| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01002850 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 03/05/2024 | 08/24/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor M & M PIPING AND HEATING Filer CAVALRY LLC | Demolition and installation of plumbing fixtures on 2nd and 4th floors as permit plans. |
| B01082610 ↗ | 1017 45 STREET BROOKLYN | Alteration CO | Permit Issued | 07/23/2024 | 08/24/2026 | Contractor HI CREST NY Filer CAVALRY LLC | TEMPORARY FENCE APPLICATION IN CONJUNCTION WITH ALT I APPLICATION B01082610-1 |
| B00433967 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 09/07/2023 | 08/19/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor BUSHBURG BUILDERS LLC | INSTALLATION OF NEW MECHANICAL SYSTEM TO 1ST AND 2ND FLOORS AS PER PLANS |
| B00890238 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 06/15/2023 | 08/19/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor BUSHBURG BUILDERS LLC | NEW WINDOW OPENINGS, ENLARGEMENTS, AND REPLACEMENTS ON THE 2ND FLOOR OF THE COMMERCIAL SPACE, INCLUDING ENLARGING AN EXISTING OPENING AND CR… |
| B00922584 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 08/25/2023 | 08/19/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor BUSHBURG BUILDERS LLC | DEMOLITION OF INTERIOR NO-LOAD BEARING PARTITION AND CEILING ON 2ND FL. BUILD OUT OF NON-BEARING PARTITION WALL. NO CHANGE TO FLOOR AREA, OC… |
| B08051308 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 01/26/2023 | 08/19/2026 | Design STEEL CORE ENGINEERING PLLC Owner BVH Contractor BUSHBURG BUILDERS LLC | Replacing of existing stairs. No change in building bulk, occupancy, use or egress. |
| Name | Projects together | Most recent |
|---|---|---|
| CKL Engineering | 14 | 08/20/2026 |
| HIRANI | 7 | 01/31/2025 |
| KUSHNER STUDIOS | 7 | 04/10/2026 |
| COSTA ARCH & ENG LLP | 4 | 04/24/2026 |
| HANSEN ENGINEERING, PC | 4 | 05/05/2025 |
| ROBERT SIQECA PE | 4 | 04/10/2026 |
| CAVALRY ASSOCIATES | 3 | 05/25/2023 |
| DAMERON ARCHITECTURE PLLC | 3 | 04/07/2026 |
| SHARON ENGINEERING, P.C | 3 | 07/07/2026 |
| GRASSO-MENZIUSO ARCHITECTS | 2 | 06/23/2026 |
| JLS DESIGNS | 2 | 05/11/2026 |
| KOH ARCHITECTURE PLLC | 2 | 02/28/2025 |
| OSTERMIER ARCHITECTURE PLLC | 2 | 02/26/2024 |
| VERSATILE ENGINEERING, P.C. | 2 | 03/12/2025 |
| 2LS CONSULTING ENGINEERING, DPC | 1 | 02/28/2025 |
| AHT ENGINEERING PLLC | 1 | 04/10/2026 |
| BANJI AWOSIKA ARCHITECT P.C. | 1 | 04/18/2023 |
| BCHEN ARCHITECT PLLC | 1 | 08/18/2020 |
| D'ANTONIO CONSULTING ENGINEERS | 1 | 05/30/2023 |
| DERMAN ENGINEERING PLLC | 1 | 06/23/2026 |
| HARDIE & ASSOCIATES CONSULTING ENG. | 1 | 03/11/2025 |
| MICHAEL MUROFF ARCHITECT LLC | 1 | 08/27/2024 |
| NAOMI LANGER STUDIO | 1 | 01/17/2025 |
| PAPER PLANE ARCHITECTURE, PLLC | 1 | 05/10/2024 |
| PINE BUREAU | 1 | 03/11/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| RAYMOND'S PLBG & HTG LLC | 58 | 08/10/2026 |
| CAVALRY LLC | 26 | 08/20/2026 |
| NORTHBAY BUILDERS CORP | 17 | 01/25/2022 |
| GIRON CONTRACTING INC | 15 | 05/11/2026 |
| MG DECORATIONS LTD | 14 | 07/21/2025 |
| JANA BUILDERS CORP | 13 | 04/17/2026 |
| ALL PRO PLBG & HTG INC | 10 | 08/20/2026 |
| AMC PLBG, HTG & CLNG, INC | 8 | 02/24/2026 |
| METHOD GENERAL CONTRACTOR | 8 | 04/10/2026 |
| GRANITE ENVIRONMENT, LLC | 7 | 01/31/2025 |
| BADGER MANAGEMENT INC | 5 | 07/14/2025 |
| CONSTRUCTION XPERT INC | 5 | 06/23/2026 |
| P.H. WORKS INC | 5 | 04/10/2026 |
| VILLAGE P & H NY INC | 5 | 06/23/2026 |
| ALEF CONSTRUCTION INC | 4 | 04/07/2026 |
| AMERICAN STANDARD P&H COR | 4 | 04/15/2025 |
| BUSHBURG BUILDERS LLC | 4 | 01/31/2025 |
| CREATIVE PLUMBING IN | 4 | 09/17/2025 |
| DAL H CHUN ENGINEER, PC | 4 | 09/08/2025 |
| SAFETY FIRE SPRINKLER COR | 4 | 08/03/2026 |
| T.N.T PLBG & HTG INC | 4 | 01/21/2022 |
| TIGER BUILDING CONSTR LLC | 4 | 06/05/2025 |
| ARIANA CONTRACTING INC | 3 | 08/10/2026 |
| T & T PLUMBING INC | 3 | 03/27/2025 |
| AL-ARSH CONSTRUCTION CORP | 2 | 12/07/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| PLATINUM | 49 | 02/02/2026 |
| PLATINUM REALTY ASSOCIATES | 33 | 08/10/2026 |
| 429 E 12 LLC | 10 | 04/10/2026 |
| BLANK PROPERTY GROUP | 6 | 06/20/2023 |
| BVH | 5 | 04/24/2026 |
| MONDAY MORNING MANAGEMENT | 5 | 04/08/2026 |
| 1189 JEFFERSON LLC | 4 | 06/05/2025 |
| 366 STOCKTON REALTY LLC | 3 | 04/30/2024 |
| BW 450 ST. MARKS, LLC | 3 | 07/05/2022 |
| LAUNDRY CAPITAL | 3 | 08/14/2025 |
| MARCY PLAZA | 3 | 02/24/2026 |
| 234 Schenectady Realty LLC | 2 | 08/05/2025 |
| Bnos Chaya School | 2 | 09/17/2025 |
| EMPIRE EQUITIES | 2 | 06/16/2025 |
| Housing Preservation & Development | 2 | 01/31/2025 |
| IP DREAM HOUSE, LLC | 2 | 07/07/2026 |
| LIBERTY SQR IN OZONE PARK LLC | 2 | 09/05/2023 |
| RK CAPITAL | 2 | 11/01/2024 |
