← Back
Elevator apt, miscellaneous
24 WEST 9 STREET
MANHATTAN · BIN 1009419
💬 Discuss this project
1923Year Built
9Stories
D9Building Class
R6Zoning
46,137 sfGross Floor Area
50Units
LL97 CoveredRent Stabilized5 Open Violations ▸FISP: SAFE
Elevator apt, miscellaneous · Owner of record: 26 W 9TH STREET LLC · 7,040 sf lot · 6.55 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivil
Permit Issued — active, not yet Signed-off
Roof1p · 1 filing · 20 docs
PenthouseUnder Construction125p · 4 filings · 20 docs
Floor 105p · 3 filings · 20 docs
Floor 9Under Construction129p · 5 filings · 20 docs
Floor 8Under Construction32p · 2 filings · 20 docs
Floor 7Under Construction32p · 2 filings · 20 docs
Floor 6Under Construction118p · 3 filings · 20 docs
Floor 5Under Construction118p · 3 filings · 20 docs
Floor 4Under Construction119p · 3 filings · 20 docs
Floor 3Under Construction118p · 3 filings · 20 docs
Floor 2Under Construction119p · 3 filings · 20 docs
Floor 1Under Construction142p · 5 filings · 20 docs
CellarUnder Construction135p · 6 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
26 WEST 9TH STREET1409/13/2026
26 W 9TH STREET4009/08/2026
BELLET CONSTRUCTION CO IN103/22/2026
S & E BRIDGE 4 SCAFFOLD L103/22/2026
ARS MANAGEMENT703/22/2026
OWNER OF 24 WEST 9 STREET103/22/2026
ADAM AND WONG REALTY G603/22/2026
WARWICK203/22/2026
ADAMS 7 WONG REALTY GR103/22/2026
OWNER OF 26 WEST 9 ST103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/30/2022$41.5M—Private party → 26 W 9TH STREET LLC$899/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAM CONSULTANTS, INC.3203/21/2026
UNITED SAFETY CONSULTANTS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
A.W. & S. CONSTRUCTION COGeneral Contractor806/28/2026
SPRING SCAFFOLDING LLCGeneral Contractor504/11/2026
A & M WARSHAW PLBG & HTGPlumbing207/08/2026
A + SPRINKLER CORPFire Protection207/08/2026
BENJAMIN DREBINElectrical103/21/2026
VICTOR, ALLANElectrical103/21/2026
MANZUR FLORES, JORGEElectrical103/21/2026
THE CLOONE GROUP INCGeneral Contractor107/08/2026
A PLUS PLUMBING CORPFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BIG APPLE GROUP NY A RMA91681706/10/2026
SITE SAFETY LLC85551106/10/2026
Building Lifecycle
All (178)Filed (25)Permit Issued (16)Signed Off (4)Facade (FISP) (17)Violation (60)Inspection (14)Objection (12)Special Inspection (30)
08/24/2026
Signed off — Alteration
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR A SALES OFFICE ON THE 4TH FLOOR INCLUDING MODEL APARTMENTS PURSUANT TO SECTION AC-28-111 AND BUILDING BULLETIN 2010-22
M01365909-I1
06/25/2026
Permit issued — Mechanical Systems
M01096787-I1-MS
06/25/2026
Permit issued — General Construction
M01025590-I1-GC
06/23/2026
Special inspection requirement — Mechanical Systems
SOORJBALLY HARILALL
06/23/2026
Special inspection requirement — Post-installed Anchors
SOORJBALLY HARILALL
06/23/2026
Special inspection requirement — Tenant Protection Plan Compliance
KHALID ALGENDE
06/23/2026
Special inspection requirement — Final
SOORJBALLY HARILALL
06/10/2026
Filed — Alteration CO
CHANGE MULTIPLE DWELLING CLASSIFICATION, ENCLOSE STAIRS, EXTEND STAIR TO ROOF, CONVERT DOCTORS OFFICES TO APARTMENTS AND RENOVATION OF EXISTING DWELLING UNITS.
