RoofUnder Construction8p · 4 filings · 9 docs
ArchitectureFire ProtectionStructural
Issued Permit Scope
Protection and Mechanical Methods · Sprinklers
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Installation of temporary roof protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
2 documents · 2 drawing sheets
PROPOSED TO REMOVE SPRINKLER SYSTEM IN CONJUNCTION WITH FULL DEMO JOB # B00929163. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 12Under Construction1 filing · 1 doc
Issued Permit Scope
Protection and Mechanical Methods
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Floor 11Under Construction2 filings · 2 docs
Issued Permit Scope
Protection and Mechanical Methods
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Floor 10Under Construction79p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 1 drawing sheet
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 9Under Construction80p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 2 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 8Under Construction80p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 2 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 7Under Construction89p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 2 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 6Under Construction89p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 2 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 5Under Construction15p · 4 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 2 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 4Under Construction16p · 4 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 3 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 3Under Construction15p · 4 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 2 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.
Floor 2Under Construction24p · 6 filings · 20 docs
ArchitectureCivilDMFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Sprinklers
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 2 drawing sheets
INSTALLATION AND USE OF TEMPORARY MATERIAL PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 6 filings on this floor.
Floor 1Under Construction20p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Sprinklers
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 3 drawing sheets
INSTALLATION AND USE OF TEMPORARY KNUCKLEBOOM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE EGRESS, OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
CellarUnder Construction63p · 2 filings · 20 docs
ArchitectureCivilMechanicalStructural
Issued Permit Scope
Earth Work · Foundation · General Construction · Protection and Mechanical Methods · Support of Excavation
Underpinning filed in conjunction to application B01172199-S1
On file for this project
84 documents · 1 drawing sheet
INSTALLATION AND USE OF TEMPORARY KNUCKLEBOOM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE EGRESS, OR OCCUPANCY.
On file for this project
2 documents