| Owner | Filings | Most Recent |
|---|---|---|
| North Shore/Lij Health Systems | 300 | 10/13/2026 |
| Long Island Jewish Hospital | 6 | 03/22/2026 |
| Plant Engineering & Maintenance | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MD Tohfaz Uddin | 1 | 10/08/2026 |
| Gilsanz Murray Steficek | 4 | 06/02/2026 |
| Pamela A. Smith | 12 | 06/01/2026 |
| Loring Consulting Engineers | 12 | 06/01/2026 |
| Burns Engineering | 4 | 04/27/2026 |
| Rimkus | 2 | 02/03/2026 |
| Lizardos Engineering | 13 | 09/02/2025 |
| NYMS Consulting | 1 | 02/12/2025 |
| AKF Engineers | 2 | 08/01/2024 |
| The McGuire Group Architects | 1 | 07/08/2024 |
| The Eipel Engineering Group | 1 | 07/03/2024 |
| Abco-Peerless Engineering | 2 | 06/03/2024 |
| DM Associates | 1 | 09/05/2023 |
| Case Engineering | 3 | 05/02/2023 |
| E & M Associates | 1 | 03/16/2023 |
| Combined Resources Consulting & de | 1 | 11/01/2022 |
| Doshi Consultant | 1 | 11/01/2022 |
| Design Forum Architects | 2 | 10/26/2022 |
| Mohammad Ahead, PE | 1 | 02/02/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Upright Expediters | 66 | 03/21/2026 |
| Construction Permit Services | 10 | 03/21/2026 |
| Skyline Access | 1 | 03/21/2026 |
| Empire City Consultants | 14 | 03/21/2026 |
| Streling Engineering Services P | 2 | 03/21/2026 |
| Kma Designs | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Kings Group NY | Scaffold | 14 | 07/08/2026 |
| The Whiting-Turner Contracting | General Contractor | 12 | 07/08/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 10 | 07/08/2026 |
| Gilbane Building Company | General Contractor | 8 | 07/08/2026 |
| Alliance Plumbing | Plumbing | 7 | 07/08/2026 |
| Botto Mechanical | specialty_contractor | 5 | 04/09/2026 |
| Sirina Fire Protection | Fire Protection | 4 | 08/26/2026 |
| Hunter Roberts Construction | General Contractor | 4 | 07/30/2026 |
| Platinum Specialty Services | General Contractor | 4 | 07/08/2026 |
| NYC Fire Sprinkler | Fire Protection | 4 | 07/08/2026 |
| Premier Mechanical Services | specialty_contractor | 3 | 03/21/2026 |
| Empire General Contracting | General Contractor | 3 | 07/08/2026 |
| Consigli Construction Co | General Contractor | 3 | 07/08/2026 |
| Current Fire Protection | Fire Protection | 3 | 10/09/2026 |
| Par Plumbing Co | Plumbing | 3 | 07/08/2026 |
| Alchemy Development | General Contractor | 2 | 07/08/2026 |
| Maccarone Plumbing | Plumbing | 2 | 07/08/2026 |
| Carrier | General Contractor | 2 | 03/21/2026 |
| Crown Mark Electrical Contractors | Electrical | 2 | 03/21/2026 |
| Weissberg Rudolph | Electrical | 1 | 03/21/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 1 | 03/21/2026 |
| G.F. Sheridan | Fire Protection | 1 | 03/21/2026 |
| A.S.R. Electrical Contracting | Electrical | 1 | 03/21/2026 |
| Denino Electric Construction | Electrical | 1 | 03/21/2026 |
| Dooley Electric Co | Electrical | 1 | 03/21/2026 |
| Ocgp | General Contractor | 1 | 07/08/2026 |
| Northwell Healthcare | Electrical | 1 | 03/22/2026 |
| Eagle Scaffolding Services | Scaffold | 1 | 10/09/2026 |
| High Quality Electric of NYC | Electrical | 1 | 03/22/2026 |
| Maccarone Plumbing | Fire Protection | 1 | 07/08/2026 |
| M & S Mechanical Services | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Soni Engineering Consulting | 9819 | 1 | 06/03/2026 |
| CC@A Engineering | 1854 | 48 | 06/02/2026 |
| NYMS Consulting | 8442 | 1 | 02/12/2025 |
| Waypoint Consulting Group | 6175 | 3 | 10/26/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | Eagle Scaffolding Services | 10/08/2026 |
| DOB NOW | Sprinklers | Permit Issued | Current Fire Protection | 10/07/2026 |
| DOB NOW | Sprinklers | Permit Issued | Current Fire Protection | 10/07/2026 |
| DOB NOW | Sprinklers | Permit Issued | Current Fire Protection | 10/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | Sirina Fire Protection | 08/25/2026 |
| DOB NOW | General Construction | Permit Issued | Hunter Roberts Construction | 07/29/2026 |
| DOB NOW | General Construction | Permit Issued | Hunter Roberts Construction | 07/28/2026 |
| DOB NOW | General Construction | Permit Issued | Hunter Roberts Construction | 07/28/2026 |
| DOB NOW | General Construction | Permit Issued | Hunter Roberts Construction | 07/27/2026 |
| DOB NOW | Plumbing | Permit Issued | Alliance Plumbing | 07/02/2026 |
| DOB NOW | Sprinklers | Permit Issued | NYC Fire Sprinkler | 07/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | Abco-Peerless Sprinkler | 06/24/2026 |
