LL97 Covered12 Active Violations ▸FISP: SAFEFDNY Report ↗
Elevator apt, fireproof without stores · Owner of record: NYC Housing Authority · 465,500 sf lot · 3.48 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofNycha - BrownsvilleUnder Construction43p · 6 filings · 20 docs
BulkheadPedestrian protection sidewalk shed1p · 1 filing · 6 docs
Floor 6Cellar concrete pad and water heater installation7p · 2 filings · 20 docs
Floor 5Cellar concrete pad and water heater installation7p · 2 filings · 20 docs
Floor 4Cellar concrete pad and water heater installation7p · 2 filings · 20 docs
Floor 3Cellar concrete pad and water heater installation7p · 2 filings · 20 docs
Floor 2Cellar concrete pad and water heater installation7p · 2 filings · 20 docs
Floor 1Cellar concrete pad and water heater installation7p · 2 filings · 20 docs
CellarNycha - BrownsvilleUnder Construction15p · 2 filings · 20 docs
Site & exteriorTemporary sidewalk shed installation41p · 7 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
New York City Housing Authority6008/29/2026
Zoria Housing403/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Superstructures Engineering + Architects103/21/2026
AK Consulting Services1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Roma ScaffoldingScaffold1807/08/2026
Richards Plum & Heating CoGeneral Contractor1007/08/2026
J & N Construction GroupScaffold907/08/2026
J & N Construction GroupGeneral Contractor407/08/2026
Roma Scaffoldingspecialty_contractor303/21/2026
Richards P and H CoPlumbing107/08/2026
Ronald Testa, JRElectrical103/21/2026
Accord PowerGeneral Contractor107/08/2026
A1 Expediting ServiceElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Synergic Design8561105/13/2026
Joel Phagoo, PE2416306/10/2024
Alan Margolin & Associates423504/04/2024
Bureau Veritas Na6902210/17/2023
Ikra Consulting7032110/25/2022
Building Lifecycle
All (133)Filed (21)Permit Issued (24)Signed Off (12)Facade (FISP) (20)Violation (16)Inspection (8)Objection (2)Special Inspection (30)
06/01/2026
Permit issued — Solar
B01276411-I1-SL
05/13/2026
Filed — Alteration
Installation of 22.89 kw solar energy system on roof. No change of occupancy, use or egress.
B01276411-I1
05/11/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Malathi Ananthakrishnan
08/22/2025
Special inspection requirement — Air barrier - visual inspection
Malathi Ananthakrishnan
08/22/2025
Special inspection requirement — Final
Malathi Ananthakrishnan
08/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Malathi Ananthakrishnan
08/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malathi Ananthakrishnan
04/11/2025
Signed off — Alteration
B00490291-I1
03/17/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B08053083-I1
03/17/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B08053089-I1
03/17/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00934317-I1
10/10/2024
Signed off — Alteration
Installation of new gas piping to new domestic water heaters and relocation of floor drain as per plans filed herewith.
B00920029-S2
10/10/2024
Signed off — Alteration
Installation of new gas piping to new domestic water heaters and relocation of floor drain as per plans filed herewith.
B00920029-I1
10/07/2024
Signed off — Alteration
Installation of new gas piping to new domestic water heaters and relocation of floor drain as per plans filed herewith.
B00920029-S1
09/25/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
09/25/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/23/2024
Permit issued — General Construction
B00920029-I1-GC
09/19/2024
Permit issued — Mechanical Systems
B00920029-S1-MS
08/19/2024
Cycle 9 facade report submitted
08/19/2024
Cycle 9 facade report signed — SAFE
08/15/2024
Cycle 9 facade inspection completed
06/10/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00934317-P2
06/10/2024
Special inspection requirement — Post-installed Anchors
JOEL PHAGOO
06/04/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/29/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/20/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
05/09/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/19/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00934317-P1
04/19/2024
Special inspection requirement — Post-installed Anchors
JOEL PHAGOO
04/12/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
04/12/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
04/12/2024
Special inspection requirement — Maintenance information
Young Suh
04/12/2024
Special inspection requirement — HVAC-R and service water heating system controls
Young Suh
04/12/2024
Special inspection requirement — HVAC-R and service water heating equipment
Young Suh
04/12/2024
Special inspection requirement — Energy Code Compliance Inspections
Young Suh
04/12/2024
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
04/04/2024
Filed — Alteration
Installation of new gas piping to new domestic water heaters and relocation of floor drain as per plans filed herewith.
