← Back
Office with commercial, 7-19 stories
270 Madison Avenue Lh Condominium
266 MADISON AVENUE · BIN 1017588
💬 Discuss this project
1923Year Built
19Stories
O6Building Class
—Zoning
217,317 sfGross Floor Area
33Units
LL97 Covered1 Open Violation ▸FISP: SWARMP
Office with commercial, 7-19 stories · Owner of record: 270 MADISON AVE ASSOC'S, LLC · 14,220 sf lot · 15.28 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire ProtectionCivilGeneralOther
Permit Issued — active, not yet Signed-off
Floor 1917p · 3 filings · 20 docs
Floor 18
Floor 1715p · 2 filings · 20 docs
Floor 16
Floor 15
Floor 14
Floor 1319p · 3 filings · 20 docs
Floor 1226p · 6 filings · 20 docs
Floor 1120p · 3 filings · 20 docs
Floor 10
Floor 9
Floor 87p · 4 filings · 20 docs
Floor 7
Floor 6Under Construction16p · 4 filings · 20 docs
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1Under Construction26p · 6 filings · 20 docs
MezzanineUnder Construction9p · 1 filing · 11 docs
CellarUnder Construction12p · 2 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
184 ASSOCIATES LLC C O ABS P1407/08/2026
ABS PARTNERS REAL ESTATE LLC2907/08/2026
184 ASSOCIATES LLC C/O ABS P1103/22/2026
270 MADISON AVE ASSOC21403/22/2026
270 MADISON PARTNERS2903/22/2026
ORIX REALTY MGMT INC403/22/2026
270 MADISON1303/22/2026
270 MADISON LTD PTSNSH403/22/2026
270 MADISON LTD PINSH103/22/2026
MENDIX REALTY103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SARK FLOORING LLCGeneral Contractor607/08/2026
20/20 GENERAL CONTRACTINGGeneral Contractor603/21/2026
E AND G MODICA CONTRACTINGeneral Contractor607/08/2026
PREMIER SANITATION LLCGeneral Contractor407/08/2026
G. C. PLBG & HTG INCPlumbing407/08/2026
LT FIRE PROTECTION CORPFire Protection407/08/2026
JOY GREE LLCGeneral Contractor303/21/2026
KINGS GROUP NY CORPGeneral Contractor303/21/2026
WON YOUNG SERV NYC INCGeneral Contractor307/08/2026
HYDROKINETIC PLBG & HTG IPlumbing207/08/2026
ANESIS SERVICES CORPFire Protection207/08/2026
DEVO FIRE PROTECTION INCFire Protection207/08/2026
PALONE BROTHERS AIRGeneral Contractor209/12/2026
SUK KIMElectrical103/21/2026
?SUK YOUNG KIMElectrical103/21/2026
SYDNEY HOFFERTElectrical103/21/2026
TOUGH STALLION LLCElectrical103/21/2026
ZIZZO, FRANKElectrical103/21/2026
AVON PLBG & HTG INCPlumbing107/08/2026
ASCO SPRINKLER CO.,INCFire Protection107/08/2026
AVON PLBG & HTG INCFire Protection107/08/2026
ALL WAYS ELECTRIC CORP.WElectrical103/22/2026
KONTOROUHAS EMANUELElectrical103/21/2026
JTE ELECTRICAL SERVICESElectrical103/22/2026
GRELLER, JOHNElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SY ENGINEERING PLLC5149107/09/2026
WALTER T. GORMAN, P.E., P2681105/19/2026
JASON M APTOWITZ CONSULTI5671103/23/2026
HARDIE & ASSOCIATES, CONS3760206/06/2025
AZ PROFESSIONAL ENGINEERI766102/16/2025
NEW AGE ENGINEERING PLLC7746210/15/2024
RYAN SPECIAL ENGINEERING2018206/12/2024
DJ ASSOCIATES ARCHITECT,2852209/26/2023
LB ENGINEERING PC3122209/19/2023
CROSSCHECK INSPECTION SER544507/29/2021
Building Lifecycle
All (232)Filed (39)Permit Issued (38)Signed Off (10)Facade (FISP) (12)Violation (60)Inspection (35)Objection (8)Special Inspection (30)
09/10/2026
Permit issued — Mechanical Systems
M01380858-I1-MS
07/17/2026
Permit issued — Mechanical Systems
M01413505-I1-MS
07/13/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/13/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/13/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/09/2026
Filed — Alteration
REMOVAL AND INSTALLATION OF NEW VRF CONDENSING UNIT, AND INSTALLATION OF NEW REFRIGERATION SYSTEM.
