbing | Signed-off | AB PLUMBING INC | 05/29/2024 |
| DOB NOW | General Construction | Permit Issued | REAL LAND GROUP LLC | 05/23/2024 |
| DOB NOW | General Construction | Signed-off | MKSSKR CONSULTING SERVICE | 04/04/2024 |
| DOB NOW | General Construction | Permit Issued | REAL LAND GROUP LLC | 01/24/2024 |
| DOB NOW | General Construction | Permit Issued | REAL LAND GROUP LLC | 01/26/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/27/2026 | Signed-off | REAL LAND GROUP LLC | Heating and Air Conditioning Systems | Heat / Cool Daikin RXTQ36TAVJU 37,000 BTU · Vrf Outdoor ×1 RXTQ48TAVJU 49,500 BTU · Vrf Outdoor ×1 RXYQ336AATJA 338,000 BTU · Vrf Outdoor ×1 RXYQ72AATJA 81,000 BTU · Vrf Outdoor ×1 RXYQ96AATJA 108,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/27/2026 | Signed-off | METFLOW FIRE CONTROL LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/27/2026 | Signed-off | CREATIVE PLUMBING IN | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/05/2024 | Complete | HIVOLTS ELECTRICAL INC | General Wiring |
| 03/09/2023 | Complete | RICHARD NEU | — |
| 02/16/2023 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 08/30/2022 | Complete | RICHARD NEU | — |
| 05/09/2022 | Complete | HIVOLTS ELECTRICAL INC | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/01/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 09/18/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/23/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/05/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 06/24/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/17/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/07/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/20/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/12/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/30/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/12/2026 | Air barrier continuity plan testing | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Exterior lighting power | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Fenestration and door U-factor and product ratings | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Insulation placement and R values | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Fenestration air leakage | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | EDWARD TOROSSIAN | special |
| 05/12/2026 | Concrete - Cast-In-Place | EDWARD TOROSSIAN | special |
| 05/12/2026 | Exterior Insulation and Finish Systems (EIFS) | EDWARD TOROSSIAN | special |
| 05/12/2026 | Masonry | EDWARD TOROSSIAN | special |
| 05/12/2026 | Fire-Resistance Rated Construction | EDWARD TOROSSIAN | progress |
| 05/12/2026 | Energy Code Compliance Inspections | EDWARD TOROSSIAN | progress |
| 05/12/2026 | Air barrier - visual inspection | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Electrical motors and elevators | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Lighting controls | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Vestibules | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Lighting in dwelling units | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Maintenance information | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Protection of exposed foundation insulation | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Metering | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Interior lighting power | EDWARD TOROSSIAN | energy_progress |
| 05/12/2026 | Fenestration areas | EDWARD TOROSSIAN | energy_progress |
| 04/16/2026 | Maintenance information | EDWARD TOROSSIAN | energy_progress |
| 04/16/2026 | Vestibules | EDWARD TOROSSIAN | energy_progress |
| 04/16/2026 | Metering | EDWARD TOROSSIAN | energy_progress |
| 04/16/2026 | Insulation placement and R values | EDWARD TOROSSIAN | energy_progress |