| SHARP MANAGEMENT CORP. | 2 | 01/02/2024 |
| 122 WASHINGTON LLC | 1 | 03/11/2025 |
| 20 RSW, LLC | 1 | 06/23/2026 |
| 255 EAST HOUSTON MANAGER, LLC | 1 | 05/10/2024 |
| 51 HART LLC | 1 | 08/13/2025 |
| 8623 FLATLANDS PROPERTY LLC | 1 | 09/19/2019 |
| AB CAPSTONE BUILDERS CORP | 1 | 02/07/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| CAVALRY LLC | 66 | 08/20/2026 |
| ALISTAS SERVICES LLC | 8 | 08/10/2026 |
| KUSHNER STUDIOS | 6 | 04/10/2026 |
| COSTA ARCHITECTURE & ENGINEERING LL | 5 | 04/24/2026 |
| HOMES R US SALES CORP | 4 | 11/01/2024 |
| JLS DESIGNS | 2 | 05/11/2026 |
| NYC DESIGN FILE | 2 | 04/23/2025 |
| Wai Yee Chan Irrevocable Trust | 2 | 12/18/2025 |
| BIG ORANGE EXPEDITING, INC | 1 | 05/13/2026 |
| BMB BUILDING CONSULTING INC. | 1 | 02/28/2025 |
| CITY EXPEDITING CO LLC | 1 | 08/03/2026 |
| DESIGN STUDIO | 1 | 04/29/2026 |
| GRASSO-MENZIUSO ARCHITECTS | 1 | 06/23/2026 |
| METROPOLIS GROUP INC | 1 | 01/17/2025 |
| SADIE SILVER | 1 | 01/31/2025 |
| TSOLAKI'S EXPEDITING | 1 | 05/10/2024 |
| XPEDITE LLC | 1 | 08/12/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01002850 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 03/05/2024 | 08/24/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor M & M PIPING AND HEATING Filer CAVALRY LLC | Demolition and installation of plumbing fixtures on 2nd and 4th floors as permit plans. |
| B01082610 ↗ | 1017 45 STREET BROOKLYN | Alteration CO | Permit Issued | 07/23/2024 | 08/24/2026 | Contractor HI CREST NY Filer CAVALRY LLC | TEMPORARY FENCE APPLICATION IN CONJUNCTION WITH ALT I APPLICATION B01082610-1 |
| B00433967 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 09/07/2023 | 08/19/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor BUSHBURG BUILDERS LLC | INSTALLATION OF NEW MECHANICAL SYSTEM TO 1ST AND 2ND FLOORS AS PER PLANS |
| B00890238 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 06/15/2023 | 08/19/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor BUSHBURG BUILDERS LLC | NEW WINDOW OPENINGS, ENLARGEMENTS, AND REPLACEMENTS ON THE 2ND FLOOR OF THE COMMERCIAL SPACE, INCLUDING ENLARGING AN EXISTING OPENING AND CR… |
| B00922584 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 08/25/2023 | 08/19/2026 | Design COSTA ARCH & ENG LLP Owner BVH Contractor BUSHBURG BUILDERS LLC | DEMOLITION OF INTERIOR NO-LOAD BEARING PARTITION AND CEILING ON 2ND FL. BUILD OUT OF NON-BEARING PARTITION WALL. NO CHANGE TO FLOOR AREA, OC… |
| B08051308 ↗ | 538 JOHNSON AVENUE BROOKLYN | Alteration | Permit Issued | 01/26/2023 | 08/19/2026 | Design STEEL CORE ENGINEERING PLLC Owner BVH Contractor BUSHBURG BUILDERS LLC | Replacing of existing stairs. No change in building bulk, occupancy, use or egress. |
| Q01170225 ↗ | 201-01 HOLLIS AVENUE QUEENS | ALT-CO - New Building with Existing Elements to Remain | Permit Issued | 01/31/2025 | 08/07/2026 | Design DAL H CHUN ENGINEER PC Contractor BLACK HAMMER CONSTRUCTION Filer DESIGN STUDIO | Subsequent Underpinning filing. No change in use, egress or occupancy. |
| B01186957 ↗ | 234 SCHENECTADY AVENUE BROOKLYN | Alteration | Permit Issued | 07/25/2025 | 07/29/2026 | Design DAL H CHUN ENGINEER PC Contractor SAPPHIRE CONSTRUCTION GR* Filer DAL H CHUN ENGINEER PC | PROPOSED ENLARGEMENT AT FRONT ENTRANCE WITH REPLACEMENT OF NEW ENTRANCE DOOR AND DWELLING UNIT #4 AND #6. RENOVATION TO REPAIR AS PLAN, N… |
| B01117598 ↗ | 344 UTICA AVENUE BROOKLYN | Alteration | Permit Issued | 10/02/2024 | 07/14/2026 | Design DAL H CHUN ENGINEER PC Contractor ARIANA CONTRACTING INC Filer ALISTAS SERVICES LLC | CAP AND REMOVAL OF EXISTING BOILER AND INSTALLATION OF NEW GAS BOILER, 2 NEW GAS HOT WATER HEATER AND NEW GAS LINE FROM UTICA AVENUE. NO CHA… |
| S00958775 ↗ | 697 NORTH RAILROAD AVE STATEN ISLAND | ALT-CO - New Building with Existing Elements to Remain | Permit Issued | 01/09/2024 | 07/06/2026 | Owner IP DREAM HOUSE, LLC Contractor CAVALRY LLC Filer CAVALRY LLC | VERTICAL (ADDIN GONE STORY) AND HORIZONTAL EXTENSION OF A SINGLE FAMILY HOUSE IN CONJUNCTION WITH ALT I S00958775 |
| Q01278154 ↗ | 25-61 31 STREET QUEENS | Alteration | Permit Issued | 09/08/2025 | 06/30/2026 | Design DAL H CHUN ENGINEER PC Contractor DAL H CHUN ENGINEER, PC | PROPOSED TWO FAMILY DWELLING FLOOR JOIST GC WORK AND ST WORK AT FLOOR LEVEL 1 NEW REPLACING FOR DAMAGING BROKEN AND LOAD BEARING WALL REPLAC… |
| Q01374750 ↗ | 35-50 31 STREET QUEENS | Alteration | Permit Issued | 04/17/2026 | 05/07/2026 | Design DAL H CHUN ENGINEER PC Owner JANA BUILDERS CORP Contractor JANA BUILDERS CORP | Interior renovation of the existing bathrooms. No change in use, egress or occupancy. |
