| Owner | Filings | Most Recent |
|---|---|---|
| NORTHWELL HEALTH | 96 | 09/13/2026 |
| KINGS GROUP NY | 19 | 07/08/2026 |
| LONG ISLAND JEWISH HOSPITAL | 20 | 03/22/2026 |
| LI JEWISH HOSPITAL | 1 | 03/22/2026 |
| PLANT ENGINEERING & MAINT | 2 | 03/21/2026 |
| NORTHWELL HEALTH SYSTEM | 1 | 03/21/2026 |
| NORTHSHORE L I J HEALTH SYSTEM | 155 | 03/21/2026 |
| N SHORE LIJ HEALTH SYSTEM | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GILSANZ MURRAY STEFICEK LLP | 4 | 06/02/2026 |
| PAMELA A. SMITH | 12 | 06/01/2026 |
| LORING CONSULTING ENGINEERS, INC. | 12 | 06/01/2026 |
| BURNS ENGINEERING, PC | 4 | 04/27/2026 |
| RIMKUS | 2 | 02/03/2026 |
| LIZARDOS ENGINEERING | 13 | 09/02/2025 |
| NYMS CONSULTING, LLC | 1 | 02/12/2025 |
| AKF ENGINEERS, LLP | 2 | 08/01/2024 |
| THE MCGUIRE GROUP ARCHITECTS | 1 | 07/08/2024 |
| THE EIPEL ENGINEERING GROUP, D.P.C. | 1 | 07/03/2024 |
| ABCO-PEERLESS ENGINEERING, P.C. | 2 | 06/03/2024 |
| DM ENGINEERS PLLC | 1 | 09/05/2023 |
| CASE ENGINEERING, INC. | 3 | 05/02/2023 |
| E/F/H ARCHITECTS, P.C. | 1 | 03/16/2023 |
| COMBINED RESOURCES CONSULTING & DE | 1 | 11/01/2022 |
| DOSHI CONSULTANT | 1 | 11/01/2022 |
| DESIGN FORUM ARCHITECTS, INC., P.C. | 2 | 10/26/2022 |
| MOHAMMAD AHEAD, PE | 1 | 02/02/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| UPRIGHT EXPEDITERS | 66 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 10 | 03/21/2026 |
| SKYLINE ACCESS | 1 | 03/21/2026 |
| EMPIRE CITY CONSULTANTS, INC. | 14 | 03/21/2026 |
| STRELING ENGINEERING SERVICES P C | 2 | 03/21/2026 |
| KMA DESIGNS LLC | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KINGS GROUP NY CORP | General Contractor | 14 | 07/08/2026 |
| THE WHITING-TURNER CONTRA | General Contractor | 12 | 07/08/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 10 | 07/08/2026 |
| GILBANE BUILDING COMPANY | General Contractor | 8 | 07/08/2026 |
| ALLIANCE PLUMBING CORP | Plumbing | 7 | 07/08/2026 |
| BOTTO MECHANICAL CORP | General Contractor | 5 | 04/09/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 4 | 08/26/2026 |
| HUNTER ROBERTS CONSTRUCTION | General Contractor | 4 | 07/30/2026 |
| PLATINUM SPECIALTY SERVIC | General Contractor | 4 | 07/08/2026 |
| NYC FIRE SPRINKLER CORP | Fire Protection | 4 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 3 | 07/08/2026 |
| JOSEPH BRAMAN | Electrical | 3 | 03/21/2026 |
| CONSIGLI CONSTRUCTION CO | General Contractor | 3 | 07/08/2026 |
| EMPIRE GENERAL CONTRACTIN | General Contractor | 3 | 07/08/2026 |
| PREMIER MECHANICAL SERVIC | General Contractor | 3 | 03/21/2026 |
| MACCARONE PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| CARRIER CORP | General Contractor | 2 | 03/21/2026 |
| LORELLI, VINCENT | Electrical | 2 | 03/21/2026 |
| COMPARATO, LOUIS | Electrical | 2 | 03/21/2026 |
| ALCHEMY DEVELOPMENT | General Contractor | 2 | 07/08/2026 |
| SHORT, HENRY | Electrical | 1 | 03/21/2026 |
| HIGH QUALITY ELEC.OF NYC | Electrical | 1 | 03/22/2026 |
| HEMSING, ROBERT | Electrical | 1 | 03/21/2026 |
| MACCARONE PLUMBING INC | Fire Protection | 1 | 07/08/2026 |
| S & P CONSTRUCTION MGMT.I | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SONI ENGINEERING CONSULTI | 9819 | 1 | 06/03/2026 |
| CC@A ENGINEERING P.C | 1854 | 48 | 06/02/2026 |
| NYMS CONSULTING, LLC | 8442 | 1 | 02/12/2025 |
| WAYPOINT CONSULTING GROUP | 6175 | 3 | 10/26/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | CURRENT FIRE PROTECTION INC | 10/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | SIRINA FIRE PROT CORP | 08/25/2026 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 07/29/2026 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 07/28/2026 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 07/28/2026 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 07/27/2026 |
| DOB NOW | Plumbing | Permit Issued | ALLIANCE PLUMBING CORP | 07/02/2026 |
| DOB NOW | Plumbing | Permit Issued | NYC FIRE SPRINKLER CORP | 07/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 06/24/2026 |
| DOB NOW | Standpipe | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 06/24/2026 |
| DOB NOW | General Construction | Permit Issued | THE WHITING-TURNER CONTRA | 06/24/2026 |
| DOB NOW | Structural | Permit Issued | THE WHITING-TURNER CONTRA | 06/24/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | DNA CONTRACTING LLC | 06/15/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | THE WHITING-TURNER CONTRA | 06/11/2026 |