B00920029-P1
04/01/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
04/01/2024
Special inspection requirement — Maintenance information
Young Suh
04/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
04/01/2024
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
04/01/2024
Special inspection requirement — Energy Code Compliance Inspections
Young Suh
04/01/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
04/01/2024
Special inspection requirement — HVAC-R and service water heating equipment
Young Suh
04/01/2024
Special inspection requirement — HVAC-R and service water heating system controls
Young Suh
03/07/2024
Permit issued — General Construction
B00490291-I1-GC-CX
01/19/2024
Signed off — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 275 BLAKE AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B00139313-I1
12/28/2023
Signed off — Alteration
FACADE RESTORATION WORK AS PER INDICATED ON PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00729976-I1
12/28/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 275 BLAKE AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B08034757-I1
12/27/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
12/22/2023
Permit issued — Sidewalk Shed
B08053083-I1-SH
12/22/2023
Permit issued — Construction Fence
B08053089-I1-FN
10/19/2023
Permit issued — Plumbing
B00920029-S2-PL
10/19/2023
Permit issued — Mechanical Systems
B00920029-S1-MS
10/19/2023
Permit issued — General Construction
B00920029-I1-GC
10/17/2023
Filed — Alteration
FACADE RESTORATION WORK AS PER INDICATED ON PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00729976-P5
10/16/2023
Special inspection requirement — Masonry
IBRAHIM MOURAD
10/16/2023
Special inspection requirement — Final
IBRAHIM MOURAD
10/16/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
IBRAHIM MOURAD
10/11/2023
Permit issued — Supported Scaffold
B00934317-I1-SF
Latest 60 of 133 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedAccord Power06/01/2026
DOB NOWGeneral ConstructionSigned-offRichards Plum & Heating Co09/23/2024
DOB NOWMechanical SystemsSigned-offRichards Plum & Heating Co09/19/2024
DOB NOWGeneral ConstructionSigned-offJ & N Construction Group03/07/2024
DOB NOWSidewalk ShedSigned-offJ & N Construction Group12/22/2023
DOB NOWConstruction FenceSigned-offJ & N Construction Group12/22/2023
DOB NOWPlumbingSigned-offRichards P and H Co10/19/2023
DOB NOWMechanical SystemsSigned-offRichards Plum & Heating Co10/19/2023
DOB NOWGeneral ConstructionSigned-offRichards Plum & Heating Co10/19/2023
DOB NOWSupported ScaffoldSigned-offJ & N Construction Group10/11/2023
DOB NOWStructuralSigned-offJ & N Construction Group01/30/2023
DOB NOWSidewalk ShedSigned-offJ & N Construction Group12/13/2022
DOB NOWConstruction FenceSigned-offJ & N Construction Group12/13/2022
DOB NOWConstruction FenceSigned-offRoma Scaffolding11/12/2022
DOB NOWSupported ScaffoldSigned-offRoma Scaffolding10/26/2022
DOB NOWGeneral ConstructionSigned-offRoma Scaffolding08/16/2022
DOB NOWConstruction FenceSigned-offRoma Scaffolding07/07/2022
DOB NOWSidewalk ShedSigned-offRoma Scaffolding05/20/2022
DOB NOWConstruction FenceSigned-offRoma Scaffolding07/07/2021
DOB NOWSidewalk ShedSigned-offRoma Scaffolding05/18/2021
DOB NOWSidewalk ShedSigned-offRoma Scaffolding05/14/2020
DOB NOWConstruction FenceSigned-offRoma Scaffolding05/11/2020
DOB NOWConstruction FenceSigned-offRoma Scaffolding04/22/2019
DOB NOWSidewalk ShedSigned-offRoma Scaffolding04/17/2019
BISOTISSUEDDavrial Enterprises05/18/2017
BISOTISSUEDZoria Housing11/14/2015
BISEQISSUEDZoria Housing08/21/2015
BISEQISSUEDZoria Housing08/07/2015
BISOTISSUEDZoria Housing07/28/2015
BISEQISSUEDZoria Housing07/08/2015
BISEQISSUEDVikrant Contracting & Builder06/23/2015
BISEQISSUEDZoria Housing03/29/2013
BISOTISSUEDZoria Housing12/28/2012
BISEQISSUEDZoria Housing11/20/2012
BISEQISSUEDVikrant Contracting & Builder11/13/2012
BISEQISSUEDZoria Housing08/03/2012
BISEQISSUEDVikrant Contracting & Builder07/24/2012
BISEQISSUEDMetropolitan Enterprises05/07/2012