| B00984249 ↗ | 321 STANHOPE STREET BROOKLYN | Alteration | Signed-off | 03/21/2024 | 04/28/2026 | Owner 429 E 12 LLC Contractor BADGER MANAGEMENT Filer CAVALRY LLC | STRUCTURAL PLANS FOR INTERIOR RENOVATION TO EXISTING 3 STORY UNITS WITH CELLAR AND NEW BULKHEAD, IN CONJUNCTION WITH ALT II B00984249 |
| Q01264274 ↗ | 94-11 37 AVENUE QUEENS | Alteration | Signed-off | 09/26/2025 | 04/22/2026 | Contractor GIRON CONTRACTING INC Filer ALISTAS SERVICES LLC | INSTALL NEW FLOOR STRUCTURE TO REPAIR AND REPLACE EXISTING WOOD JOIST TO RESOLVE ECB VIOLATION #39148906K. NO CHANGE IN USE, EGRESS OR OCCUP… |
| M00989673 ↗ | 196 STANTON STREET MANHATTAN | Alteration CO | Permit Issued | 01/19/2024 | 04/06/2026 | Owner HELM MANAGEMENT INC Contractor TRIDENT BUILDERS GROUP Filer CAVALRY LLC | To convert existing community facility dormitory rooming units at 2nd floor to residential apartments.. |
| B01382051 ↗ | 3210 CHURCH AVENUE BROOKLYN | Alteration | Filed — no permit on record | 04/05/2026 | — | Filer ALISTAS SERVICES LLC | — |
| S01021883 ↗ | 189 ST MARYS AVENUE STATEN ISLAND | Alteration CO | Permit Issued | 05/20/2024 | 03/31/2026 | Owner IP DREAM HOUSE, LLC Contractor CAVALRY LLC Filer CAVALRY LLC | VERTICAL AND HORIZONTAL ENLARGMENT IN THE REAR OF EXISTING 2 STORY RESIDENCE. CONVERSION FROM BASEMENT TO CELLAR |
| M01135513 ↗ | 1095 PARK AVENUE MANHATTAN | Alteration | Permit Issued | 01/17/2025 | 03/03/2026 | Design NAOMI LANGER STUDIO Contractor CONSTRUCTION XPERT INC Filer METROPOLIS GROUP INC | Interior renovation to apartment 18C. Minor removal and construction of partitions and replace finishes as shown on drawings. No change to u… |
| B00984394 ↗ | 419 STANHOPE STREET BROOKLYN | Alteration CO | Permit Issued | 02/21/2024 | 02/04/2026 | Owner 429 E 12 LLC Contractor CONSTRUCTION XPERT INC Filer CAVALRY LLC | STRUCTURAL PLANS FOR INTERIOR RENOVATION TO EXISTING 3 STORY UNITS WITH CELLAR, ADDITION OF THE FOURTH FLOOR AND NEW BULKHEAD. |
| Q01353485 ↗ | 219-25 NORTH CONDUIT AVENUE QUEENS | Alteration | Filed — no permit on record | 02/02/2026 | — | Owner PLATINUM | — |
| B01135719 ↗ | 364 HANCOCK STREET BROOKLYN | Alteration | Signed-off | 11/15/2024 | 01/23/2026 | Contractor ALEF CONSTRUCTION INC Filer CAVALRY LLC | RENOVATION OF AN EXISTING TWO FAMILY TOWNHOUSE. NO CHANGE TO USE, EGRESS OR OCCUPANCY |
| Q00229680 ↗ | 82-34 TRYON PLACE QUEENS | Alteration | Signed-off | 09/27/2019 | 01/09/2026 | Design JLS DESIGNS Contractor RAYMOND'S PLBG & HTG LLC Filer JLS DESIGNS | To install new plumbing fixtures as per plans. |
| M01252294 ↗ | 149 EAST 116 STREET MANHATTAN | Alteration | Permit Issued | 07/21/2025 | 12/22/2025 | Contractor MG DECORATIONS LTD | Gut renovation of existing 4-story mixed use building to address ECB violation 39150904J. No change in use, egress or occupancy. |
| Q01256293 ↗ | 87-25 CLOVER PLACE QUEENS | Alteration | Permit Issued | 07/17/2025 | 12/18/2025 | Contractor LMLJ CONTRACTORS INC | Demolish existing retaining and install new driveway to address ECB violation 39140868M. No change in use, egress or occupancy. |
| Q01282586 ↗ | 25-61 31 STREET QUEENS | Alteration | Filed — no permit on record | 12/18/2025 | — | Design DAL H CHUN ENGINEER PC | — |
| B01058291 ↗ | 10 MANHATTAN COURT BROOKLYN | Alteration CO | Permit Issued | 07/01/2024 | 12/02/2025 | Design TAL IRIS SHEMESH ,ARCHITECT Contractor FINE ITALIAN ARTISAN CONS Filer CAVALRY LLC | TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT I APPLICATION #B01058291 |
| B01271169 ↗ | 586 CONEY ISLAND AVENUE BROOKLYN | Alteration | Signed-off | 10/03/2025 | 11/25/2025 | Design DAL H CHUN ENGINEER PC Contractor JANA BUILDERS CORP | APPLICATION FILED HERE TO PROPOSE DIRECT REPLACEMENT OF EXISTING RTU. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01298713 ↗ | 50-18 ROOSEVELT AVENUE QUEENS | Alteration | Signed-off | 10/08/2025 | 11/24/2025 | Design DAL H CHUN ENGINEER PC Contractor JANA BUILDERS CORP | APPLICATION FILED HERE TO PROPOSE DIRECT REPLACEMENT OF EXISTING RTU. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01038433 ↗ | 84 UNIVERSITY PLACE MANHATTAN | Alteration CO | Permit Issued | 05/14/2024 | 11/14/2025 | Design AHT ENGINEERING PLLC Owner GD CAPITAL Contractor METHOD GENERAL CONTRACTOR Filer KUSHNER STUDIOS | STRUCTURAL AND SPECIFICATIONS FILED IN CONJUNCTIONWITH EXISTING BUILDING. FILED IN CONJUNCTIONWITH GC #M01038433-I1. |
| Q01169911 ↗ | 82-34 TRYON PLACE QUEENS | Alteration | Signed-off | 02/13/2025 | 10/16/2025 | Design JLS DESIGNS Contractor GIRON CONTRACTING INC Filer JLS DESIGNS | PROPOSED MECHANICAL AND VENTILATION SYSTEMS FOR A TWO STORY ONE FAMILY DWELLING WITH CELLAR. |
| B01208689 ↗ | 1584 ROCKAWAY PARKWAY BROOKLYN | Alteration | Signed-off | 05/15/2025 | 10/02/2025 | Design DAL H CHUN ENGINEER PC Owner PLATINUM Contractor RAYMOND'S PLBG & HTG LLC | Cap and Removal of high pressure boiler #51663 and install gas-fired furnace. No change in use, egress or occupancy. |
