← Back
BuildNYC
Public elementary, junior or senior high
P.S. X10
2750 LAFAYETTE AVENUE · BIN 2080231
💬 Discuss this project
1957Year Built
3Stories
W1Building Class
R4-1Zoning
103,712 sfGross Floor Area
1Units
LL97 Covered5 Active Violations 0 unresolved · 5 paperwork only 9 likely answered ▸
Public elementary, junior or senior high · Owner of record: NYC Department of Parks and Recreation · 163,128 sf lot · 0.64 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 1P.S. 304 Early Childhood School, P.S. 101X +1Under Construction18p · 4 filings · 18 docs
CellarP.S. 304 Early Childhood SchoolUnder Construction4p · 1 filing · 20 docs
BasementP.S. 304 Early Childhood SchoolUnder Construction3p · 1 filing · 20 docs
Sub-BasementP.S. 304 Early Childhood SchoolUnder Construction24p · 3 filings · 20 docs
Site & exteriorP.S. 304 Early Childhood SchoolUnder Construction21p · 2 filings · 20 docs
Filed — no permit issuedP.S. 101X, P.S. 304 Early Childhood School11p · 2 filings · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority13910/13/2026
NYC Department of Design and Construction403/21/2026
NYC Department of Parks and Recreation103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Synergy Strategic Design Architects808/05/2026
360 Engineering107/21/2026
Princeton1206/22/2026
Systra302/17/2026
Benjamin Malamed111/17/2025
Sean Cunningham107/16/2025
KNF Services Crop104/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY Contracting & Safety Consulting203/21/2026
Synergy Strategic Design Architects303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ABC Construction ContGeneral Contractor607/08/2026
Eagle 1 MechanicalPlumbing510/09/2026
Empire Control Abatementspecialty_contractor403/21/2026
Empire Control AbatementScaffold203/21/2026
I.M.P. Plumbing & HeatingPlumbing207/08/2026
A.T.J. Electrical CoElectrical103/21/2026
Awl IndustriesGeneral Contractor104/09/2026
Perfetto Enterprises Co IScaffold107/01/2026
Air-Tek Mechanicalspecialty_contractor107/08/2026
Charan Electrical Enterp'sElectrical103/22/2026
KLK ElectricElectrical103/21/2026
Samco ElectricElectrical103/22/2026
Tru-Val ElectricElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Tectonic Engineering Cons106408/05/2026
MP Engineers & Architects1438107/30/2025
Future Tech Consultants O589901/30/2025
Building Lifecycle
All (168)Filed (27)Permit Issued (17)Violation (60)Inspection (2)Objection (32)Special Inspection (30)
10/08/2026
Permit issued — Plumbing
X00875799-S1-PL
08/05/2026
Filed — Alteration
Provide new Ceiling Mounted Exhaust Fan and Associated Ductwork and Louver.
X01260148-P1
07/31/2026
Objection resolved — Addressed
07/29/2026
Objection raised — Other
07/21/2026
Filed — Alteration
SUPPORT OF EXCAVATION FOR MANHOLE INSTALLATION. IN CONJUNCTION WITH JOB WITH JOB# X01164981.
X01431830-I1
07/01/2026
Objection raised — Other
07/01/2026
Objection raised — Other
06/22/2026
Filed — Alteration
X101 CTF-Class Reduction Project to include new HVAC controls and rebalance existing exhaust system to the CFM shown on drawings. Provide new exhaust fan and associated ductwork. Provide new interior lighting and controls.
X01405375-S3
06/22/2026
Filed — Alteration
X101 CTF-Class Reduction Project to include new HVAC controls and rebalance existing exhaust system to the CFM shown on drawings. Provide new exhaust fan and associated ductwork. Provide new interior lighting and controls.
X01405375-S2
06/19/2026
Filed — Alteration
X101 CTF-Class Reduction Project to include new HVAC controls and rebalance existing exhaust system to the CFM shown on drawings. Provide new exhaust fan and associated ductwork. Provide new interior lighting and controls.
X01405375-I1
06/19/2026
Special inspection requirement — Fire-Resistance Rated Construction
06/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/05/2026
Filed — Alteration
X101-B19_ CTF Room Conversion of Room B19 into Classrooms. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS PROPOSED UNDER THIS APPLICATION.
X01409288-I1
06/05/2026
Filed — Alteration
X101-B19_ CTF Room Conversion of Room B19 into Classrooms. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS PROPOSED UNDER THIS APPLICATION.