M01025590-P6
06/10/2026
Special inspection requirement — Tenant Protection Plan Compliance
KHALID ALGENDE
06/10/2026
Special inspection requirement — Fire-Resistance Rated Construction
SOORJBALLY HARILALL
06/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
06/08/2026
Filed — Alteration CO
CHANGE MULTIPLE DWELLING CLASSIFICATION, ENCLOSE STAIRS, EXTEND STAIR TO ROOF, CONVERT DOCTORS OFFICES TO APARTMENTS AND RENOVATION OF EXISTING DWELLING UNITS.
M01025590-P5
06/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
06/08/2026
Special inspection requirement — Tenant Protection Plan Compliance
06/08/2026
Special inspection requirement — Fire-Resistance Rated Construction
SOORJBALLY HARILALL
05/27/2026
Filed — Alteration CO
CHANGE MULTIPLE DWELLING CLASSIFICATION, ENCLOSE STAIRS, EXTEND STAIR TO ROOF, CONVERT DOCTORS OFFICES TO APARTMENTS AND RENOVATION OF EXISTING DWELLING UNITS.
M01025590-P4
05/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
05/27/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/27/2026
Special inspection requirement — Fire-Resistance Rated Construction
SOORJBALLY HARILALL
05/04/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
04/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
KHALID ALGENDE
04/23/2026
Filed — Alteration
Replacement of existing plumb. fixtures with new on exist. roughing, addition of limited roughing for kitchens/bathrooms, removal of gas service, water heating installation of new water heating plant, installation of new water service & backflow devices.
M01096844-P5
04/23/2026
Filed — Alteration
New sprinkler protection to include Fire Pump, Riser, Floor control assemblies, drain risers. Replace exist. fire hose racks with new fire valve cabinets. Standpipe system modification removal of exist. fire hose & relocate exist. hose valves.
M01098721-P3
04/20/2026
Special inspection requirement — Tenant Protection Plan Compliance
KHALID ALGENDE
04/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
04/15/2026
Filed — Alteration
Installation of New VRV Systems made up of condensing units on the Roof piped to evaporators at each floor to provide Heating/Cooling throughout building. Exhaust is provided to BOH spaces, Cellar, trash closets. Electric Unit heaters provided throughout.
M01096787-P3
04/10/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/10/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/09/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01010286-I1
04/01/2026
Permit issued — General Construction
M01365909-I1-GC
03/23/2026
Filed — Alteration
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR A SALES OFFICE ON THE 4TH FLOOR INCLUDING MODEL APARTMENTS PURSUANT TO SECTION AC-28-111 AND BUILDING BULLETIN 2010-22
M01365909-I1
03/23/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/20/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
03/20/2026
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
03/18/2026
Signed off — Alteration
Removal of a section of exterior bearing wall at Cellar, Framing for new penetrations through mechanical room roof (1st Floor), Addition of roof dunnage for support of MEP units per plans filed.
M01096750-I1
03/17/2026
Permit issued — Standpipe
M01098721-I1-EW-SP
03/12/2026
Special inspection requirement — Mechanical Systems
SOORJBALLY HARILALL
03/12/2026
Special inspection requirement — Tenant Protection Plan Compliance
03/12/2026
Special inspection requirement — Post-installed Anchors
SOORJBALLY HARILALL
03/12/2026
Special inspection requirement — Final
SOORJBALLY HARILALL
03/06/2026
Permit issued — Sidewalk Shed
M01010286-I1-SH
02/12/2026
Filed — Alteration CO
CHANGE MULTIPLE DWELLING CLASSIFICATION, ENCLOSE STAIRS, EXTEND STAIR TO ROOF, CONVERT DOCTORS OFFICES TO APARTMENTS AND RENOVATION OF EXISTING DWELLING UNITS.