M01413505-I1
07/08/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/18/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/11/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/09/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/08/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/08/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
SUNGBOM YI
06/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SUNGBOM YI
06/08/2026
Special inspection requirement — Energy Code Compliance Inspections
SUNGBOM YI
06/08/2026
Special inspection requirement — Mechanical Systems
SUNGBOM YI
06/08/2026
Special inspection requirement — Maintenance information
SUNGBOM YI
06/08/2026
Special inspection requirement — Final
SEOK HUN KIM
06/08/2026
Special inspection requirement — HVAC-R and service water heating equipment
SUNGBOM YI
06/08/2026
Special inspection requirement — HVAC-R and service water heating system controls
SUNGBOM YI
06/04/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/04/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/26/2026
Permit issued — Sprinklers
M01380913-I1-EW-SP
05/22/2026
Permit issued — Sprinklers
M01380913-I1-PL
05/21/2026
Permit issued — General Construction
M01380839-I1-GC
05/19/2026
Filed — Alteration
Propose to perform mechanical work. No change in use, egress or occupancy.
M01380858-I1
05/19/2026
Filed — Alteration
Propose to perform plumbing and sprinkler work. No change in use, egress or occupancy.
M01380913-I1
05/18/2026
Filed — Alteration
Propose stair infill, skylight refurbishment, roof replacement. No change in use, egress or occupancy.
M01380839-I1
03/31/2026
Special inspection requirement — Energy Code Compliance Inspections
Walter Gorman
03/31/2026
Special inspection requirement — Final
Walter Gorman
03/31/2026
Special inspection requirement — Mechanical Systems
Walter Gorman
03/31/2026
Special inspection requirement — Shutoff dampers
Walter Gorman
03/31/2026
Special inspection requirement — HVAC-R and service water heating system controls
Walter Gorman
03/31/2026
Special inspection requirement — Maintenance information
Walter Gorman
03/31/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Walter Gorman
03/31/2026
Special inspection requirement — HVAC-R and service water heating equipment
Walter Gorman
03/23/2026
Filed — Alteration
FACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01365008-I1
02/26/2026
Special inspection requirement — Final
JASON APTOWITZ
02/26/2026
Special inspection requirement — Masonry
JASON APTOWITZ
02/26/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
JASON APTOWITZ
02/24/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/07/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
08/28/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/25/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/09/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/07/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/07/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/02/2025
Permit issued — Sprinklers
M01218295-I1-EW-SP
07/02/2025
Permit issued — Plumbing
M01218293-I1-PL
06/25/2025
Permit issued — Mechanical Systems
M01218294-I1-MS
06/23/2025
Signed off — Alteration
APPLICATION FILED FOR STANDPIPE MODIFICATIONS/ADDITIONS IN THE CELLAR AND ON THE 1ST FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00848849-I1
06/17/2025
Permit issued — General Construction
M01218292-I1-GC
06/06/2025
Filed — Alteration
