| Owner | Filings | Most Recent |
|---|---|---|
| 2754 REALTY LLC | 2 | 03/22/2026 |
| 2754 CRESTON PROPERTY | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/09/2021 | $500K | — | Private party → 2754 CRESTON PROPERTY LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| RISE ARCHITECTURE | 6 | 08/12/2024 |
| NEW YORK ENGINEERS LLC | 5 | 05/30/2024 |
| MOHAMMAD AHEAD, PE | 2 | 06/01/2023 |
| M C STRUCTURAL ENGINEERING | 5 | 04/20/2023 |
| REVAP CONSULTING ENGINEERS LLC | 1 | 03/23/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| SALLY LOVE ASSOCIATES | 32 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SELCA CONSTRUCTION INC | General Contractor | 36 | 07/08/2026 |
| B SOSA ENTERPRISES CORP | General Contractor | 4 | 07/08/2026 |
| DYNAMIX SCAFFOLD GROUP LL | General Contractor | 3 | 07/08/2026 |
| GO PRO FIRE PROTECTION C | Fire Protection | 2 | 07/08/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 2 | 07/08/2026 |
| JEFF AKERMAN | Electrical | 2 | 03/21/2026 |
| MILAZZO DESIGN AND EXP | Electrical | 2 | 03/21/2026 |
| JAM ELECTRICAL CORP 003652 | General Contractor | 1 | 03/22/2026 |
| ANTHONY LUCIANO | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CONCRETE SOLUTIONS LAB CO | 5344 | 16 | 08/12/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Earth Work | Signed-off | SELCA CONSTRUCTION | 06/24/2024 |
| DOB NOW | Earth Work | Signed-off | SELCA CONSTRUCTION | 05/29/2024 |
| DOB NOW | Structural | Signed-off | SELCA CONSTRUCTION | 05/22/2024 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 05/02/2024 |
| DOB NOW | Sprinklers | Signed-off | GO PRO FIRE PROTECTION C | 03/13/2024 |
| DOB NOW | General Construction | Permit Issued | SELCA CONSTRUCTION | 02/06/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SELCA CONSTRUCTION | 01/02/2024 |
| DOB NOW | Construction Fence | Signed-off | SELCA CONSTRUCTION | 09/21/2023 |
| DOB NOW | Sprinklers | Signed-off | GO PRO FIRE PROTECTION C | 06/09/2023 |
| DOB NOW | Supported Scaffold | Signed-off | DYNAMIX SCAFFOLD GROUP LL | 06/01/2023 |
| DOB NOW | General Construction | Permit Issued | SELCA CONSTRUCTION | 05/18/2023 |
| DOB NOW | General Construction | Permit Issued | SELCA CONSTRUCTION | 04/28/2023 |
| DOB NOW | Structural | Signed-off | SELCA CONSTRUCTION | 04/28/2023 |
| DOB NOW | Earth Work | Signed-off | SELCA CONSTRUCTION | 04/28/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIX SCAFFOLD GROUP LL | 04/05/2023 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 03/02/2023 |
| DOB NOW | General Construction | Permit Issued | SELCA CONSTRUCTION | 02/27/2023 |
| DOB NOW | Earth Work | Signed-off | SELCA CONSTRUCTION | 02/27/2023 |
| DOB NOW | General Construction | Permit Issued | SELCA CONSTRUCTION | 12/30/2022 |
| DOB NOW | Earth Work | Signed-off | SELCA CONSTRUCTION | 12/16/2022 |
| DOB NOW | Structural | Signed-off | SELCA CONSTRUCTION | 12/16/2022 |
| DOB NOW | Support of Excavation | Signed-off | SELCA CONSTRUCTION | 12/13/2022 |
| DOB NOW | Earth Work | Signed-off | SELCA CONSTRUCTION | 10/20/2022 |
| DOB NOW | Construction Fence | Signed-off | SELCA CONSTRUCTION | 09/30/2022 |
| DOB NOW | Earth Work | Signed-off | B SOSA ENTERPRISES CORP | 06/02/2022 |
| DOB NOW | Construction Fence | Signed-off | B SOSA ENTERPRISES CORP | 04/01/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/21/2023 | Complete | JAM ELECTRICAL CORP | — |
| 06/30/2023 | Complete | LIFE SPOT ELECTRIC CORP | General Wiring |
| 04/12/2023 | Complete | HIGH QUALITY ELECTRIC OF | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/01/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/22/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/16/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 06/12/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/26/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/24/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/01/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/01/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/10/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/10/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/12/2024 | Vestibules | MINA HANNA | energy_progress |
| 08/12/2024 | Maintenance information | MINA HANNA | energy_progress |
| 08/12/2024 | Lighting controls | MINA HANNA | energy_progress |
| 08/12/2024 | Electrical motors and elevators | MINA HANNA | energy_progress |
| 08/12/2024 | Insulation placement and R values | MINA HANNA | energy_progress |
| 08/12/2024 | Interior lighting power | MINA HANNA | energy_progress |
| 08/12/2024 | Lighting in dwelling units | MINA HANNA | energy_progress |
| 08/12/2024 | Air barrier — testing | MINA HANNA | energy_progress |
| 08/12/2024 | Fenestration areas | MINA HANNA | energy_progress |
| 08/12/2024 | Air barrier continuity plan testing | MINA HANNA | energy_progress |
| 08/12/2024 | Protection of exposed foundation insulation | MINA HANNA | energy_progress |
| 08/12/2024 | Metering | MINA HANNA | energy_progress |
| 08/12/2024 | Concrete - Cast-In-Place | MINA HANNA | special |
| 08/12/2024 | Concrete - Precast | MINA HANNA | special |
| 08/12/2024 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 08/12/2024 | Masonry | MINA HANNA | special |
| 08/12/2024 | Energy Code Compliance Inspections | MINA HANNA | progress |
| 08/12/2024 | Fire-Resistance Rated Construction | MINA HANNA | progress |
| 08/12/2024 | Air barrier - visual inspection | MINA HANNA | energy_progress |
| 08/12/2024 | Exterior lighting power | MINA HANNA | energy_progress |
| 08/12/2024 | Fenestration and door U-factor and product ratings | MINA HANNA | energy_progress |
| 08/12/2024 | Fenestration air leakage | MINA HANNA | energy_progress |
| 08/01/2024 | Electrical motors and elevators | MINA HANNA | energy_progress |
| 08/01/2024 | Protection of exposed foundation insulation | MINA HANNA | energy_progress |
| 08/01/2024 | Air barrier - visual inspection | MINA HANNA | energy_progress |