BISEQISSUEDMetropolitan Enterprises05/20/2011
BISPLISSUEDKordun Construction01/31/2008
+ 8 more permits on file
7 projects · most recent 09/02/2025
General Wiring
FiledStatusContractorScope
09/02/2025Permit IssuedAccord Power Electric2 meters, 1 new_meters
05/07/2024CompleteGilston Electrical ContngGeneral Wiring
01/26/2023CompleteLit Mode Electrical Contg—
12/09/2022CompleteLit Mode Electrical Contg—
04/19/2021Permit IssuedHylan Datacom & Electrical—
09/11/2020Permit IssuedAmin Electrical—
03/04/2019Permit IssuedUSA Elect'l Services—
1 project · most recent 05/13/2026
FiledStatusContractorScope
05/13/2026Permit IssuedAccord Power42 panels, 22.89 kw, 6,474.62 roof_area_sqft
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
09/25/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/25/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/04/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/29/2024Pass-Final CND-Occupancy InspectionPassView ↗
05/20/2024Fail-Final CND-Occupancy InspectionFailView ↗
05/09/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/01/2024Fail-Final CND-Occupancy InspectionFailView ↗
12/27/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 37
DateRequirementInspectorRole
05/11/2026Structural Stability – Alterations of existing buildingsMalathi Ananthakrishnanspecial
08/22/2025Air barrier - visual inspectionMalathi Ananthakrishnanenergy_progress
08/22/2025FinalMalathi Ananthakrishnanprogress
08/22/2025Energy Code Compliance InspectionsMalathi Ananthakrishnanprogress
08/22/2025Fire-Resistant Penetrations and JointsMalathi Ananthakrishnanspecial
06/10/2024Post-installed AnchorsJOEL PHAGOOspecial
04/19/2024Post-installed AnchorsJOEL PHAGOOspecial
04/12/2024Fire-Resistant Penetrations and JointsYoung Suhspecial
04/12/2024HVAC-R and service water piping design and insulationYoung Suhenergy_progress
04/12/2024Maintenance informationYoung Suhenergy_progress
04/12/2024HVAC-R and service water heating system controlsYoung Suhenergy_progress
04/12/2024HVAC-R and service water heating equipmentYoung Suhenergy_progress
04/12/2024Energy Code Compliance InspectionsYoung Suhprogress
04/12/2024Tenant Protection Plan ComplianceYoung Suhspecial
04/01/2024Maintenance informationYoung Suhenergy_progress
04/01/2024Fire-Resistant Penetrations and JointsYoung Suhspecial
04/01/2024Tenant Protection Plan ComplianceYoung Suhspecial
04/01/2024Energy Code Compliance InspectionsYoung Suhprogress
04/01/2024HVAC-R and service water piping design and insulationYoung Suhenergy_progress
04/01/2024HVAC-R and service water heating equipmentYoung Suhenergy_progress
04/01/2024HVAC-R and service water heating system controlsYoung Suhenergy_progress
10/16/2023MasonryIBRAHIM MOURADspecial
10/16/2023FinalIBRAHIM MOURADprogress
10/16/2023Structural Stability – Alterations of existing buildingsIBRAHIM MOURADspecial
09/19/2023FinalIBRAHIM MOURADprogress
Latest 25 of 37.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Nycha - BrownsvilleResidentialRoof
Project B01276411 Alteration · Permit Entire · 05/13/2026
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 235 on file (BIS + DOB NOW)
▸Plans & Drawings21
▸DOB NOWPlans/Sketch18
09/01/2026B00490291-I1Request digital key ↗
08/29/2026B00729976-I1Request digital key ↗
08/29/2026B00729976-P3Request digital key ↗
Showing 3 of 18 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/02/2026B00139313-I1Request digital key ↗
09/02/2026B00139313-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00156592-I1Request digital key ↗
▸Applications & Permits24
▸BISWORK PERMIT APPLICATION14
05/19/2017321116118Open ↗
08/20/2015340294595Open ↗
08/06/2015340289609Open ↗
Showing 3 of 14 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION10
08/20/2015340294595Open ↗
08/06/2015340289609Open ↗
07/27/2015340278791Open ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications90
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION22
10/03/2017321116118Open ↗
12/06/2016340289609Open ↗
11/21/2016340289609Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature21
