| Owner | Filings | Most Recent |
|---|---|---|
| BLUE SKY GROUP | 8 | 07/08/2026 |
| ALL EMPIRE BUILDING CONTRACTORS | 4 | 07/08/2026 |
| NAMDAR HUGHES DEV LLC | 1 | 03/22/2026 |
| 2507 HUGHES AVENUE LLC | 5 | 03/22/2026 |
| KLOSED PROPERTIES | 9 | 03/21/2026 |
| HUGHES BH LLC | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/06/2019 | $1.2M | — | 2507 HUGHES AVE, LLC → NAMDAR HUGHES DEV LLC | $364/sf building |
| 04/07/2014 | $495K | — | — → — | $150/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LONGTIN SOLUTIONS LLC | 4 | 07/11/2023 |
| SYED ENGINEERING, P.C. | 1 | 02/08/2022 |
| BASIC GROUPS CORP | 1 | 01/21/2021 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMC PLBG, HTG & CLNG, INC | Plumbing | 6 | 07/08/2026 |
| WINWAY DEVELOPMENT LLC | General Contractor | 4 | 07/08/2026 |
| JIAN YANG YU | Electrical | 2 | 03/21/2026 |
| STEEL TONE CONSTRUCTION | General Contractor | 2 | 07/08/2026 |
| ALL EMPIRE BUILDING CON | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LONGTIN SOLUTIONS LLC | 8320 | 4 | 07/11/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | AMC PLBG, HTG & CLNG, INC | 04/07/2023 |
| DOB NOW | General Construction | Signed-off | STEEL TONE CONSTRUCTION | 04/02/2023 |
| DOB NOW | General Construction | Signed-off | STEEL TONE CONSTRUCTION | 02/10/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | WINWAY DEVELOPMENT LLC | 10/12/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | ALL EMPIRE BUILDING CON | 02/24/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | WINWAY DEVELOPMENT LLC | 01/22/2021 |
| BIS | OT | ISSUED | GREAT AMERICAN CONSTR SER | 01/05/2022 |
| BIS | OT | ISSUED | BLUESKY DEVELOPMENT | 12/21/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2023 | Complete | J Y ELECTRIC INC | 4 meters, 4 new_meters |
| 03/09/2023 | Complete | J Y ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/08/2022 | Permit Issued | ALL EMPIRE BUILDING CON | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/04/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/20/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 06/26/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/26/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/16/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/12/2023 | HVAC-R and service water piping design and insulation | TIM TSAI | energy_progress |
| 07/12/2023 | Fire-Resistant Penetrations and Joints | TIM TSAI | special |
| 07/12/2023 | Energy Code Compliance Inspections | TIM TSAI | progress |
| 07/12/2023 | Fire-Resistance Rated Construction | TIM TSAI | progress |
| 07/12/2023 | HVAC-R and service water heating equipment | TIM TSAI | energy_progress |
| 07/12/2023 | HVAC-R and service water heating system controls | TIM TSAI | energy_progress |
| 07/12/2023 | Interior lighting power | TIM TSAI | energy_progress |
| 07/10/2023 | Fire-Resistant Penetrations and Joints | TIM TSAI | special |
| 07/10/2023 | Energy Code Compliance Inspections | TIM TSAI | progress |
| 07/10/2023 | Fire-Resistance Rated Construction | TIM TSAI | progress |
| 07/10/2023 | HVAC-R and service water heating system controls | TIM TSAI | energy_progress |
| 07/10/2023 | Interior lighting power | TIM TSAI | energy_progress |
| 07/10/2023 | HVAC-R and service water piping design and insulation | TIM TSAI | energy_progress |
| 07/10/2023 | HVAC-R and service water heating equipment | TIM TSAI | energy_progress |
| 06/23/2023 | Fire-Resistant Penetrations and Joints | TIM TSAI | special |
| 06/23/2023 | Energy Code Compliance Inspections | TIM TSAI | progress |