INTERIOR RENOVATION FOR REMOVAL AND CONSTRUCTION OF NON-LOAD BEARING PARTITIONS AND FINISHES AS PER PLAN. NO EXTERIOR WORK. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01218292-I1
06/06/2025
Filed — Alteration
INTERIOR MECHANICAL RENOVATION FOR INSTALLATION OF AIR COOLED CONDITIONING UNITS AND EXHAUST FANS AS PER PLANS. NO EXTERIOR WORK. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01218294-I1
06/06/2025
Filed — Alteration
INTERIOR RENOVATION OF 8TH FLOOR FOR NEW INSTALLATION AND RELOCATION OF SPRINKLERS AS PER PLANS. NO EXTERIOR WORK. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01218295-I1
06/06/2025
Filed — Alteration
INTERIOR RENOVATION OF 8TH FLOOR FOR INSTALLATION OF NEW PLUMBING FIXTURES AS PER PLANS. NO EXTERIOR WORK. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01218293-I1
06/06/2025
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
06/04/2025
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
05/02/2025
Permit issued — Sprinklers
M01053172-S4-EW-SP
04/30/2025
Special inspection requirement — Final
Anthony Nicholas
04/30/2025
Special inspection requirement — Sprinkler Systems
ELLIOTT HARDIE
Latest 60 of 232 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedPALONE BROTHERS AIR09/10/2026
DOB NOWMechanical SystemsPermit IssuedNYC REFRIGERATION MECHANICAL07/17/2026
DOB NOWSprinklersPermit IssuedLT FIRE PROTECTION CORP05/26/2026
DOB NOWSprinklersSigned-offG. C. PLBG & HTG INC05/22/2026
DOB NOWGeneral ConstructionPermit IssuedSARK FLOORING LLC05/21/2026
DOB NOWSprinklersSigned-offLT FIRE PROTECTION CORP07/02/2025
DOB NOWPlumbingSigned-offG. C. PLBG & HTG INC07/02/2025
DOB NOWMechanical SystemsPermit IssuedPALONE BROTHERS AIR06/25/2025
DOB NOWGeneral ConstructionPermit IssuedSARK FLOORING LLC06/17/2025
DOB NOWSprinklersSigned-offASCO SPRINKLER CO.,INC05/02/2025
DOB NOWStandpipeSigned-offDEVO FIRE PROTECTION INC04/21/2025
DOB NOWMechanical SystemsPermit Issued20/20 GENERAL CONTRACTING07/11/2024
DOB NOWGeneral ConstructionPermit Issued20/20 GENERAL CONTRACTING07/10/2024
DOB NOWGeneral ConstructionSigned-offPREMIER SANITATION LLC02/02/2024
DOB NOWStandpipeSigned-offDEVO FIRE PROTECTION INC01/03/2024
DOB NOWMechanical SystemsPermit IssuedE AND G MODICA CONTRACTIN11/22/2023
DOB NOWGeneral ConstructionPermit IssuedE AND G MODICA CONTRACTIN11/22/2023
DOB NOWPlumbingPermit IssuedLT FIRE PROTECTION CORP11/17/2023
DOB NOWPlumbingSigned-offG. C. PLBG & HTG INC11/17/2023
DOB NOWGeneral ConstructionPermit IssuedJOY GREE LLC11/15/2023
DOB NOWPlumbingPermit IssuedAVON PLBG & HTG INC10/24/2023
DOB NOWMechanical SystemsPermit IssuedWON YOUNG SERV NYC INC09/29/2023
DOB NOWSprinklersPermit IssuedAVON PLBG & HTG INC09/15/2023
DOB NOWGeneral ConstructionPermit IssuedWON YOUNG SERV NYC INC06/14/2023
DOB NOWGeneral ConstructionSigned-offE AND G MODICA CONTRACTIN09/06/2022
DOB NOWPlumbingSigned-offG. C. PLBG & HTG INC06/14/2022
DOB NOWSprinklersPermit IssuedLT FIRE PROTECTION CORP06/14/2022
DOB NOWGeneral ConstructionSigned-offE AND G MODICA CONTRACTIN06/03/2022
DOB NOWGeneral ConstructionSigned-offSARK FLOORING LLC05/19/2022
DOB NOWStructuralSigned-offMELICO CONTRACTING INC03/18/2022
DOB NOWGeneral ConstructionSigned-offPREMIER SANITATION LLC12/22/2021
DOB NOWMechanical SystemsSigned-offSARK FLOORING LLC11/16/2021
DOB NOWSidewalk ShedSigned-offMANHATTAN D ENTERPRISES03/02/2021
DOB NOWSprinklersSigned-offTHOMAS FAY03/18/2020
DOB NOWSprinklersSigned-offHYDROKINETIC PLBG & HTG I03/03/2020
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP03/02/2020
