| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/10/2024 | $1.5M | — | Private party → Private party | $547/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 1 | 10/10/2025 |
| BARRY STRUCTURAL ENGINEERING, PLLC | 1 | 07/31/2024 |
| MALETZ DESIGN | 2 | 06/26/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| EPAC BUILDING CONSULTING INC | 6 | 03/21/2026 |
| BROOKLYN SOLARWORKS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MAMC CONSULTING REPS LLC | General Contractor | 3 | 03/21/2026 |
| BROOKLYN SOLARWORKS LLC | General Contractor | 1 | 04/09/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 1 | 10/10/2025 |
| BARRY STRUCTURAL ENGINEER | 749 | 2 | 07/31/2024 |
| MALETZ DESIGN | 3250 | 2 | 06/26/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | BROOKLYN SOLARWORKS LLC | 10/20/2025 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 08/08/2024 |
| DOB NOW | General Construction | Permit Issued | MAMC CONSULTING REPS LLC | 08/07/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2024 | Signed-off | JMW PLUMBING, INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/01/2025 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| 09/04/2024 | Complete | RIVIERA ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2024 | Signed-off | JMW PLUMBING, INC | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/21/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/17/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/13/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/01/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 10/01/2025 | Final | NARESH MAHANGU | progress |
| 10/01/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 10/01/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 10/01/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 07/15/2024 | Structural Steel - High Strength Bolting | MICHAEL BARRY | special |
| 07/15/2024 | Structural Steel - Welding | MICHAEL BARRY | special |
| 07/15/2024 | Structural Stability – Alterations of existing buildings | MICHAEL BARRY | special |
| 07/15/2024 | Structural Steel - Details | MICHAEL BARRY | special |
| 07/15/2024 | Final | MICHAEL BARRY | progress |
| 07/08/2024 | Structural Stability – Alterations of existing buildings | MICHAEL BARRY | special |
| 06/26/2024 | Fire-Resistant Penetrations and Joints | ELIZABETH MALETZ | special |
| 06/26/2024 | Energy Code Compliance Inspections | ELIZABETH MALETZ | progress |
| 06/13/2024 | Energy Code Compliance Inspections | ELIZABETH MALETZ | progress |
| 06/13/2024 | Fenestration and door U-factor and product ratings | ELIZABETH MALETZ | energy_progress |
| 06/13/2024 | Interior lighting power | ELIZABETH MALETZ | energy_progress |
| 06/13/2024 | Lighting controls | ELIZABETH MALETZ | energy_progress |
| 06/13/2024 | Lighting in dwelling units | ELIZABETH MALETZ | energy_progress |
| 06/13/2024 | Fenestration air leakage | ELIZABETH MALETZ | energy_progress |
| 06/13/2024 | Fire-Resistant Penetrations and Joints | ELIZABETH MALETZ | special |
| 06/13/2024 | Final | ELIZABETH MALETZ | progress |