| X01058612 ↗ | 761 DAWSON STREET BRONX | Alteration | Signed-off | 09/05/2024 | 10/01/2025 | Design CKL Engineering Contractor R & G MECHANICAL CORP Filer CAVALRY LLC | MINOR INTERIOR RENOVATION TO 3 FAMILY RESIDENTIAL BUILDING.. NO CHANGE TO USE OR EGRESS |
| M01283309 ↗ | 92 WEST HOUSTON STREET MANHATTAN | Alteration | Signed-off | 09/18/2025 | 09/25/2025 | Design DAL H CHUN ENGINEER PC Contractor RAYMOND'S PLBG & HTG LLC | REPLACEMENT OF EXISTING BOILER WITH NEW GAS BOILER. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B01005856 ↗ | 71 GRAND AVENUE BROOKLYN | Alteration | Permit Issued | 07/24/2024 | 09/23/2025 | Design CKL Engineering Owner MARCY PLAZA Contractor AMC PLBG, HTG & CLNG, INC Filer CAVALRY LLC | Plumbing work in conjunction with general construction work. No change in use, egress or occupancy |
| Q01123259 ↗ | 81-14 KENT STREET QUEENS | Alteration | Signed-off | 09/03/2025 | 09/05/2025 | Design DAL H CHUN ENGINEER PC Contractor RAYMOND'S PLBG & HTG LLC Filer DAL H CHUN ENGINEER PC | INSTALL PLUMBING RPZ BACKFLOW PREVENTER (PRIMARY) WITH CONJUNCTION IN NB #421217114, NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M01222632 ↗ | 106 AVENUE B MANHATTAN | Alteration | Signed-off | 06/04/2025 | 08/29/2025 | Owner PLATINUM Contractor MG DECORATIONS LTD | INSTALL NEW STOREFRONT TO ADDRESS ECB VIOLATION # 39146241X. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| X01271132 ↗ | 2829 EDSON AVENUE BRONX | Alteration | Signed-off | 08/14/2025 | 08/18/2025 | Design DAL H CHUN ENGINEER PC Owner Laundry Capital Contractor JANA BUILDERS CORP | APPLICATION FILED HERE TO PROPOSE DIRECT REPLACEMENT OF EXISTING RTU. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B00950015 ↗ | 352 LAFAYETTE AVENUE BROOKLYN | Alteration | Permit Issued | 11/02/2023 | 08/12/2025 | Design CKL Engineering Owner MARCY PLAZA Contractor AMC PLBG, HTG & CLNG, INC Filer CAVALRY LLC | Plumbing hob filed in conjunction with B00950015-I1 for removing ecb violation 350001422M, 35242287X, 35001422M. No change in use, egress or… |
| M01242074 ↗ | 92 WEST HOUSTON STREET MANHATTAN | Alteration | Signed-off | 06/20/2025 | 08/07/2025 | Contractor RAYMOND'S PLBG & HTG LLC | REPLACEMENT OF EXISTING BOILER WITH NEW GAS BOILER AND INSTALLATION OF NEW GAS HOT WATER HEATER. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B01188432 ↗ | 234 SCHENECTADY AVENUE BROOKLYN | Alteration | Filed — no permit on record | 08/05/2025 | — | Design DAL H CHUN ENGINEER PC Filer DAL H CHUN ENGINEER PC | — |
| B00891451 ↗ | 1145 60 STREET BROOKLYN | ALT-CO - New Building with Existing Elements to Remain | Permit Issued | 09/13/2023 | 07/29/2025 | Contractor CR BUILDERS NY Filer NYC DESIGN FILE | TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT I APPLICATION #B00891451 |
| X01081337 ↗ | 5782 MOSHOLU AVENUE BRONX | Alteration | Signed-off | 08/03/2024 | 07/23/2025 | Contractor NYC CLEANING AND MAINTENA | ENLARGEMENT OF THE BUILDING IN THE REAR, NEW STOREFRONT FOR ONE RETAIL STORE AND REMOVAL OF SIGNAGE TO ADDRESS ECB VIOLATION 39115907L, 3911… |
| B01188040 ↗ | 8923 FLATLAND AVE BROOKLYN | Alteration | Signed-off | 03/03/2025 | 07/21/2025 | Owner PLATINUM Contractor RAYMOND'S PLBG & HTG LLC | Relocation of existing RPZ to front of the building. No change in use, egress or occupancy. |
| B01188044 ↗ | 3046 AVENUE X BROOKLYN | Alteration | Signed-off | 03/11/2025 | 07/21/2025 | Owner PLATINUM Contractor RAYMOND'S PLBG & HTG LLC | Replace existing 2 RPZ with 3 RPZ. No change in use, egress or occupancy. |
| B00966972 ↗ | 501 SMITH STREET BROOKLYN | ALT-CO - New Building with Existing Elements to Remain | Permit Issued | 12/21/2023 | 07/10/2025 | Owner PLATINUM Contractor JANA BUILDERS CORP | Subsequent temporary construction fence filing. No change in use, egress or occupancy. |
| S01226435 ↗ | 1287 CASTLETON AVENUE STATEN ISLAND | Alteration | Signed-off | 07/04/2025 | 07/08/2025 | Design DAL H CHUN ENGINEER PC Contractor JANA BUILDERS CORP | APPLICATION FILED HERE TO PROPOSE DIRECT REPLACEMENT OF EXISTING RTU. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| X01083151 ↗ | 354 EAST 149 STREET BRONX | Alteration | Permit Issued | 07/31/2024 | 07/08/2025 | Design KOH ARCHITECTURE PLLC Contractor ALMA DESIGN | PROPOSE INTERIOR RENOVATION ON CELLAR AND ROOF AND MINOR STAIRWORK ON FIRST FLOOR, MINOR PARTITIONS AND FINISH WORK AS PER PLANS. NO CHANGE … |