| DOB NOW | Structural | Permit Issued | The Whiting-Turner Contracting | 06/24/2026 |
| DOB NOW | Standpipe | Permit Issued | Abco-Peerless Sprinkler | 06/24/2026 |
| DOB NOW | General Construction | Permit Issued | The Whiting-Turner Contracting | 06/24/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | DNA Contracting | 06/15/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | The Whiting-Turner Contracting | 06/11/2026 |
| DOB NOW | Plumbing | Signed-off | Alliance Plumbing | 04/28/2026 |
| DOB NOW | General Construction | Permit Issued | Consigli Construction Co | 03/12/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Kings Group NY | 01/30/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | Skyline Restoration | 01/22/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Kings Group NY | 01/21/2026 |
| DOB NOW | Sprinklers | Signed-off | NYC Fire Sprinkler | 12/10/2025 |
| DOB NOW | Plumbing | Signed-off | Cardoza Plumbing Wmbe | 11/03/2025 |
| DOB NOW | Plumbing | Signed-off | Maccarone Plumbing | 09/22/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Botto Mechanical | 08/01/2025 |
| DOB NOW | Standpipe | Permit Issued | Abco-Peerless Sprinkler | 07/29/2025 |
| DOB NOW | Sprinklers | Permit Issued | Abco-Peerless Sprinkler | 07/29/2025 |
| DOB NOW | Structural | Signed-off | The Whiting-Turner Contracting | 07/28/2025 |
| DOB NOW | General Construction | Signed-off | The Whiting-Turner Contracting | 07/21/2025 |
| DOB NOW | Plumbing | Signed-off | Cardoza Plumbing Wmbe | 04/18/2025 |
| DOB NOW | Standpipe | Signed-off | Sirina Fire Protection | 04/17/2025 |
| DOB NOW | Sprinklers | Signed-off | Sirina Fire Protection | 04/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Consigli Construction Co | 04/14/2025 |
| DOB NOW | General Construction | Permit Issued | Consigli Construction Co | 04/11/2025 |
| DOB NOW | Boiler Equipment | Signed-off | American Boiler & Welding | 02/12/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | Kings Group NY | 02/03/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | Kings Group NY | 01/23/2025 |
| DOB NOW | Sprinklers | Signed-off | NYC Fire Sprinkler | 11/22/2024 |
| DOB NOW | Plumbing | Signed-off | Maccarone Plumbing | 11/21/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/26/2025 | Permit Issued | Botto Mechanical | Air Conditioning Systems, Refrigeration Systems, Ventilation Systems | |
| 03/18/2025 | Permit Issued | Consigli Construction Co | Air Conditioning Systems | Cooling Mitsubishi Electric PUY-A30NHA7 (note this is a 2.5 ton unit) 2 tons · Condensing Unit ×2 PUY-A36NKA7 3 tons · Condensing Unit ×2 Liebert PDX018 5 tons · Crac Unit ×2 |
| 01/02/2020 | Signed-off | Carrier | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/27/2026 | Permit Issued | Current Fire Protection I | 615 heads |
| 04/24/2026 | Permit Issued | Current Fire Protection I | — |
| 04/24/2026 | Permit Issued | Sirina Fire Protection | 2,153 heads |
| 04/20/2026 | Permit Issued | Current Fire Protection I | 328 heads |
| 01/29/2026 | Signed-off | NYC Fire Sprinkler | 24 heads |
| 09/02/2025 | Permit Issued | Abco-Peerless Sprinkler | 18 heads, 37 outlets |
| 03/18/2025 | Signed-off | Sirina Fire Protection | 9 heads, 2 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/29/2026 | Signed-off | Maccarone Plumbing | Medical Gas, Water/Sanitary |
| 09/02/2025 | Signed-off | Par Plumbing Co | Water/Sanitary |
| 03/18/2025 | Signed-off | Cardoza Plumbing Wmbe | Water/Sanitary |
| 10/30/2023 | Permit Issued | M & S Mechanical Services | Gas |
| 05/02/2023 | Signed-off | Par Plumbing Co | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2026 | Complete | Northwell Healthcare | General Wiring |
| 03/11/2026 | Complete | Hatzel and Buehler | General Wiring |
| 03/10/2026 | Permit Issued | High Quality Electric of NYC | — |
| 03/13/2025 | Complete | Hatzel and Buehler | General Wiring |
| 03/12/2025 | Complete | Hatzel and Buehler | General Wiring |
| 01/22/2025 | Complete | Diane Electric | General Wiring |
| 10/17/2024 | Complete | High Quality Electric of | — |
| 07/22/2024 | Complete | E-J Electric Installation Co | General Wiring |
| 03/13/2024 | Complete | Northwell Healthcare | — |
| 02/21/2024 | Complete | Northwell Healthcare | — |
| 02/21/2024 | Complete | Northwell Healthcare | — |