| DOB NOW | Plumbing | Signed-off | ALLIANCE PLUMBING CORP | 04/28/2026 |
| DOB NOW | General Construction | Permit Issued | CONSIGLI CONSTRUCTION CO | 03/12/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | KINGS GROUP NY CORP | 01/30/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 01/22/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | KINGS GROUP NY CORP | 01/21/2026 |
| DOB NOW | Plumbing | Signed-off | NYC FIRE SPRINKLER CORP | 12/10/2025 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING WMBE | 11/03/2025 |
| DOB NOW | Sprinklers | Signed-off | MACCARONE PLUMBING INC | 09/22/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | BOTTO MECHANICAL CORP | 08/01/2025 |
| DOB NOW | Sprinklers | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 07/29/2025 |
| DOB NOW | Sprinklers | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 07/29/2025 |
| DOB NOW | Structural | Signed-off | THE WHITING-TURNER CONTRA | 07/28/2025 |
| DOB NOW | General Construction | Signed-off | THE WHITING-TURNER CONTRA | 07/21/2025 |
| DOB NOW | Plumbing | Signed-off | CARDOZA PLUMBING WMBE | 04/18/2025 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 04/17/2025 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 04/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | CONSIGLI CONSTRUCTION CO | 04/14/2025 |
| DOB NOW | General Construction | Permit Issued | CONSIGLI CONSTRUCTION CO | 04/11/2025 |
| DOB NOW | Boiler Equipment | Signed-off | AMERICAN BOILER & WELDING | 02/12/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | KINGS GROUP NY CORP | 02/03/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | KINGS GROUP NY CORP | 01/23/2025 |
| DOB NOW | Sprinklers | Signed-off | NYC FIRE SPRINKLER CORP | 11/22/2024 |
| DOB NOW | Sprinklers | Signed-off | MACCARONE PLUMBING INC | 11/21/2024 |
| DOB NOW | Mechanical Systems | Signed-off | BOTTO MECHANICAL CORP | 11/20/2024 |
| DOB NOW | General Construction | Signed-off | THE WHITING-TURNER CONTRA | 11/13/2024 |
| DOB NOW | Structural | Signed-off | THE WHITING-TURNER CONTRA | 10/25/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/26/2025 | Permit Issued | BOTTO MECHANICAL CORP | Air Conditioning Systems, Refrigeration Systems, Ventilation Systems | |
| 03/18/2025 | Permit Issued | CONSIGLI CONSTRUCTION CO | Air Conditioning Systems | Cooling Mitsubishi Electric PUY-A30NHA7 (note this is a 2.5 ton unit) 2 tons · Condensing Unit ×2 PUY-A36NKA7 3 tons · Condensing Unit ×2 Liebert PDX018 5 tons · Crac Unit ×2 |
| 01/02/2020 | Signed-off | CARRIER CORP | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/27/2026 | — | — | 615 heads |
| 04/24/2026 | Permit Issued | SIRINA FIRE PROT CORP | 2,153 heads |
| 04/24/2026 | Permit Issued | CURRENT FIRE PROTECTION I | — |
| 04/20/2026 | — | — | 328 heads |
| 01/29/2026 | Signed-off | NYC FIRE SPRINKLER CORP | 24 heads |
| 09/02/2025 | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 18 heads, 37 outlets |
| 03/18/2025 | Signed-off | SIRINA FIRE PROT CORP | 9 heads, 2 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/29/2026 | Signed-off | MACCARONE PLUMBING INC | Medical Gas, Water/Sanitary |
| 09/02/2025 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| 03/18/2025 | Signed-off | CARDOZA PLUMBING WMBE | Water/Sanitary |
| 10/30/2023 | Permit Issued | M & S MECHANICAL SVCS INC | Gas |
| 05/02/2023 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2026 | Permit Issued | NORTHWELL HEALTHCARE, INC | General Wiring |
| 03/11/2026 | Complete | HATZEL AND BUEHLER, INC | General Wiring |
| 03/10/2026 | Permit Issued | HIGH QUALITY ELEC.OF NYC | — |
| 03/13/2025 | Complete | HATZEL AND BUEHLER, INC | General Wiring |
| 03/12/2025 | Complete | HATZEL AND BUEHLER, INC | General Wiring |
| 01/22/2025 | Complete | DIANE ELECTRIC INC. | General Wiring |
| 10/17/2024 | Complete | HIGH QUALITY ELECTRIC OF | — |
| 07/22/2024 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 03/13/2024 | Complete | NORTHWELL HEALTHCARE, INC | — |
| 02/21/2024 | Complete | NORTHWELL HEALTHCARE, INC | — |
| 02/21/2024 | Complete | NORTHWELL HEALTHCARE, INC | — |
| 10/16/2023 | Complete | HATZEL AND BUEHLER, INC | General Wiring |