M01025590-P3
02/12/2026
Special inspection requirement — Tenant Protection Plan Compliance
01/30/2026
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
01/30/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/08/2026
Permit issued — Plumbing
M01096844-I1-PL
11/20/2025
Filed — Alteration
Replacement of existing plumb. fixtures with new on exist. roughing, addition of limited roughing for kitchens/bathrooms, removal of gas service, water heating installation of new water heating plant, installation of new water service & backflow devices.
M01096844-P3
11/20/2025
Filed — Alteration
Installation of New VRV Systems made up of condensing units on the Roof piped to evaporators at each floor to provide Heating/Cooling throughout building. Exhaust is provided to BOH spaces, Cellar, trash closets. Electric Unit heaters provided throughout.
M01096787-P2
11/20/2025
Filed — Alteration
New sprinkler protection to include Fire Pump, Riser, Floor control assemblies, drain risers. Replace exist. fire hose racks with new fire valve cabinets. Standpipe system modification removal of exist. fire hose & relocate exist. hose valves.
M01098721-P2
10/30/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/30/2025
Special inspection requirement — Tenant Protection Plan Compliance
KHALID ALGENDE
10/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
10/16/2025
Filed — Alteration CO
CHANGE MULTIPLE DWELLING CLASSIFICATION, ENCLOSE STAIRS, EXTEND STAIR TO ROOF, CONVERT DOCTORS OFFICES TO APARTMENTS AND RENOVATION OF EXISTING DWELLING UNITS.
M01025590-P2
10/08/2025
Special inspection requirement — Tenant Protection Plan Compliance
09/16/2025
Permit issued — Structural
M01096750-I1-ST
09/16/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
08/14/2025
Permit issued — Sprinklers
M01098721-I1-EW-SD
07/14/2025
Objection raised — Inspections
Latest 60 of 178 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offA.W. & S. CONSTRUCTION CO06/25/2026
DOB NOWGeneral ConstructionPermit IssuedA.W. & S. CONSTRUCTION CO06/25/2026
DOB NOWGeneral ConstructionSigned-offA.W. & S. CONSTRUCTION CO04/01/2026
DOB NOWStandpipeSigned-offA PLUS PLUMBING CORP03/17/2026
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC03/06/2026
DOB NOWPlumbingPermit IssuedA & M WARSHAW PLBG & HTG01/08/2026
DOB NOWStructuralSigned-offA.W. & S. CONSTRUCTION CO09/16/2025
DOB NOWSprinklersSigned-offA + SPRINKLER CORP08/14/2025
DOB NOWGeneral ConstructionPermit IssuedA.W. & S. CONSTRUCTION CO06/30/2025
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC03/05/2025
DOB NOWGeneral ConstructionPermit IssuedA.W. & S. CONSTRUCTION CO01/22/2025
DOB NOWSprinklersSigned-offA + SPRINKLER CORP01/16/2025
DOB NOWMechanical SystemsSigned-offA.W. & S. CONSTRUCTION CO01/15/2025
DOB NOWPlumbingPermit IssuedA & M WARSHAW PLBG & HTG01/14/2025
DOB NOWGeneral ConstructionSigned-offTHE CLOONE GROUP INC09/09/2024
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC02/26/2024
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.04/20/2022
BISOTISSUEDSASCO CONSTRUCTION SVCE L01/03/2022
BISOTISSUEDBELLET CONSTRUCTION CO.IN10/05/2021
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.04/28/2021
BISOTISSUEDBELLET CONSTRUCTION CO.IN11/02/2020
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.05/19/2020
BISOTISSUEDBELLET CONSTRUCTION CO.IN11/12/2019
BISOTISSUEDBELLET CONSTRUCTION CO.IN10/22/2018
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.05/30/2018
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.06/13/2017
BISOTISSUEDSASCO CONSTRUCTION SVCE L08/12/2016