| Q01226440 ↗ | 112-05 SUTPHIN BOULEVARD QUEENS | Alteration | Signed-off | 05/22/2025 | 07/07/2025 | Design DAL H CHUN ENGINEER PC Owner Laundry Capital Contractor JANA BUILDERS CORP | APPLICATION FILED HERE TO PROPOSE DIRECT REPLACEMENT OF EXISTING RTU. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01075223 ↗ | 94-11 37 AVENUE QUEENS | Alteration | Signed-off | 07/05/2024 | 06/26/2025 | Contractor GIRON CONTRACTING INC Filer ALISTAS SERVICES LLC | RESTORE TO PRIOR LEGAL CONDITION AND REMOVE ILLEGAL EXTENSION & CANOPY TENT AT THE REAR OF THE BUILDING TO RESOLVE DOB VIOLATION #100423AEUH… |
| B00953681 ↗ | 103 BERRY STREET BROOKLYN | Alteration | Signed-off | 09/11/2024 | 06/20/2025 | Design DAL H CHUN ENGINEER PC Contractor SAMA CONSTRUCTION LLC | REPLACING EXISTING GAS BOILER WITH NEW GAS BOILER. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B01113779 ↗ | 907 ST MARKS AVENUE BROOKLYN | Alteration | Signed-off | 11/07/2024 | 06/10/2025 | Design CKL Engineering Owner 429 E 12 LLC Contractor BADGER MANAGEMENT Filer CAVALRY LLC | MINOR INTERIOR RENOVATION TO 4TH FLOOR OF EXISTING 4-STORY BUILDING WITH CELLAR. NO CHANGE IN USE EGRESS OR OCCUPANCY. |
| B01230668 ↗ | 299 BUFFALO AVENUE BROOKLYN | Alteration | Signed-off | 05/27/2025 | 05/30/2025 | Design DAL H CHUN ENGINEER PC Contractor IRIDIUM CONSTRUCTION CORP | SUPPORT OF EXCAVATION FILED IN CONJUNCTION WITH NB APPLICATION 321631454. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B01208690 ↗ | 1584 ROCKAWAY PARKWAY BROOKLYN | Alteration | Signed-off | 05/18/2025 | 05/29/2025 | Design DAL H CHUN ENGINEER PC Owner PLATINUM Contractor MG DECORATIONS LTD | Installation of new HVAC equipment for retail use. No change in use, egress or occupancy. |
| M01226180 ↗ | 149 EAST 116 STREET MANHATTAN | Alteration | Permit Issued | 05/15/2025 | 05/29/2025 | Design DAL H CHUN ENGINEER PC Owner PLATINUM Contractor MG DECORATIONS LTD | Gut renovation of existing retail space. No change in use, egress or occupancy. |
| M01226182 ↗ | 151 EAST 116 STREET MANHATTAN | Alteration | Signed-off | 05/15/2025 | 05/29/2025 | Design DAL H CHUN ENGINEER PC Contractor MG DECORATIONS LTD | Gut renovation of existing retail space. No change in use, egress or occupancy. |
| M01065123 ↗ | 230 WEST 116 STREET MANHATTAN | Alteration | Signed-off | 06/18/2024 | 05/28/2025 | Design CKL Engineering Owner HIRSHMARK Contractor AMC PLBG, HTG & CLNG, INC Filer CAVALRY LLC | PLUMBING JOB FILED HERE IN TO SUPERSEDE OLD JOB 123823933 THAT WAS NEVER SIGNED OFF. FILING TO PROPOSE MINOR WORK IN BATHROOM OF APARTMENT U… |
| Q01156816 ↗ | 30-13 STEINWAY STREET QUEENS | Alteration | Signed-off | 01/13/2025 | 05/12/2025 | Contractor GIRON CONTRACTING INC Filer ALISTAS SERVICES LLC | Subsequent plumbing filing. No change in use, egress or occupancy. |
| B01169900 ↗ | 2201 85 STREET BROOKLYN | Alteration | Signed-off | 03/12/2025 | 04/25/2025 | Design VERSATILE ENGINEERING, P.C. Contractor BEST ZRK SERVICES INC Filer ALISTAS SERVICES LLC | REMOVAL OF ILLIGALLY INSTALLED SIGNS TO COMPLY WITH ECB VIOLATIONS FOR WORK WITHOUT PERMIT |
| Q01177147 ↗ | 85-33 213 STREET QUEENS | Alteration | Signed-off | 02/10/2025 | 04/15/2025 | Contractor ALMA DEVELOPERS | INSTALLATION OF THE FRONT YARD PORCH TO ADDRESS VIOLATION # 39130109M AT EXPOSURE #1 AND NEW FACADE. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Q01195865 ↗ | 955 SENECA AVENUE QUEENS | Alteration | Signed-off | 03/20/2025 | 04/02/2025 | Owner PLATINUM Contractor MG DECORATIONS LTD | INTERIOR RENOVATION OF AN EXISTING APARTMENT 3L. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B01165247 ↗ | 183 MILLER AVENUE BROOKLYN | Full Demolition | Signed-off | 01/31/2025 | 03/21/2025 | Design HIRANI Contractor GRANITE ENVIRONMENT, LLC Filer SADIE SILVER | Full demolition of 2 story residential building to comply with NYC HPD Immediate Emergency Declaration for Demolition, IED# 18924 |
| B01190575 ↗ | 262 MELROSE STREET BROOKLYN | Alteration | Signed-off | 03/12/2025 | 03/20/2025 | Owner 429 E 12 LLC Contractor CONSTRUCTION XPERT INC Filer CAVALRY LLC | INTERIOR RENOVATION TO ADD BEDROOMS TO EXISTING DWELLING UNITS ON SECOND AND THIRD FLOOR |
| M01155150 ↗ | 135 WEST BROADWAY MANHATTAN | Alteration | Signed-off | 01/16/2025 | 03/12/2025 | Contractor CAVALRY LLC | FILING TO GET EQUIPMENT USE CARDS FOR 2 OUTDOOR UNITS. ADDRESS FDNY VIOLATION 0116904212X AND VIOLATIONS 39064115X AND 39063809X |
| B01176618 ↗ | 80 GRAHAM AVENUE BROOKLYN | Alteration | Signed-off | 02/10/2025 | 03/10/2025 | Contractor SB RENOVATION & MODELING | RESTORE TO LEGAL CONDITION TO ADDRESS VIOLATION #39082095R. REMOVED AT EXPOSURE 4 THREE ERECTEDMETAL UNITS WITH ROLL DOWN GATES AND OVERHEAD… |
| Q01156025 ↗ | 106-20 CORONA AVENUE QUEENS | Alteration | Signed-off | 01/22/2025 | 03/07/2025 | Design VERSATILE ENGINEERING, P.C. Contractor GIRON CONTRACTING INC Filer ALISTAS SERVICES LLC | REMOVAL OF ILLEGALLY BUILT DURING COVID-19 WOODEN STRUCTURE ON CITY SIDEWALK, AFFIXED TO THE RESTAURANT. THIS APPLICATION IS TO ADRESS VIOLA… |
