Whole building & multi-floor projects25 Water Gp Holdings LLC7 filings
Facade work to include the partial demolition of the existing masonry facade and installation of new window wall and in-swing casement windows.
On file for this project
41 documents · 2 drawing sheets
Vertical enlargement and conversion to residential use of existing 22-story building.
On file for this project
214 documents · 22 drawing sheets
INSTALLATION OF DUAL PERSONNEL/MATERIAL HOISTS. CAR # 1 SHALL BE 10000# & CAR # 2 SHALL BE 7000# CAPACITY. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCC OR EGRESS UNDER THIS APP. ELEV APP SUB SEP.
On file for this project
8 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Roof25 Water Gp Holdings LLC7p · 3 filings
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY HOIST RUN-BACK STRUCTURE DURING BLDG ALTERATION, FILED SEP. HOIST RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPL. HOIST & ELEVATOR APPL. SUBMITTED SEP.
On file for this project
4 documents · 2 drawing sheets
INSTALLATION OF TEMPORARY BRACING OF THE EXISTING COLUMN, SPANDREL, AND MASONRY WALL SYSTEM ALONG 125 BROAD STREET TO MAINTAIN THE STABILITY OF THE ELEMENTS AFTER DEMOLITION OF THE MOTOR ROOM AND PENTHOUSE ROOF SLAB AND FRAMING.
On file for this project
15 documents · 3 drawing sheets
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents · 2 drawing sheets
Penthouse25 Water Gp Holdings LLC1p · 1 filing
ArchitectureDMMechanicalStructural
INSTALLATION OF TEMPORARY BRACING OF THE EXISTING COLUMN, SPANDREL, AND MASONRY WALL SYSTEM ALONG 125 BROAD STREET TO MAINTAIN THE STABILITY OF THE ELEMENTS AFTER DEMOLITION OF THE MOTOR ROOM AND PENTHOUSE ROOF SLAB AND FRAMING.
On file for this project
15 documents · 1 drawing sheet
Floor 25Temporary hoist run-back structure1p · 2 filings
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY HOIST RUN-BACK STRUCTURE DURING BLDG ALTERATION, FILED SEP. HOIST RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPL. HOIST & ELEVATOR APPL. SUBMITTED SEP.
On file for this project
4 documents · 1 drawing sheet
CARS C&D: DUAL 7250# CAPACITY PERSONNEL/MATERIAL HOISTS DURING BLDG ALTERATION FILED SEP. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEV APPL SUB TO ELEV DEPT.
On file for this project
9 documents · 1 drawing sheet
Floor 24
Floor 23
Floor 227 Hanover Fee Owner CO LLC3p · 4 filings
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Installation of (6) six gas boilers
On file for this project
11 documents
TEMPORARY WINDOW PROTECTION AT THE ADJACENT PROPERTY (125 BROAD STREET) DURING BLDG ALTERATION, FILED SEP. WINDOW PROTECTION SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 1 drawing sheet
TEMPORARY NEEDLE BEAM PLATFORM AS PER DRAWINGS. NEEDLE BEAM PLATFORM SHALL SERVE AS THE BASE STRUCTURE FOR PIPE SCAFFOLDING & SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. PIPE SCAFFOLD FILED SEP.
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 211 filing
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Upgrade of lateral systems and existing columns. Additional structural bracing filed separately under M08027648.
On file for this project
3 documents
Floor 20
Floor 1925 Water Gp Holdings LLC1 filing
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Existing building connection reinforcement for temporary construction loading, as per plans filed herewith.
On file for this project
5 documents
Floor 1825 Water Gp Holdings LLC1 filing
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Existing building connection reinforcement for temporary construction loading, as per plans filed herewith.
On file for this project
5 documents
Floor 1725 Water Gp Holdings LLC1 filing
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Existing building connection reinforcement for temporary construction loading, as per plans filed herewith.
On file for this project
5 documents
Floor 16
Floor 15
Floor 14Plumbing and sprinkler work6p · 3 filings
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
sprinkler, plumbing modifications to the 14th floor as shown on plans
On file for this project
5 documents
Interior modification on the 14th floor as shown on plans. There is no change in use, egress or occupancy.
On file for this project
6 documents · 5 drawing sheets
Mechanical modification on the 14th floor. There is no change in use, egress or occupancy
On file for this project
5 documents · 1 drawing sheet
Floor 13
Floor 12
Floor 111 filing
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Upgrade of lateral systems and existing columns. Additional structural bracing filed separately under M08027648.