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.06/28/2016
BISOTISSUEDSASCO CONSTRUCTION SVCE L03/11/2016
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.07/02/2015
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.07/23/2014
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.06/24/2013
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.02/28/2013
BISOTISSUEDPRESERV BLD RESTOR MGT IN08/08/2012
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.03/14/2012
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.02/03/2012
BISOTISSUEDPRESERV BLD RESTOR MGT IN04/05/2010
BISOTISSUEDPRESERV BLD RESTOR MGT IN10/28/2009
BISOTISSUEDPRESERV BUILDINGS TECHNOLOGIES I03/28/2007
BISEQISSUEDPERIMETER BRIDGE & SCAFFOLD01/11/2007
+ 11 more permits on file
1 project · most recent 04/15/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
04/15/2026Signed-offA.W. & S. CONSTRUCTION COHeating and Air Conditioning Systems
Heat / Cool
— DAIKEN FXSQ36TBVJU 30,000 BTU · Heat Pump Outdoor ×95
DAIKEN FXSQ07TBVJU 5,800 BTU · Heat Pump Outdoor ×18
DAIKEN FXSQ48TBVJU 40,000 BTU · Heat Pump Outdoor ×19
DAIKEN FXAQ18PVJU 14,700 BTU · Heat Pump Outdoor ×12
DAIKEN FXSQ18TBVJU 15,000 BTU · Heat Pump Outdoor ×5
FXSQ48TBVJU 40,000 BTU · Heat Pump Outdoor ×6
DAIKEN FXAQ12PVJU 7,900 BTU · Heat Pump Outdoor ×4
DAIKEN FXSQ24TBVJU 20,000 BTU · Heat Pump Outdoor ×2
DAIKEN FXSQ48TAVJU 40,000 BTU · Heat Pump Outdoor ×3
DAIKEN FXSQ05TBVJU 5,800 BTU · Heat Pump Outdoor ×9
DAIKIN FXSQ48TBVJU 40,000 BTU · Heat Pump Outdoor ×8
DAIKIN FXSQ18TBVJU 15,000 BTU · Heat Pump Outdoor ×1
DAIKIN FXSQ24TBVJU 20,000 BTU · Heat Pump Outdoor ×1
DAIKEN FXAQ36TAVJU 30,000 BTU · Heat Pump Outdoor ×4
DAIKEN FXAQ24TAVJU 20,000 BTU · Heat Pump Outdoor ×3
DAIKEN FXAQ18TAVJU 15,000 BTU · Heat Pump Outdoor ×2
DAIKEN FXAQ48TAVJU 40,000 BTU · Heat Pump Outdoor ×2
DAIKEN FXAQ05BVVJU 30,000 BTU · Heat Pump Outdoor ×1
DAIKEN FXAQ12TAVJU 9,900 BTU · Heat Pump Outdoor ×1
Daikin FXSQ18TBVJU 15,000 BTU · Vrf Indoor ×3
1 project · most recent 04/23/2026
FiledStatusContractorScope
04/23/2026Signed-offA PLUS PLUMBING CORP1,564 heads, 33 outlets
1 project · most recent 04/23/2026
Water/Sanitary
FiledStatusContractorScope
04/23/2026Permit IssuedA & M WARSHAW PLBG & HTGWater/Sanitary
4 projects · most recent 04/15/2026
General Wiring
FiledStatusContractorScope
04/15/2026CompleteJAM ELECTRICAL CORP—
10/15/2025Permit IssuedLIVE WIRE ELECTRIC 1 LLCGeneral Wiring
01/09/2025CancelledEMPIRE STATE ELEC MAINT &2 meters, 1 new_meters
02/21/2024CompleteTOP SHELF ELECTRIC CORP—
▾Field Inspections (DOB CAP) — 14
DateTypeResultReport
05/04/2026Pass-Final CND-Occupancy InspectionPassView ↗
04/10/2026Pass-Final CND-Occupancy InspectionPassView ↗
04/10/2026Pass-Final General Construction Non-Directive 14PassView ↗
03/23/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/20/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/20/2026Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
01/30/2026Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
01/30/2026Fail-Final General Construction Non-Directive 14FailView ↗
10/30/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/30/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/16/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/11/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/19/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/19/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 44
DateRequirementInspectorRole
06/23/2026Mechanical SystemsSOORJBALLY HARILALLspecial