09/02/2026B00139313-P1Open ↗
09/02/2026B00139313-I1Open ↗
09/02/2026B00156592-I1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWProgress Inspector Seal & Signature12
09/01/2026B01276411-I1Open ↗
09/01/2026B01276411-I1Open ↗
09/01/2026B01276411-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/01/2026B01276411-I1Open ↗
09/01/2026B01276411-I1Open ↗
09/01/2026B00920029-S2Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
08/20/2015340294595Open ↗
08/06/2015340289609Open ↗
07/27/2015340278791Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY5
08/20/2015340294595Open ↗
08/06/2015340289609Open ↗
07/27/2015340278791Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
08/06/2012320496389Open ↗
07/25/2012320496254Open ↗
07/11/2012320503344Open ↗
Showing 3 of 5 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
08/20/2015340294595Open ↗
08/06/2015340289609Open ↗
07/27/2015340278791Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
08/06/2012320496389Open ↗
07/25/2012320496254Open ↗
08/03/2010320195999Open ↗
Showing 3 of 4 on file for this type
▸BISPC FULL REPORT1
10/05/2007310034780Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
05/19/2017321116118Open ↗
▸Environmental & Asbestos12
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/26/2026B00920029-S1Open ↗
08/26/2026B00920029-S2Open ↗
08/26/2026B00920029-P1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
08/20/2015340294595Open ↗
07/27/2015340278791Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/01/2026B00490291-I1Open ↗
08/29/2026B00729976-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
08/03/2010320195999Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
10/05/2007310034780Open ↗
▸BISDEP FORM V5 - ASBESTOS VARIANCE1
01/04/2013320503344Open ↗
▸Energy Compliance13
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
10/03/2017321116118Open ↗
04/23/2015321116118Open ↗
12/12/2012320503344Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections3
04/14/2014320503344Open ↗
11/29/2013320503344Open ↗
07/11/2012320503344Open ↗
▸BISEN2 - As Built Energy Analysis2
04/14/2014320503344Open ↗
10/03/2017321116118Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
06/22/2015340273714Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B00920029-S2Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00490291-I1Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY5
08/20/2015340294595Open ↗
08/06/2015340289609Open ↗
07/27/2015340278791Open ↗
Showing 3 of 5 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
08/06/2015340289609Open ↗
▸Approvals, Objections & Sign-offs46
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter21
09/02/2026B00139313-I1Open ↗
09/02/2026B00139313-P1Open ↗
09/02/2026B00156592-I1Open ↗
Showing 3 of 21 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST10
10/03/2017321116118Open ↗
12/06/2016340289609Open ↗
08/09/2016340278791Open ↗
Showing 3 of 10 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION7
12/31/2015340273714Open ↗
12/31/2015340277710Open ↗
12/31/2015340294595Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS6
04/23/2015321116118Open ↗
08/06/2012320496389Open ↗
07/25/2012320496254Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP Variance (V5) letter2
09/01/2026B00490291-I1Open ↗
08/29/2026B00729976-I1Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT8
10/03/2017321116118Open ↗
08/09/2016340278791Open ↗
07/27/2015340278791Open ↗
Showing 3 of 8 on file for this type
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE (PGLI)1
07/11/2012320503344Open ↗
▸Filing & Intake Forms11
▸BISEFILING JOB APPLICATION COVER SHEET6
08/20/2015340294595Open ↗
08/06/2015340289609Open ↗
07/27/2015340278791Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET4
04/23/2015321116118Open ↗
08/06/2012320496389Open ↗
07/25/2012320496254Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM1
10/03/2017321116118Open ↗
▸Other Documents2
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
05/09/2017321116118Open ↗
08/09/2016340278791Open ↗