DOB NOWSprinklersSigned-offHYDROKINETIC PLBG & HTG I01/10/2020
DOB NOWSprinklersSigned-offTHOMAS FAY01/09/2020
BISMHISSUEDPALONE BROTHERS AIR08/19/2021
BISSPISSUEDALLSTATE SPRINKLER LLC06/10/2020
+ 48 more permits on file
5 projects · most recent 07/09/2026
Air Conditioning Systems Heating and Air Conditioning Systems Refrigeration Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
07/09/2026Permit IssuedNYC REFRIGERATION MECHANIHeating and Air Conditioning Systems, Refrigeration Systems
Heat / Cool
Daikin RXTQ48TBVJUB 4 tons · Vrf Outdoor ×1
RXYQ168AATJB 14 tons · Vrf Outdoor ×1
RXYQ96AATJB 8 tons · Vrf Outdoor ×1
Refrigeration
Emerson XFAM-060Z-TFC-081 15,000 BTU · Condensing Unit ×1
05/19/2026Permit IssuedPALONE BROTHERS AIRAir Conditioning Systems
Cooling
Lg ARNU483M3A4 48,100 BTU · Vrf Indoor ×9
ARNU363M2A4 36,200 BTU · Vrf Indoor ×3
ARUM241BTE5 233,100 BTU · Vrf Outdoor ×2
06/06/2025Permit IssuedPALONE BROTHERS AIRHeating and Air Conditioning Systems
Heat / Cool
Lg ARNU483M3A4 54,200 BTU · Vrf Indoor ×9
ARNU363M2A4 40,600 BTU · Vrf Indoor ×3
ARUM241BTE5 243,000 BTU · Vrf Outdoor ×2
Greenheck SP-A700-VG 400 CFM · Exhaust Fan ×4
SP-A390-VG 75 CFM · Exhaust Fan ×2
SP-A510-VG 140 CFM · Exhaust Fan ×2
Stelpro ASSO1001T2TW 1,706 BTU · Electric Heater ×1
11/10/2023Permit IssuedE AND G MODICA CONTRACTINAir Conditioning Systems
Cooling
Daikin RXTQ48TBVJUA 45,500 BTU · Vrf Outdoor ×3
FXTQ48TAVJUD 48,000 BTU · Vrf Indoor ×2
FXTQ60TAVJUD 60,000 BTU · Vrf Indoor ×2
RXTQ60TBVJUA 57,000 BTU · Vrf Outdoor ×2
Carrier FX4DNB049L00 45,640 BTU · Split System ×1
11/15/2022——Air Conditioning Systems, Heating Systems
Cooling
Florida Heat Pump 3vtc-fbfbua 251,100 BTU · Packaged Unit ×10
3vt-fbfbua 157,800 BTU · Packaged Unit ×2
Daikin 4mxs36rmvjua 36,000 BTU · Split System ×2
6 projects · most recent 05/19/2026
FiledStatusContractorScope
05/19/2026Permit IssuedLT FIRE PROTECTION CORP347 heads
06/06/2025Signed-offLT FIRE PROTECTION CORP212 heads
02/16/2025Signed-offASCO SPRINKLER COMPANY, INC100 heads
11/08/2023Permit IssuedLT FIRE PROTECTION CORP—
09/14/2023Permit IssuedAVON PLBG & HTG INC—
08/08/2023Permit IssuedLT FIRE PROTECTION CORP—
5 projects · most recent 05/19/2026
Water/Sanitary
FiledStatusContractorScope
05/19/2026Signed-offG. C. PLBG & HTG INCWater/Sanitary
06/06/2025Signed-offG. C. PLBG & HTG INCWater/Sanitary
02/16/2025——Water/Sanitary
11/08/2023Signed-offG. C. PLBG & HTG INCWater/Sanitary
09/19/2023Permit IssuedAVON PLBG & HTG INCWater/Sanitary
14 projects · most recent 04/27/2026
General Wiring
FiledStatusContractorScope
04/27/2026Permit IssuedTITAN ELEC'L & ELEV CONTRGeneral Wiring
07/09/2025Permit IssuedTITAN ELEC'L & ELEV CONTRGeneral Wiring
06/12/2024CompleteJTE ELECTRICAL SERVICESGeneral Wiring
01/04/2024CompleteSALVATORE CAMPISI & SONSGeneral Wiring
08/30/2023Permit IssuedASKO ELEC CONST & MAIN INGeneral Wiring
06/06/2023CompleteARC POWER ELECL CONTS INCGeneral Wiring
12/14/2022CompleteSALVATORE CAMPISI & SONSGeneral Wiring
11/28/2022CompleteARC POWER ELECL CONTS INCGeneral Wiring
03/23/2022CompleteALL WAYS ELECTRIC CORP.W—
02/21/2020Complete5 J'S ELECTL CONTS CORP—
06/17/2019CompletePHILIP A. ROBINSONGeneral Wiring
12/06/2018Permit IssuedAKEEA ELECTRIC INCGeneral Wiring
09/06/2018Permit IssuedGMC ELECTRICAL CORPGeneral Wiring
12/29/2017Permit IssuedY.S ELECTRICGeneral Wiring
1 project · most recent 05/18/2026
Steel Concrete
FiledStatusContractorScope
05/18/2026Permit IssuedSARK FLOORING LLCSteel, Concrete