X01409288-S1
06/05/2026
Filed — Alteration
X101-B19_ CTF Room Conversion of Room B19 into Classrooms. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS PROPOSED UNDER THIS APPLICATION.
X01409288-S2
06/05/2026
Special inspection requirement — Final
06/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/05/2026
Special inspection requirement — Mechanical Systems
06/05/2026
Special inspection requirement — Lighting controls
06/05/2026
Special inspection requirement — HVAC-R and service water heating system controls
06/05/2026
Special inspection requirement — Duct leakage testing, insulation and design
06/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/05/2026
Special inspection requirement — Maintenance information
06/05/2026
Special inspection requirement — Interior lighting power
06/05/2026
Special inspection requirement — Energy Code Compliance Inspections
06/02/2026
Permit issued — Plumbing
X01164981-S2-PL
05/01/2026
Violation issued (ECB, open)
Construction
05/01/2026
Violation issued (ECB, open)
Construction
05/01/2026
Violation issued (ECB, open)
Construction
03/11/2026
Objection resolved — Addressed
03/02/2026
Objection raised — Other
02/17/2026
Filed — Alteration
Installation of a manhole
X01164981-S5
02/16/2026
Special inspection requirement — Subgrade Inspections
02/05/2026
Special inspection requirement — Final
02/05/2026
Special inspection requirement — Concrete - Precast
02/05/2026
Special inspection requirement — Concrete - Cast-In-Place
01/22/2026
Objection resolved — Resolved
01/22/2026
Special inspection requirement — Subgrade Inspections
12/23/2025
Objection raised — Other
12/22/2025
Filed — Alteration
Installation of a manhole
X01164981-S4
12/18/2025
Special inspection requirement — Concrete - Precast
11/17/2025
Filed — Alteration
X01318146-I1
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/07/2025
Filed — Alteration
Installation of a manhole
X01164981-S3
10/17/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
10/15/2025
Permit issued — Plumbing
X00875799-S1-PL
10/08/2025
Objection resolved — Addressed
10/08/2025
Special inspection requirement — Electrical motors and elevators
JAMES WILSON
10/08/2025
Special inspection requirement — Lighting controls
JAMES WILSON
10/08/2025
Special inspection requirement — Interior lighting power
JAMES WILSON
10/08/2025
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GHEBRYAL
10/06/2025
Objection resolved — Addressed
09/24/2025
Objection resolved — Addressed
08/13/2025
Objection raised — Other
08/13/2025
Objection raised — Other
08/12/2025
Objection raised — Other
07/30/2025
Filed — Alteration
Provide new Ceiling Mounted Exhaust Fan and Associated Ductwork and Louver.
X01260148-S2
07/30/2025
Filed — Alteration
Provide new Ceiling Mounted Exhaust Fan and Associated Ductwork and Louver.
X01260148-S1
Latest 60 of 168 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedEagle 1 Mechanical10/08/2026
DOB NOWPlumbingPermit IssuedI.M.P. Plumbing & Heating06/02/2026
DOB NOWPlumbingPermit IssuedEagle 1 Mechanical10/15/2025
DOB NOWConstruction FencePermit IssuedPerfetto Enterprises Co I07/30/2025
DOB NOWPlumbingPermit IssuedI.M.P. Plumbing & Heating05/09/2025
DOB NOWGeneral ConstructionPermit IssuedEmpire Control Abatement05/01/2025
DOB NOWGeneral ConstructionPermit IssuedABC Construction Cont04/29/2025
DOB NOWMechanical SystemsPermit IssuedAwl Industries04/29/2025
DOB NOWGeneral ConstructionPermit IssuedEmpire Control Abatement04/25/2025
DOB NOWConstruction FencePermit IssuedEmpire Control Abatement04/24/2025
DOB NOWPlumbingPermit IssuedEagle 1 Mechanical10/22/2024
DOB NOWGeneral ConstructionPermit IssuedABC Construction Cont05/14/2024
DOB NOWPlumbingPermit IssuedEagle 1 Mechanical10/27/2023
DOB NOWGeneral ConstructionPermit IssuedABC Construction Cont09/29/2023
DOB NOWPlumbingSigned-offEagle 1 Mechanical08/14/2023