| 07/07/2023 | Permit Issued | HATZEL AND BUEHLER, INC | General Wiring |
| 01/10/2023 | Complete | ANCO ELECTL CONTCTNG INC | General Wiring |
| 08/30/2022 | Permit Issued | NEE ELECTRICAL, LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/03/2026 | Permit Issued | KINGS GROUP NY CORP | Scaffold, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Permit Issued | DNA CONTRACTING LLC | Suspended Scaffold (SC) |
| 01/14/2026 | Permit Issued | SKYLINE ACCESS LLC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/15/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/19/2026 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 06/19/2026 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 06/19/2026 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 06/19/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/01/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/27/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 01/13/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/15/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/15/2025 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 10/15/2025 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 10/15/2025 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/25/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 06/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/16/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/16/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 05/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/28/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/22/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/01/2026 | Post-installed Anchors | nayan soni | special |
| 06/01/2026 | Alternative Materials - OTCR Buildings Bulletin Number | nayan soni | special |
| 05/27/2026 | Maintenance information | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | HVAC-R and service water heating equipment | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | HVAC-R and service water piping design and insulation | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | Shutoff dampers | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | Energy Code Compliance Inspections | CHAROULIS CHARALAMBOUS | progress |
| 05/27/2026 | Fire-Resistant Penetrations and Joints | CHAROULIS CHARALAMBOUS | special |
| 05/27/2026 | HVAC-R and service water heating system controls | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | Post-installed Anchors | CHAROULIS CHARALAMBOUS | special |
| 05/18/2026 | Structural Steel - Details | CHAROULIS CHARALAMBOUS | special |
| 05/18/2026 | Structural Steel - High Strength Bolting | CHAROULIS CHARALAMBOUS | special |
| 05/18/2026 | Structural Steel - Welding | CHAROULIS CHARALAMBOUS | special |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | CHAROULIS CHARALAMBOUS | special |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | CHAROULIS CHARALAMBOUS | special |
| 05/12/2026 | Post-installed Anchors | CHAROULIS CHARALAMBOUS | special |
| 05/06/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 05/06/2026 | Sprinkler Systems | CHAROULIS CHARALAMBOUS | special |
| 05/06/2026 | Mechanical Systems | CHAROULIS CHARALAMBOUS | special |
| 05/05/2026 | Lighting controls | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/05/2026 | Energy Code Compliance Inspections | CHAROULIS CHARALAMBOUS | progress |
| 05/05/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 05/05/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 05/05/2026 | Interior lighting power | CHAROULIS CHARALAMBOUS | energy_progress |
| 04/08/2026 | Post-installed Anchors | CHAROULIS CHARALAMBOUS | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Long Island Jewish Medical Center | Medical / Healthcare | Floors 1, 2 | Project Q01397668 Project Q01397604 |
| Northwell Health | Medical / Healthcare | Sub-basement, Basement, Ground, Floors 1, 2 | Project Q01372794 Project Q01162581 Project Q00917732 Project Q00919163 Project Q00874244 Project Q00837129 Project Q00840003 |
| Northwell | W Health" | SM | LONG ISLAND JEWISH MEDICAL | CENTER | Medical / Healthcare | Floor 2, Roof | Project Q01372018 Project Q01372753 Project Q01219392 Project Q01219230 Project Q01121439 Project Q01121555 |
| Northwell LIJ Hospital | Medical / Healthcare | Floor 1 | Project Q00833222 |