▾Field Inspections (DOB CAP) — 35
DateTypeResultReport
07/13/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/13/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/13/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/08/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/18/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/11/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/09/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/08/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/04/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/04/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/24/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/07/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/28/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/25/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/09/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/07/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/07/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/06/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
06/04/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
04/23/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
04/19/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
03/27/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/14/2025Pass-Final CND-Occupancy InspectionPassView ↗
02/12/2025Fail-Final CND-Occupancy InspectionFailView ↗
02/10/2025Fail-Final CND-Occupancy InspectionFailView ↗
Latest 25 of 35.
▾Special Inspection Requirements (DOB NOW) — 93
DateRequirementInspectorRole
06/08/2026HVAC-R and service water heating equipmentSUNGBOM YIenergy_progress
06/08/2026HVAC-R and service water piping design and insulationSUNGBOM YIenergy_progress
06/08/2026HVAC-R and service water heating system controlsSUNGBOM YIenergy_progress
06/08/2026Energy Code Compliance InspectionsSUNGBOM YIprogress
06/08/2026FinalSEOK HUN KIMprogress
06/08/2026Mechanical SystemsSUNGBOM YIspecial
06/08/2026Fire-Resistant Penetrations and JointsSUNGBOM YIspecial
06/08/2026Maintenance informationSUNGBOM YIenergy_progress
03/31/2026Shutoff dampersWalter Gormanenergy_progress
03/31/2026HVAC-R and service water piping design and insulationWalter Gormanenergy_progress
03/31/2026FinalWalter Gormanprogress
03/31/2026Energy Code Compliance InspectionsWalter Gormanprogress
03/31/2026Mechanical SystemsWalter Gormanspecial
03/31/2026Maintenance informationWalter Gormanenergy_progress
03/31/2026HVAC-R and service water heating equipmentWalter Gormanenergy_progress
03/31/2026HVAC-R and service water heating system controlsWalter Gormanenergy_progress
02/26/2026Structural Stability – Alterations of existing buildingsJASON APTOWITZspecial
02/26/2026FinalJASON APTOWITZprogress
02/26/2026MasonryJASON APTOWITZspecial
04/30/2025Sprinkler SystemsELLIOTT HARDIEspecial
04/30/2025FinalAnthony Nicholasprogress
10/15/2024Standpipe SystemsStephen Shishkospecial
10/07/2024Standpipe SystemsStephen Shishkospecial
05/23/2024Energy Code Compliance InspectionsWilliam Ryanprogress
05/23/2024Lighting controlsWilliam Ryanenergy_progress
Latest 25 of 93.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Abs Partners RealestateOfficeFloor 19
Project M00945641 Alteration · Permit Entire · 11/10/2023
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 1,931 on file (BIS + DOB NOW)
▸Plans & Drawings42
▸DOB NOWPlans/Sketch34
09/03/2026M00625913-I1Request digital key ↗
09/02/2026M00668400-I1Request digital key ↗