| 10/16/2023 | Complete | Hatzel and Buehler | General Wiring |
| 07/07/2023 | Permit Issued | Hatzel and Buehler | General Wiring |
| 01/10/2023 | Complete | Anco Electl Contctng | General Wiring |
| 08/30/2022 | Permit Issued | Nee Electrical | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/03/2026 | Permit Issued | Kings Group NY | Scaffold, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Permit Issued | DNA Contracting | Suspended Scaffold (SC) |
| 01/14/2026 | Permit Issued | Skyline Access | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/31/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/19/2026 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 06/19/2026 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 06/19/2026 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 06/19/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/01/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/27/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 01/13/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/15/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/15/2025 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 10/15/2025 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 10/15/2025 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/25/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 06/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/16/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/16/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 05/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/28/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/22/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/20/2025 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 03/20/2025 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/01/2026 | Alternative Materials - OTCR Buildings Bulletin Number | nayan soni | special |
| 06/01/2026 | Post-installed Anchors | nayan soni | special |
| 05/27/2026 | Energy Code Compliance Inspections | CHAROULIS CHARALAMBOUS | progress |
| 05/27/2026 | HVAC-R and service water heating system controls | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | Fire-Resistant Penetrations and Joints | CHAROULIS CHARALAMBOUS | special |
| 05/27/2026 | HVAC-R and service water heating equipment | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | Maintenance information | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | Shutoff dampers | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | HVAC-R and service water piping design and insulation | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/27/2026 | Post-installed Anchors | CHAROULIS CHARALAMBOUS | special |
| 05/18/2026 | Structural Steel - High Strength Bolting | CHAROULIS CHARALAMBOUS | special |
| 05/18/2026 | Structural Steel - Details | CHAROULIS CHARALAMBOUS | special |
| 05/18/2026 | Structural Steel - Welding | CHAROULIS CHARALAMBOUS | special |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | CHAROULIS CHARALAMBOUS | special |
| 05/12/2026 | Post-installed Anchors | CHAROULIS CHARALAMBOUS | special |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | CHAROULIS CHARALAMBOUS | special |
| 05/06/2026 | Mechanical Systems | CHAROULIS CHARALAMBOUS | special |
| 05/06/2026 | Sprinkler Systems | CHAROULIS CHARALAMBOUS | special |
| 05/06/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 05/05/2026 | Energy Code Compliance Inspections | CHAROULIS CHARALAMBOUS | progress |
| 05/05/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 05/05/2026 | Lighting controls | CHAROULIS CHARALAMBOUS | energy_progress |
| 05/05/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 05/05/2026 | Interior lighting power | CHAROULIS CHARALAMBOUS | energy_progress |
| 04/08/2026 | Fire-Resistant Penetrations and Joints | CHAROULIS CHARALAMBOUS | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Northwell Health | Medical / Healthcare | Entire building | Project Q01397668 Project Q01397604 Project Q01397913 Project Q01397925 Project Q01371447 Project Q01372794 Project Q01372018 Project Q01371454 Project Q01371463 Project Q01372753 Project Q01219392 Project Q01219210 |
| Long Island Jewish NS-lid Healt H System | Medical / Healthcare | Sub-basement, Floor 1 | Project Q01045913 |
| LIJ Medical Center | Medical / Healthcare | Floor 1 | Project Q08031707 Project Q08031806 |