| Q01130031 ↗ | 115-20 JAMAICA AVENUE QUEENS | Alteration | Signed-off | 10/29/2024 | 02/11/2025 | Owner PLATINUM Contractor RAYMOND'S PLBG & HTG LLC Filer ALISTAS SERVICES LLC | LEGALIZATION OF THE WORK FOR REMOVAL OF CELLAR GAS PIPING AND GAS VALVE REMAINED AFTER REMOVAL OF EXISTING BOILER UNDER SIGNED OFF JOB #Q009… |
| B01155243 ↗ | 1571 EASTERN PARKWAY BROOKLYN | Alteration | Signed-off | 01/03/2025 | 02/03/2025 | Design DAL H CHUN ENGINEER PC Contractor DAL H CHUN ENGINEER, PC Filer DAL H CHUN ENGINEER PC | PROPOSED REPLACE TO NEW FIRE REGISTERED DOOR, PARTITION WALL, CEILING AND INSTALL FRESH AIR INTAKE & CARBON MONOXIDE/SMOKE DETECTOR IN THE … |
| B01104159 ↗ | 2702 AVENUE X BROOKLYN | Alteration | Filed — no permit on record | 01/29/2025 | — | Filer CAVALRY LLC | — |
| Q00682577 ↗ | 41-15 45 STREET QUEENS | Alteration | Signed-off | 05/03/2022 | 01/13/2025 | Contractor MASTER TECH PLUMBING LLC Filer CAVALRY LLC | FILING TO ADDRESS ECB VIOLATION 39036116J AND DOB VIOLATION 051221AEUHAZ100409. INSTALL WASHER AND DRYERS WITH SPRINKLERS IN THE CELLAR. NO … |
| B01136881 ↗ | 1005 65 STREET BROOKLYN | Alteration | Signed-off | 11/19/2024 | 01/10/2025 | Contractor NY BUILDING ASSOCIATES IN | STRUCTURAL WORK IN CONJUNCTION WITH GENERAL CONSTRUCTION WORK JOB # B01136881. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B00339125 ↗ | 376 CLEVELAND STREET BROOKLYN | Alteration | Signed-off | 08/18/2020 | 01/08/2025 | Design BCHEN ARCHITECT PLLC Contractor CAVALRY LLC | install (3) 4 ton mini-spllit a/c unit for new 2 family alt I filing. |
| B01104655 ↗ | 2411 DEAN STREET BROOKLYN | Full Demolition | Signed-off | 10/16/2024 | 12/30/2024 | Design HIRANI Contractor GRANITE ENVIRONMENT, LLC | Full Demolition of 3 story walk-up, mixed use building to comply with NYC HPD Immediate Emergency Declaration for Demolition, IED# 18646. |
| S01127971 ↗ | 1074 CASTLETON AVENUE STATEN ISLAND | Full Demolition | Signed-off | 11/13/2024 | 12/12/2024 | Design HIRANI Contractor GRANITE ENVIRONMENT, LLC | Full Demolition of 2 Story Commercial Building to comply with NYC HPD's Immediate Emergency Declaration IED #18729 |
| S01127953 ↗ | 144 VAN PELT AVENUE | Full Demolition | Signed-off | 11/11/2024 | 12/11/2024 | Design HIRANI Contractor GRANITE ENVIRONMENT, LLC | Full Demolition of 2 Story Residential Building to comply with NYC HPD Immediate Emergency Declaration, IED #18728 |
| B01134749 ↗ | 974 DAHILL ROAD BROOKLYN | Alteration | Signed-off | 11/19/2024 | 12/10/2024 | Contractor ALEF CONSTRUCTION INC | Window installation as per plan and remove ECB violation 39126785X. No change in use, egress or occupancy |
| B00781676 ↗ | 220 ST JAMES PLACE BROOKLYN | Alteration CO | Permit Issued | 12/11/2023 | 12/03/2024 | Design GRASSO-MENZIUSO ARCHITECTS Owner 20 RSW, LLC Contractor CONSTRUCTION XPERT INC | Structural work to include reframing first floor for new stair opening and lintel for new exterior door as per plans. No change to use, bulk… |
| Q01077146 ↗ | 117-59 140 STREET QUEENS | Full Demolition | Signed-off | 07/29/2024 | 11/22/2024 | Design HIRANI Contractor GRANITE ENVIRONMENT, LLC Filer XPEDITE LLC | Full demolition of 3 Story Residential Building to Comply with NYC HPD Accelerated Emergency Declaration for Demolition, DEC# 18455 |
| B00947847 ↗ | 560 1 STREET BROOKLYN | Alteration | Signed-off | 10/23/2023 | 11/18/2024 | Design DAMERON ARCHITECTURE PLLC Contractor ROSE & STONE CONSTRUCTION Filer CAVALRY LLC | Plumbing work in conjunction with general construction work job #B00947847. No change in use, egress or occupancy. |
| X01134565 ↗ | 355 EAST 149 STREET BRONX | Alteration | Permit Issued | 11/08/2024 | 11/15/2024 | Design DAL H CHUN ENGINEER PC Contractor ALMA DESIGN | Facade repair to remedy DOB violation 060724SR0102RF . No change in use, egress or occupancy. |
| B01125951 ↗ | 1438 44 STREET BROOKLYN | Alteration | Signed-off | 10/11/2024 | 11/14/2024 | Contractor CAVALRY LLC Filer CAVALRY LLC | REMOVAL OF STEEL STRUCTURE IN THE REAR YARD. NO CHANGEIN USE, EXITS OR OCCUPANCY |
| B00982252 ↗ | 216 GRAND STREET BROOKLYN | Alteration | Signed-off | 12/27/2023 | 11/13/2024 | Owner EMPIRE EQUITIES Contractor M & M PIPING AND HEATING Filer CAVALRY LLC | INSTALLATION OF PIPING AND PLUMBING FIXUTRES IN CONJUNCTION WITH MAIN APPLICATION # B00989408-I1 |
| B01133863 ↗ | 1273 ROGERS AVENUE BROOKLYN | Alteration CO | Filed — no permit on record | 11/13/2024 | — | — | |
| M01081169 ↗ | 429 EAST 12 STREET MANHATTAN | Alteration | Signed-off | 07/16/2024 | 11/13/2024 | Owner 429 E 12 LLC Contractor JEM FIRE PREVENTION INC Filer CAVALRY LLC | PLUMBING AND SPRINKLER APPLICATION IN CONJUNCTION WITH ALT I JOB #M00943708 |