09/02/2026M00729683-I1Request digital key ↗
Showing 3 of 34 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/03/2026M00243398-I1Request digital key ↗
08/15/2026M00243398-P1Request digital key ↗
08/15/2026M00243398-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
09/03/2026M00243468-I1Request digital key ↗
08/15/2026M00243468-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
09/03/2026M00243468-I1Request digital key ↗
08/15/2026M00243468-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00320656-I1Request digital key ↗
▸Applications & Permits349
▸BISPLAN / WORK APPROVAL APPLICATION196
09/24/2025124039432Open ↗
09/17/2025124039432Open ↗
08/12/2025124039432Open ↗
Showing 3 of 196 on file for this type
▸BISWORK PERMIT APPLICATION151
08/19/2021123859903Open ↗
06/12/2020123142429Open ↗
02/12/2020123787740Open ↗
Showing 3 of 151 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Zoning, Tax Lot & Property Records3
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
09/26/2025124039432Open ↗
11/07/2022123573114Open ↗
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
03/20/2024123573123Open ↗
▸Seals & Professional Certifications503
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION232
03/16/2020123859903Open ↗
03/16/2020123859903Open ↗
03/02/2020123678653Open ↗
Showing 3 of 232 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT69
12/04/2019123787740Open ↗
11/14/2019123697446Open ↗
10/17/2019123787740Open ↗
Showing 3 of 69 on file for this type
▸DOB NOWProgress Inspector Seal & Signature49
09/28/2026M00945641-I1Open ↗
09/28/2026M00945641-I1Open ↗
09/28/2026M00945641-I1Open ↗
Showing 3 of 49 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST48
11/14/2019123697446Open ↗
10/17/2019123787740Open ↗
05/02/2019123859903Open ↗
Showing 3 of 48 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature40
09/05/2026M00320656-I1Open ↗
09/03/2026M00243398-P1Open ↗
09/03/2026M00243398-P2Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature23
09/28/2026M00945641-I1Open ↗
09/28/2026M00945641-I1Open ↗
09/25/2026M00848849-P1Open ↗
Showing 3 of 23 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸Trade Schedules & Equipment134
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE37
03/10/2020123859903Open ↗
03/06/2020123859903Open ↗
05/02/2019123859903Open ↗
Showing 3 of 37 on file for this type
▸BISSELF-CERT PLUMBING NOTICE31
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 31 on file for this type
▸BISEQUIPMENT USE PERMITS22
02/07/2022123707444Open ↗
02/07/2022123707444Open ↗
02/07/2022123707444Open ↗
Showing 3 of 22 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA16
08/23/2021123001134Open ↗
03/19/2020123838277Open ↗
02/21/2020122117949Open ↗
Showing 3 of 16 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT12
02/07/2022123707444Open ↗
02/07/2022123707444Open ↗
01/27/2022123707444Open ↗
Showing 3 of 12 on file for this type
▸BISSCHEDULE B - PLUMBING10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSIGN HANGER CERTIFICATE4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSPRINKLER/STANDPIPE ELECTRICAL LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISST-1 Street Tree Checklist1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos176
▸BISASBESTOS: CERTIFICATION (DEP ACP5)71
11/14/2019123697446Open ↗
10/17/2019123787740Open ↗
05/02/2019123859903Open ↗
Showing 3 of 71 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report39
09/03/2026M00243398-I1Open ↗
09/03/2026M00243398-P1Open ↗