On file for this project
3 documents
Floor 1025 Water Gp Holdings LLC2 filings
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Existing building connection reinforcement for temporary construction loading, as per plans filed herewith.
On file for this project
5 documents
Upgrade of lateral systems and existing columns. Additional structural bracing filed separately under M08027648.
On file for this project
3 documents
Floor 97 Hanover Fee Owner CO LLC7p · 3 filings
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
This application is filed for a Temporary Use Permit for a sales office including model apartments pursuant to section AC 28-111 and Buildings Bulletin 2010-002. Scope of work include the model units only; Sales office filed separately under M01108031-I1.
On file for this project
3 documents · 4 drawing sheets
This application is filed for a Temporary Use Permit for a sales office including model apartments pursuant to section AC 28-111 and Buildings Bulletin 2010-002.
On file for this project
3 documents · 3 drawing sheets
Existing building connection reinforcement for temporary construction loading, as per plans filed herewith.
On file for this project
5 documents
Floor 825 Water Gp Holdings LLC3p · 2 filings
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Existing building connection reinforcement for temporary construction loading, as per plans filed herewith.
On file for this project
5 documents
GENERAL CONSTRUCTION WORK AS SHOWN ON PLANS
On file for this project
21 documents · 3 drawing sheets
Floor 7
Floor 6
Floor 525 Water Gp Holdings LLC2p · 1 filing
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Removal of existing brick masonry, back-up wall, and existing windows along future hoist run. No change to egress, use, or occupancy.
On file for this project
7 documents · 2 drawing sheets
Floor 4
Floor 3
Floor 2Temporary hoist run-back structure1p · 1 filing
ArchitectureCivilDMElectricalFire ProtectionGeneralLandscapeMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
TEMPORARY HOIST RUN-BACK STRUCTURE DURING BLDG ALTERATION, FILED SEP. HOIST RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPL. HOIST & ELEVATOR APPL. SUBMITTED SEP.
On file for this project
4 documents · 1 drawing sheet
Floor 17 Hanover Fee Owner CO LLC3p · 7 filings
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
This application is filed for a Temporary Use Permit for a sales office including model apartments pursuant to section AC 28-111 and Buildings Bulletin 2010-002. Scope of work include the model units only; Sales office filed separately under M01108031-I1.
On file for this project
3 documents
This application is filed for a Temporary Use Permit for a sales office including model apartments pursuant to section AC 28-111 and Buildings Bulletin 2010-002.
On file for this project
3 documents
TEMPORARY HOIST RUN-BACK STRUCTURE DURING BLDG ALTERATION, FILED SEP. HOIST RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPL. HOIST & ELEVATOR APPL. SUBMITTED SEP.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Cellar2p · 1 filing · 5 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
No filed description on record for this project.
On file for this project
5 documents · 10 drawing sheets
Sub-CellarEdge Funds Management7p · 3 filings · 5 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
TEMPORARY SHORING AS PER DRAWINGS. SHORING SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
REPLACEMENT (1) NEW 20,000 GALLON OIL TANK IN THE SUBCELLAR WITH NEW 3HR CONCRETE BLOCK WALL ENCLOSURE. NO CHANGE IN MEANS OF EGRESS, USE GROUP OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
No filed description on record for this project.
On file for this project
5 documents · 10 drawing sheets
Site & exterior25 Water Gp Holdings LLC14 filings
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · General Construction · Protection and Mechanical Methods · Sidewalk Shed · Sign · Sprinklers · Standpipe · Supported Scaffold
INSTALLATION OF HEAVY-DUTY SIDEWALK SHED DURING BLDG ALTERATION, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. DOT PERMITS BY OTHERS FOR SHED INSTALLED ON ROADWAY.
On file for this project
10 documents · 11 drawing sheets
INSTALL NON-ILLUMINATED SIGN ON WALL (25 WATER STREET)
On file for this project
2 documents · 1 drawing sheet
TEMPORARY HOIST RUN-BACK STRUCTURE DURING BLDG ALTERATION, FILED SEP. HOIST RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPL. HOIST & ELEVATOR APPL. SUBMITTED SEP.
On file for this project
4 documents · 12 drawing sheets
Latest 3 of 14 filings on this floor.
Filed — no permit issuedFacade inspection1 filing · 2 docs
Structural
facade inspection
On file for this project
2 documents · 1 drawing sheet