| S08040396 ↗ | 471 NORTH GANNON AVENUE STATEN ISLAND | Alteration CO | Permit Issued | 01/26/2023 | 11/07/2024 | Owner Bnos Chaya School Contractor CAVALRY LLC Filer CAVALRY LLC | PLUMBING AND SPRINKLER FILED IN CONJUNCTIONWITH MAIN APPLICATION # S08040396_I1 |
| B01135515 ↗ | 426 CHAUNCEY STREET BROOKLYN | Alteration | Signed-off | 11/01/2024 | 11/04/2024 | Owner RK CAPITAL Contractor GREGG NY PLUMBING, INC Filer HOMES R US SALES CORP | PLUMBING FILING IN CONJUNCTION WITH M01064101 AND 321292739. Job Number 321292739 will be withdrawn , when application nimber B01135515-i1 w… |
| S01116727 ↗ | 2734 VICTORY BOULEVARD STATEN ISLAND | Alteration | Signed-off | 10/09/2024 | 10/31/2024 | Contractor CAVALRY LLC Filer CAVALRY LLC | MECHANICAL FILING FOR EQUIPMENT USE CARDS FOR HVAC ON ROOF TO ADDRESS FDNY VIOLATION 014142007M |
| B01060083 ↗ | 426 CHAUNCEY STREET BROOKLYN | Alteration | Signed-off | 06/05/2024 | 10/16/2024 | Owner RK CAPITAL Contractor RCM GROUP INC Filer HOMES R US SALES CORP | SUBSEQUENT STRUCTURAL FILING. NO CHANGE IN USE, EXITS OR OCCUPANCY. |
| M01057670 ↗ | 421 WEST 154 STREET MANHATTAN | Alteration | Signed-off | 07/18/2024 | 10/15/2024 | Owner 51 HART LLC Contractor PRIME PIPING & HEATING IN Filer CAVALRY LLC | PLUMBING FILING IN CONJUNCTION WITH ALT2 APPLICATION M01057670. |
| B08047219 ↗ | 318 UNION STREET BROOKLYN | Alteration | Signed-off | 02/13/2023 | 10/08/2024 | Design DAMERON ARCHITECTURE PLLC Contractor DYNAMIC CONSTRUCTION OF Filer CAVALRY LLC | Plumbing filed herein in conjunction with ALT II B08047219 |
| B01109258 ↗ | 421 TOMPKINS AVENUE BROOKLYN | Alteration | Filed — no permit on record | 09/30/2024 | — | — | |
| M01030398 ↗ | 403 WEST 148 STREET MANHATTAN | Alteration | Signed-off | 04/15/2024 | 09/24/2024 | Contractor CAVALRY LLC Filer CAVALRY LLC | REPLACING OF PLUMBING FIXTURES ON EXISTING ROUGHING AND CAP AND REMOVAL OF GAS BOILER IN CONJUNCTION WITH MAIN APPLICATION #M01030398_Alt II |
| M01075461 ↗ | 63 AUDUBON AVENUE MANHATTAN | Full Demolition | Signed-off | 07/24/2024 | 09/19/2024 | Design HIRANI Contractor GRANITE ENVIRONMENT, LLC | Full demolition of 2 story residential building to comply with NYC HPD Immediate Emergency, IED# 18506 |
| M01069801 ↗ | 410 WEST 47 STREET MANHATTAN | Alteration | Signed-off | 06/24/2024 | 09/16/2024 | Design GRASSO-MENZIUSO ARCHITECTS Contractor CAVALRY LLC | PROPOSED TO REPAIR FIRE ESCAPE. WORK TO INCLUDE RE-WELDING AND CLEANING UP AND REPAIRING DAMAGED COMPONENETS. IN CONNECTION WITH VIOLATION… |
| B01068176 ↗ | 4309 13 AVENUE BROOKLYN | Alteration | Signed-off | 08/26/2024 | 09/12/2024 | Owner N.C. CALLER P.C. Contractor MARCAL CONTRACTING CO LLC Filer CAVALRY LLC | RENOVATION PROPOSED ON 2ND AND 3RD FLOOR TO CORRECT WORK WITHOUT PERMIT DONE UNDER DOB VIOLATION 070606C1202VP. PROPOSED NEW INTERIOR PARTIT… |
| B01064109 ↗ | 179 GUERNSEY STREET BROOKLYN | Alteration | Signed-off | 06/28/2024 | 09/11/2024 | Owner KOSSA CONSTRUCTION LLC Contractor KOSSA CONTRUCTION LLC Filer CAVALRY LLC | EXTERIOR WORK ONLY ON FACADE. NO CHANGE IN USE OCCUPANCY OR EGRESS |
| Q01082713 ↗ | 104-20 68 DRIVE QUEENS | Alteration | Signed-off | 07/18/2024 | 09/11/2024 | Contractor 2MG MANAGEMENT Filer HOMES R US SALES CORP | RENOVATE EXISTING FIRST FLOOR RETAIL SPACE TO CURE ECB VIOLATION 35656265P. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| B00937461 ↗ | 1362 PACIFIC STREET BROOKLYN | Alteration | Signed-off | 10/10/2023 | 09/10/2024 | Owner 429 E 12 LLC Contractor VILLAGE P & H NY INC Filer CAVALRY LLC | INSTALLATION OF PIPING, PLUMBING FIXTURES AND SPRINKLER SYSTEM IN CONJUNCTIONWITH MAIN APPLICATION #321537431 |
| B00765217 ↗ | 2052 63 STREET BROOKLYN | Alteration | Signed-off | 07/13/2022 | 09/05/2024 | Design CAVALRY ASSOCIATES Contractor CLASSIC BUILDERS CORP Filer CAVALRY LLC | SOE FILING IN CONJUNCTION WITH DOB APPLICATION B00660801.NO CHANGE IN USE, EXITS OR OCCUPANCY. |
| M00943708 ↗ | 429 EAST 12 STREET MANHATTAN | Alteration CO | Permit Issued | 10/31/2023 | 08/28/2024 | Owner 429 E 12 LLC Contractor BADGER MANAGEMENT Filer CAVALRY LLC | TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT I JOB # M00943708 |
| B00661658 ↗ | 2052 63 STREET BROOKLYN | Alteration | Signed-off | 02/13/2023 | 08/27/2024 | Contractor ORBIT PLBG & HTG INC Filer CAVALRY LLC | Plumbing filed in conjunction with ALT I B00660801 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 09/16/2026 | Metering | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 09/16/2026 | Interior lighting power | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 09/16/2026 | Lighting in dwelling units | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 09/16/2026 | Insulation placement and R values | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 09/16/2026 | Lighting controls | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 09/16/2026 | Air barrier - visual inspection | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 09/16/2026 | Fire-Resistant Penetrations and Joints | 84 UNIVERSITY PLACE | JAMES CHUN | special |