09/03/2026M00243398-P2Open ↗
Showing 3 of 39 on file for this type
▸DOB NOWOER: Notice to Proceed17
09/02/2026M00729683-I1Open ↗
09/02/2026M00671036-I1Open ↗
09/02/2026M00692271-I1Open ↗
Showing 3 of 17 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸DOB NOWOER: Notice of Satisfaction12
09/02/2026M00671036-I1Open ↗
09/02/2026M00692271-I1Open ↗
08/13/2026M00980984-I1Open ↗
Showing 3 of 12 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED10
11/22/2019123787740Open ↗
11/22/2019123697446Open ↗
05/13/2019123859903Open ↗
Showing 3 of 10 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION4
02/24/2022123859903Open ↗
01/27/2022123707444Open ↗
09/23/2020123787740Open ↗
Showing 3 of 4 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance142
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS82
12/05/2019123787740Open ↗
12/05/2019123787740Open ↗
11/14/2019123697446Open ↗
Showing 3 of 82 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS29
09/23/2020123787740Open ↗
Showing 1 of 29 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY14
02/24/2022123859903Open ↗
01/27/2022123707444Open ↗
09/23/2020123787740Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)3
02/24/2022123859903Open ↗
01/27/2022123707444Open ↗
08/06/2020123697446Open ↗
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
09/02/2026M00671036-I1Open ↗
▸Inspections & Test Reports44
▸BISTECHNICAL REPORT: RESPONSIBILITY36
02/28/2022123859903Open ↗
02/28/2022123859903Open ↗
02/24/2022123859903Open ↗
Showing 3 of 36 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISHYDRO FLOW TEST LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs138
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST79
02/28/2022123859903Open ↗
01/31/2022123707444Open ↗
12/08/2021140546069Open ↗
Showing 3 of 79 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION27
07/29/2025124039432Open ↗
12/05/2019123787740Open ↗
Showing 2 of 27 on file for this type
▸BISADMINISTRATIVE OBJECTIONS25
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 25 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE7
11/07/2022123573114Open ↗
Showing 1 of 7 on file for this type
▸Cost, Insurance & Ownership186
▸BISCOST AFFIDAVIT178
02/22/2021122638155Open ↗
09/30/2020123787740Open ↗
09/30/2020123787740Open ↗
Showing 3 of 178 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
08/06/2024123183937Open ↗
02/24/2022123859903Open ↗
01/27/2022123707444Open ↗
Showing 3 of 4 on file for this type
▸BISDEPT OF FINANCE VERIFICATION4
07/29/2025124039432Open ↗
03/19/2024123573123Open ↗
03/19/2024123573123Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms192
▸BISEFILING COVER SHEET99
07/29/2025124039432Open ↗
03/19/2024123573123Open ↗
10/12/2022123573114Open ↗
Showing 3 of 99 on file for this type
▸BISBOROUGH INTAKE FORM39
07/29/2025124039432Open ↗
03/19/2020123838277Open ↗
03/06/2020123859903Open ↗
Showing 3 of 39 on file for this type
▸BISADDITIONAL INFORMATION33
01/14/2022123707444Open ↗
10/05/2021123707444Open ↗
09/13/2021123859903Open ↗
Showing 3 of 33 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸Other Documents14
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION10
09/26/2025124039432Open ↗
09/26/2025124039432Open ↗
09/26/2025124039432Open ↗
Showing 3 of 10 on file for this type
▸BISPLOT DIAGRAM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
09/26/2025124039432Open ↗
▸BISFIRE SUPP ANSUL APPROVL: FD-FSS1
On file, but not among the 200 most recently loaded documents for this source.