06/23/2026Post-installed AnchorsSOORJBALLY HARILALLspecial
06/23/2026Tenant Protection Plan ComplianceKHALID ALGENDEspecial
06/23/2026FinalSOORJBALLY HARILALLprogress
06/10/2026Tenant Protection Plan ComplianceKHALID ALGENDEspecial
06/10/2026Fire-Resistance Rated ConstructionSOORJBALLY HARILALLprogress
06/10/2026Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
06/08/2026Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
06/08/2026Tenant Protection Plan Compliance—special
06/08/2026Fire-Resistance Rated ConstructionSOORJBALLY HARILALLprogress
05/27/2026Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
05/27/2026Tenant Protection Plan Compliance—special
05/27/2026Fire-Resistance Rated ConstructionSOORJBALLY HARILALLprogress
04/26/2026Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
04/26/2026Tenant Protection Plan ComplianceKHALID ALGENDEspecial
04/20/2026Tenant Protection Plan ComplianceKHALID ALGENDEspecial
04/20/2026Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
03/12/2026Mechanical SystemsSOORJBALLY HARILALLspecial
03/12/2026Tenant Protection Plan Compliance—special
03/12/2026Post-installed AnchorsSOORJBALLY HARILALLspecial
03/12/2026FinalSOORJBALLY HARILALLprogress
02/12/2026Tenant Protection Plan Compliance—special
10/30/2025Tenant Protection Plan ComplianceKHALID ALGENDEspecial
10/30/2025Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
10/08/2025Tenant Protection Plan Compliance—special
Latest 25 of 44.
▾Documents — 316 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch25
08/25/2026M00911777-I1Request digital key ↗
08/25/2026M00911777-P1Request digital key ↗
08/25/2026M01096750-I1Request digital key ↗
Showing 3 of 25 on file for this type
▸Applications & Permits79
▸BISPLAN / WORK APPROVAL APPLICATION35
11/03/2025122711002Open ↗
10/27/2025102134110Open ↗
10/17/2025104459364Open ↗
Showing 3 of 35 on file for this type
▸BISWORK PERMIT APPLICATION22
04/20/2022120937834Open ↗
01/04/2022122711002Open ↗
04/30/2021120937834Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWLPC Approval/Permit22
08/17/2026M01098721-P3Open ↗
08/17/2026M01096844-P5Open ↗
08/16/2026M01025590-P6Open ↗
Showing 3 of 22 on file for this type
▸Seals & Professional Certifications68
▸DOB NOWDPL-1: Design Professional Seal & Signature25
08/25/2026M00911777-P1Open ↗
08/25/2026M00911777-I1Open ↗
08/24/2026M01010286-I1Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature20
08/31/2026M01096844-P1Open ↗
08/31/2026M01096844-P1Open ↗
08/30/2026M01025590-P6Open ↗
Showing 3 of 20 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST7
11/08/2019122711002Open ↗
11/07/2019122711002Open ↗
05/10/2019120937834Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
05/23/2019120937834Open ↗
05/10/2019120937834Open ↗
03/23/2016122711002Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/01/2026M00911777-P1Open ↗
08/29/2026M01096750-I1Open ↗
08/26/2026M01096787-P1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
02/06/2012120967196Open ↗
02/06/2012120937834Open ↗
10/23/2009120191470Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
05/10/2019120937834Open ↗
03/23/2016122711002Open ↗
▸Safety & Tenant Protection10
▸DOB NOWStreet Tree Checklist7
08/16/2026M01025590-P5Open ↗
08/16/2026M01025590-P6Open ↗
08/16/2026M01025590-P4Open ↗
Showing 3 of 7 on file for this type
▸BISTenant Protection Plan and Notes3
11/08/2019122711002Open ↗
11/07/2019122711002Open ↗
11/04/2021120937834Open ↗
▸Environmental & Asbestos20
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/17/2026M01098721-P2Open ↗