| 09/16/2026 | Fire-Resistance Rated Construction | 84 UNIVERSITY PLACE | JAMES CHUN | progress |
| 09/16/2026 | Fenestration and door U-factor and product ratings | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 09/16/2026 | Energy Code Compliance Inspections | 84 UNIVERSITY PLACE | JAMES CHUN | progress |
| 09/16/2026 | Fenestration air leakage | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 08/26/2026 | HVAC-R and service water heating equipment | 538 JOHNSON AVENUE | ANGELO COSTA | energy_progress |
| 08/26/2026 | Maintenance information | 538 JOHNSON AVENUE | ANGELO COSTA | energy_progress |
| 08/26/2026 | HVAC-R and service water heating system controls | 538 JOHNSON AVENUE | ANGELO COSTA | energy_progress |
| 08/26/2026 | Fire-Resistant Penetrations and Joints | 538 JOHNSON AVENUE | ANGELO COSTA | special |
| 08/26/2026 | Tenant Protection Plan Compliance | 538 JOHNSON AVENUE | JAMES CHUN | special |
| 08/14/2026 | Fire-Resistant Penetrations and Joints | 344 UTICA AVENUE | DAL CHUN | special |
| 08/14/2026 | Energy Code Compliance Inspections | 344 UTICA AVENUE | DAL CHUN | progress |
| 08/14/2026 | HVAC-R and service water heating system controls | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 08/14/2026 | HVAC-R and service water heating equipment | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 08/14/2026 | HVAC-R and service water piping design and insulation | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 08/14/2026 | Maintenance information | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 07/23/2026 | Fire-Resistant Penetrations and Joints | 344 UTICA AVENUE | DAL CHUN | special |
| 07/23/2026 | Energy Code Compliance Inspections | 344 UTICA AVENUE | DAL CHUN | progress |
| 07/23/2026 | HVAC-R and service water heating equipment | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 07/23/2026 | Maintenance information | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 07/23/2026 | HVAC-R and service water heating system controls | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 07/23/2026 | HVAC-R and service water piping design and insulation | 344 UTICA AVENUE | DAL CHUN | energy_progress |
| 06/11/2026 | Fire-Resistance Rated Construction | 942 51 STREET | JAMES CHUN | progress |
| 06/11/2026 | Final | 942 51 STREET | JAMES CHUN | progress |
| 06/11/2026 | Energy Code Compliance Inspections | 942 51 STREET | JAMES CHUN | progress |
| 06/11/2026 | Structural Stability – Alterations of existing buildings | 942 51 STREET | JAMES CHUN | special |
| 06/11/2026 | Fire-Resistant Penetrations and Joints | 942 51 STREET | JAMES CHUN | special |
| 05/15/2026 | Fire-Resistance Rated Construction | 3210 CHURCH AVENUE | DAL CHUN | progress |
| 04/21/2026 | Mechanical Systems | 82-34 TRYON PLACE | DAL CHUN | special |
| 04/21/2026 | Final | 82-34 TRYON PLACE | DAL CHUN | progress |
| 04/21/2026 | HVAC-R and service water heating system controls | 82-34 TRYON PLACE | DAL CHUN | energy_progress |
| 04/21/2026 | HVAC-R and service water piping design and insulation | 82-34 TRYON PLACE | DAL CHUN | energy_progress |
| 04/21/2026 | HVAC-R and service water heating equipment | 82-34 TRYON PLACE | DAL CHUN | energy_progress |
| 04/21/2026 | Ventilation and air distribution system | 82-34 TRYON PLACE | DAL CHUN | energy_progress |
| 04/21/2026 | Duct leakage testing, insulation and design | 82-34 TRYON PLACE | DAL CHUN | energy_progress |
| 04/21/2026 | Maintenance information | 82-34 TRYON PLACE | DAL CHUN | energy_progress |
| 04/10/2026 | Fire-Resistant Penetrations and Joints | 84 UNIVERSITY PLACE | JAMES CHUN | special |
| 04/10/2026 | Energy Code Compliance Inspections | 84 UNIVERSITY PLACE | JAMES CHUN | progress |
| 04/10/2026 | Fire-Resistance Rated Construction | 84 UNIVERSITY PLACE | JAMES CHUN | progress |
| 04/10/2026 | Metering | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 04/10/2026 | Insulation placement and R values | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 04/10/2026 | Interior lighting power | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 04/10/2026 | Lighting in dwelling units | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |
| 04/10/2026 | Fenestration and door U-factor and product ratings | 84 UNIVERSITY PLACE | JAMES CHUN | energy_progress |