DOB NOWMechanical SystemsSigned-offAir-Tek Mechanical08/01/2023
DOB NOWGeneral ConstructionPermit IssuedABC Construction Cont06/05/2023
BISMHISSUEDCentral Mechanical Systems03/27/2026
BISOTISSUEDCentral Mechanical Systems03/27/2026
BISMHISSUEDCentral Mechanical Systems03/27/2026
BISEQISSUEDCentral Mechanical Systems03/27/2026
BISOTISSUEDCentral Mechanical Systems03/27/2026
BISOTISSUEDCentral Mechanical Systems03/27/2026
BISEQISSUEDCentral Mechanical Systems03/12/2026
BISOTISSUEDCentral Mechanical Systems03/12/2026
BISMHISSUEDCentral Mechanical Systems03/12/2026
BISMHISSUEDCentral Mechanical Systems03/12/2026
BISOTISSUEDCentral Mechanical Systems03/12/2026
BISOTISSUEDCentral Mechanical Systems03/12/2026
BISPLISSUEDForsythe P&H06/12/2025
BISBLISSUEDForsythe P&H06/12/2025
BISOTISSUEDCentral Mechanical Systems03/27/2025
BISOTISSUEDCentral Mechanical Systems03/27/2025
BISOTISSUEDCentral Mechanical Systems03/27/2025
BISMHISSUEDCentral Mechanical Systems03/27/2025
BISEQISSUEDCentral Mechanical Systems03/27/2025
BISMHISSUEDCentral Mechanical Systems03/27/2025
BISBLISSUEDForsythe P&H06/04/2024
BISMHISSUEDCentral Mechanical Systems04/01/2024
BISOTISSUEDCentral Mechanical Systems04/01/2024
+ 27 more permits on file
5 projects · most recent 08/05/2026
Ventilation Systems Heating and Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
08/05/2026——Ventilation Systems
Ventilation
06/22/2026——Ventilation Systems—
06/05/2026——Ventilation Systems—
02/17/2026Permit IssuedEmpire Control AbatementHeating and Air Conditioning Systems, Heating Systems, Ventilation Systems
Heat / Cool
Trane TUHYE1203AN41AN 120,000 BTU · Condensing Unit ×2
UCCAC12A0G0RU0435041BBFDJ00BB 6,200 CFM · Ahu ×1
Heating
Marley CU935 17,000 BTU · Baseboard ×1
Ventilation
Trane ×4
09/21/2023Permit IssuedABC Construction ContVentilation Systems
Ventilation
N/A NA 2,100 CFM · Ductwork ×1
6 projects · most recent 08/05/2026
Water/Sanitary
FiledStatusContractorScope
08/05/2026——Water/Sanitary
06/22/2026——Water/Sanitary
06/05/2026——Water/Sanitary
02/17/2026Permit IssuedI.M.P. Plumbing & HeatingWater/Sanitary
12/10/2024Permit IssuedEagle 1 MechanicalWater/Sanitary
09/21/2023Signed-offEagle 1 MechanicalWater/Sanitary
22 projects · most recent 09/24/2026
General Wiring Lighting HVAC Wiring Boiler Controls
FiledStatusContractorScope
09/24/2026Permit IssuedA.T.J. Electrical CoGeneral Wiring
03/30/2026CompleteAnco Electl Contctng—
02/12/2026CompleteAnco Electl Contctng—
01/07/2026Permit IssuedKLK ElectricGeneral Wiring
09/26/2025CompleteAnco Electl Contctng—
09/18/2025Permit IssuedA.T.J. Electrical Co2 meters, 1 new_meters
08/11/2025CompleteAnco Electl Contctng—
07/23/2025Permit IssuedDNR ElectricGeneral Wiring
06/20/2024CompleteAnco Electl Contctng—
09/14/2023CompleteJamcob ElectricGeneral Wiring
06/21/2023CompleteAnco Electl Contctng—
06/15/2023CompleteMilad ContractingGeneral Wiring, Lighting
01/27/2023CompleteCharan Electrical Enterp's—
07/21/2022Permit IssuedSamco ElectricGeneral Wiring
01/24/2020Permit IssuedSamco Electric—
2 projects · most recent 07/21/2026
FiledStatusContractorScope
07/21/2026——4 scope_items
02/17/2026Permit IssuedI.M.P. Plumbing & Heating2 scope_items
1 project · most recent 04/17/2025
Fence
FiledStatusContractorScope
04/17/2025Permit IssuedEmpire Control AbatementFence
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
08/31/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/31/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 69
DateRequirementInspectorRole
06/19/2026Fire-Resistance Rated Construction—progress
06/19/2026Fire-Resistant Penetrations and Joints—special
06/05/2026HVAC-R and service water heating system controls—energy_progress
06/05/2026Fire-Resistant Penetrations and Joints—special
06/05/2026Final—progress
06/05/2026Lighting controls—energy_progress
06/05/2026Energy Code Compliance Inspections—progress
