| Owner | Filings | Most Recent |
|---|---|---|
| MIDO REALTY INC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CKL ENGINEERING | 4 | 08/20/2026 |
| SHARON ENGINEERING, P.C | 4 | 04/28/2026 |
| CHUN ENGINEERING CONSULTANT PLLC | 6 | 07/01/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| CAVALRY LLC | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HI-TOWER CONTRACTORS INC | General Contractor | 5 | 08/25/2026 |
| CAVALRY LLC | General Contractor | 4 | 03/21/2026 |
| CHOICEPRO INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHUN ENGINEERING CONSULTA | 9605 | 5 | 04/28/2026 |
| MUNICIPAL TESTING LABORAT | 230 | 1 | 04/23/2026 |
| DAL H CHUN ENGINEER PC | 1972 | 3 | 10/09/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | HI-TOWER CONTRACTORS INC | 08/24/2026 |
| DOB NOW | General Construction | Permit Issued | HI-TOWER CONTRACTORS INC | 08/21/2026 |
| DOB NOW | Support of Excavation | Permit Issued | HI-TOWER CONTRACTORS INC | 08/20/2026 |
| DOB NOW | Structural | Permit Issued | HI-TOWER CONTRACTORS INC | 08/20/2026 |
| DOB NOW | Construction Fence | Permit Issued | HI-TOWER CONTRACTORS INC | 06/22/2026 |
| DOB NOW | Mechanical Systems | Signed-off | CAVALRY LLC | 10/31/2024 |
| DOB NOW | Plumbing | Signed-off | CHOICEPRO INC | 07/30/2024 |
| DOB NOW | General Construction | Signed-off | CAVALRY LLC | 07/24/2024 |
| BIS | PL | ISSUED | PLUMBING PLBG & PLBG CORP | 05/28/2013 |
| BIS | PL | ISSUED | WNW & SONS PLBG & HTG INC | 07/13/2012 |
| BIS | OT | ISSUED | GALA J CONSTRUCTION INC | 07/02/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2024 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Permit Issued | HI-TOWER CONTRACTORS INC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Permit Issued | HI-TOWER CONTRACTORS INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/18/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/16/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/14/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/15/2026 | Concrete - Cast-In-Place | — | special |
| 04/15/2026 | Post-installed Anchors | JAMES CHUN | special |
| 04/15/2026 | Structural Steel - Welding | JAMES CHUN | special |
| 04/15/2026 | Structural Steel - High Strength Bolting | JAMES CHUN | special |
| 04/15/2026 | Structural Steel - Details | JAMES CHUN | special |
| 04/15/2026 | Structural Cold-Formed Steel | JAMES CHUN | special |
| 04/15/2026 | Structural Stability – Alterations of existing buildings | JAMES CHUN | special |
| 04/15/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 03/31/2026 | Seismic Isolation Systems | JAMES CHUN | special |
| 03/31/2026 | Energy Code Compliance Inspections | JAMES CHUN | progress |
| 03/31/2026 | HVAC-R and service water heating equipment | JAMES CHUN | energy_progress |
| 03/31/2026 | HVAC-R and service water piping design and insulation | JAMES CHUN | energy_progress |
| 03/31/2026 | HVAC-R and service water heating system controls | JAMES CHUN | energy_progress |
| 03/31/2026 | Fire-Resistant Penetrations and Joints | JAMES CHUN | special |
| 03/31/2026 | Post-installed Anchors | JAMES CHUN | special |
| 03/31/2026 | Maintenance information | JAMES CHUN | energy_progress |
| 07/01/2025 | Final | Cloud Lee | progress |
| 06/11/2025 | Footing and Foundation | — | progress |
| 06/11/2025 | Final | — | progress |
| 06/09/2025 | Air barrier — testing | JAMES CHUN | energy_progress |
| 06/09/2025 | Electrical motors and elevators | JAMES CHUN | energy_progress |
| 06/09/2025 | Lighting controls | JAMES CHUN | energy_progress |
| 06/09/2025 | Maintenance information | JAMES CHUN | energy_progress |
| 05/20/2025 | Public Assembly Emergency Lighting | JAMES CHUN | progress |
| 05/07/2025 | Interior lighting power | JAMES CHUN | energy_progress |