08/17/2026M01098721-P1Open ↗
08/17/2026M01098721-P3Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/25/2026M00911777-I1Open ↗
08/17/2026M01096787-I1Open ↗
08/17/2026M01096844-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
02/06/2012120967196Open ↗
▸BIS* ASBESTOS ACP 7 OR 5 OR ASB 41
10/27/2025120191470Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/23/2016122711002Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
10/23/2009120191470Open ↗
▸BISASBESTOS-EXEMPTION (ASB4)1
02/06/2012120937834Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
10/31/2025120967196Open ↗
10/31/2025104459364Open ↗
10/31/2025102134110Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
10/31/2025104459364Open ↗
10/31/2025102134110Open ↗
10/09/2025120191470Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
12/11/2025122711002Open ↗
10/31/2025120967196Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
12/11/2025122711002Open ↗
▸BISTECHNICAL REPORT: ENERGY1
02/06/2012120967196Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
03/23/2016122711002Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY5
10/31/2025102134110Open ↗
09/22/2025102134110Open ↗
09/18/2025102134110Open ↗
Showing 3 of 5 on file for this type
▸BIS* STRUCTURAL STABILITY 1 RCNY:16-012
11/03/2025102134110Open ↗
10/31/2025104459364Open ↗
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
10/31/2025104459364Open ↗
▸Approvals, Objections & Sign-offs39
▸BISLETTERS - SUPPORTING DOCUMENTATION15
04/20/2022120937834Open ↗
01/04/2022122711002Open ↗
04/30/2021120937834Open ↗
Showing 3 of 15 on file for this type
▸BISSHED LETTER5
04/20/2022120937834Open ↗
05/20/2020120937834Open ↗
05/20/2020120937834Open ↗
Showing 3 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
12/15/2025120967196Open ↗
12/12/2025122711002Open ↗
12/12/2025104459364Open ↗
Showing 3 of 5 on file for this type
▸BISLANDMARKS SIGNOFF4
12/15/2025120967196Open ↗
12/12/2025122711002Open ↗
12/12/2025104459364Open ↗
Showing 3 of 4 on file for this type
▸BISLANDMARKS APPROVAL3
03/23/2016122711002Open ↗
02/06/2012120967196Open ↗
10/23/2009120191470Open ↗
▸BISADMINISTRATIVE OBJECTIONS3
02/06/2012120967196Open ↗
02/06/2012120937834Open ↗
10/23/2009120191470Open ↗
▸BISFINAL3
12/11/2025122711002Open ↗
10/31/2025120967196Open ↗
10/09/2025120191470Open ↗
▸BISSUPERSEDING LETTER1
11/27/2018122711002Open ↗
▸Cost, Insurance & Ownership12
▸BISCOST AFFIDAVIT8
11/03/2025122711002Open ↗
10/31/2025102134110Open ↗
04/22/2021122711002Open ↗
Showing 3 of 8 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
12/12/2025122711002Open ↗
10/31/2025120967196Open ↗
10/31/2025104459364Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms17
▸BISADDITIONAL INFORMATION7
11/03/2025122711002Open ↗
11/04/2021120937834Open ↗
06/15/2021120937834Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM6
04/20/2022120937834Open ↗
01/04/2022122711002Open ↗
04/30/2021120937834Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET4
03/23/2016122711002Open ↗
02/06/2012120967196Open ↗
02/06/2012120937834Open ↗
Showing 3 of 4 on file for this type
▸Other Documents26
▸DOB NOWProof of Historic Building16
08/17/2026M01096844-P5Open ↗
08/16/2026M01025590-P5Open ↗
08/16/2026M01025590-P4Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProperty Ownership Certification7
08/16/2026M01025590-P5Open ↗
08/16/2026M01025590-P4Open ↗
08/16/2026M01025590-P6Open ↗
Showing 3 of 7 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
04/20/2022120937834Open ↗
11/07/2019122711002Open ↗
▸BISLL-2 6/04-31
05/20/2020120937834Open ↗