06/05/2026Mechanical Systems—special
06/05/2026Fire-Resistant Penetrations and Joints—special
06/05/2026Duct leakage testing, insulation and design—energy_progress
06/05/2026Interior lighting power—energy_progress
06/05/2026Maintenance information—energy_progress
02/16/2026Subgrade Inspections—special
02/05/2026Concrete - Cast-In-Place—special
02/05/2026Concrete - Precast—special
02/05/2026Final—progress
01/22/2026Subgrade Inspections—special
12/18/2025Concrete - Precast—special
10/17/2025Excavations - Sheeting, Shoring, and Bracing—special
10/08/2025Fire-Resistance Rated ConstructionGEORGE GHEBRYALprogress
10/08/2025Lighting controlsJAMES WILSONenergy_progress
10/08/2025Interior lighting powerJAMES WILSONenergy_progress
10/08/2025Electrical motors and elevatorsJAMES WILSONenergy_progress
07/28/2025HVAC-R and service water piping design and insulationJAMES WILSONenergy_progress
07/28/2025Mechanical SystemsJAMES WILSONspecial
Latest 25 of 69.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
P.S. 101XEducationFloor 1
Project X01431830 Alteration · Approved · 07/21/2026
Project X01250033 Alteration · Permit Entire · 07/16/2025
P.S. 304 Early Childhood SchoolEducationCellar, Sub-basement, Floor 1
Project X01405375 Alteration · Plan Examiner Review · 06/19/2026
Project X01409288 Alteration · Approved · 06/05/2026
Project X01318146 Alteration · Objections · 11/17/2025
Project X01260148 Alteration · Approved · 07/24/2025
Project X01210185 Alteration · Permit Entire · 04/17/2025
Project X01164981 Alteration · Permit Entire · 01/17/2025
Project X00875799 Alteration · Permit Entire · 05/22/2023
P.S. X101EducationFloor 1
Project X00838848 Alteration · Permit Entire · 03/07/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 185 on file (BIS + DOB NOW)
▸Plans & Drawings28
▸DOB NOWPlans/Sketch28
08/20/2026X00875799-P3Request digital key ↗
08/20/2026X00875799-P1Request digital key ↗
08/20/2026X00875799-S1Request digital key ↗
Showing 3 of 28 on file for this type
▸Seals & Professional Certifications48
▸DOB NOWDPL-1: Design Professional Seal & Signature29
08/23/2026X00838848-S1Open ↗
08/23/2026X00838848-I1Open ↗
08/23/2026X00838848-P1Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
09/17/2026X01164981-S1Open ↗
09/01/2026X00838848-S1Open ↗
09/01/2026X00875799-P1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/17/2026X01164981-S1Open ↗
09/17/2026X01164981-S1Open ↗
09/01/2026X00838848-S1Open ↗
Showing 3 of 8 on file for this type
▸Trade Schedules & Equipment1
▸BISFA - FDNY APPROVAL : FD-FAA1
02/12/2025201201886Open ↗
▸Safety & Tenant Protection2
▸DOB NOWNYCSCA - Approved Site Safety Plans2
08/13/2026X01210185-I1Open ↗
08/13/2026X01250033-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/20/2026X01164981-S3Open ↗
08/18/2026X01260148-I1Open ↗
08/18/2026X01260148-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/14/2026X01164981-I1Open ↗
▸Approvals, Objections & Sign-offs68
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter28
08/20/2026X01164981-S3Open ↗
08/18/2026X01250033-I1Open ↗
08/18/2026X01260148-P1Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)27
08/18/2026X01260148-P1Open ↗
08/16/2026X01409288-S2Open ↗
08/16/2026X01409288-S1Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWDEP Variance (V5) letter8
08/15/2026X01164981-S1Open ↗
08/15/2026X01164981-S2Open ↗
08/14/2026X01164981-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)5
08/14/2026X01405375-I1Open ↗
08/13/2026X01210185-I1Open ↗
08/13/2026X00838848-I1Open ↗
Showing 3 of 5 on file for this type
▸Filing & Intake Forms1
▸DOB NOWAI1 Form1
08/13/2026X00838848-I1Open ↗
▸Other Documents29
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal28
08/18/2026X01260148-P1Open ↗
08/16/2026X01409288-I1Open ↗
08/16/2026X01409288-S2Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWNYCSCA Exhibit 21
08/13/2026X01260148-S1Open ↗