| Owner | Filings | Most Recent |
|---|---|---|
| NYCHA | 60 | 09/13/2026 |
| NEW YORK CITY HOUSING AUTHORITY | 23 | 07/08/2026 |
| P K CONTRACTING | 4 | 04/09/2026 |
| NYCHA 9 99 | 1 | 03/22/2026 |
| NYC HOUSING AUTHORITY | 12 | 03/22/2026 |
| NYC HA 9 | 1 | 03/22/2026 |
| NYCHA 99 | 3 | 03/22/2026 |
| CASHMIN | 1 | 03/21/2026 |
| S N BUILDERS | 6 | 03/21/2026 |
| NAVTECH CONSTRUCTION | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JOEL PHAGOO P.E. PLLC | 4 | 04/01/2026 |
| RAMAN & OUNDJIAN ENGINEERS & ARCHIT | 2 | 01/04/2026 |
| VENTROP ENGINEERING CONSULTING GROU | 9 | 09/25/2023 |
| AK CONSULTING SERVICES, INC | 7 | 06/23/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| BAZINI ENGINEERING P C | 18 | 03/21/2026 |
| AK CONSULTING SERVICES | 18 | 03/21/2026 |
| LGML GROUP | 2 | 03/21/2026 |
| JOEL PHAGOO P.E. PLLC | 1 | 03/21/2026 |
| JOEL PHAGOO P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STEEL CONSTRUCTION LLC | General Contractor | 17 | 07/08/2026 |
| MNK ENTERPRISES LLC | General Contractor | 12 | 07/17/2026 |
| DYNAMIC US, INC | General Contractor | 5 | 07/08/2026 |
| P & K CONTRACTING INC | General Contractor | 4 | 07/08/2026 |
| DYNAMIC CONTRACTING CORP | Plumbing | 3 | 07/08/2026 |
| SKYWORX CONTRACTING INC | General Contractor | 2 | 07/08/2026 |
| SKYLINE P & H INC | Plumbing | 2 | 03/22/2026 |
| AMIN ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| RIGLIETTI MICHAEL | Electrical | 1 | 03/21/2026 |
| BALZOFIORE, F | Electrical | 1 | 03/21/2026 |
| CHARNJIT SINGH | Electrical | 1 | 03/21/2026 |
| KUWAILID, MOHAMED | Electrical | 1 | 03/21/2026 |
| LIBERTY FABRICATION INC | Electrical | 1 | 03/21/2026 |
| LIT MODE ELECL CONTG INC | Electrical | 1 | 03/22/2026 |
| MICHAEL RIGLIETTI | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AK CONSULTING SERVICES, I | 6198 | 8 | 08/07/2026 |
| BUREAU VERITAS NA | 6902 | 2 | 01/04/2026 |
| JOEL PHAGOO ,PE, PLLC | 2416 | 1 | 07/17/2025 |
| TECTONIC ENGINEERING CONS | 106 | 8 | 09/25/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 07/16/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | MNK ENTERPRISES LLC | 07/15/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | VENTURE NK CORP | 04/06/2026 |
| DOB NOW | General Construction | Permit Issued | P & K CONTRACTING INC | 04/02/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | WALL CONTRACTOR CORP | 12/18/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | ZORIA HOUSING LLC | 07/18/2025 |
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 07/11/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | MNK ENTERPRISES LLC | 07/11/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | MNK ENTERPRISES LLC | 07/05/2024 |
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 06/28/2024 |
| DOB NOW | General Construction | Signed-off | DYNAMIC US, INC | 02/13/2024 |
| DOB NOW | Sidewalk Shed | Permit Issued | MNK ENTERPRISES LLC | 02/01/2024 |
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 02/01/2024 |
| DOB NOW | Plumbing | Signed-off | DYNAMIC CONTRACTING CORP | 05/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | DYNAMIC US, INC | 03/10/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | MNK ENTERPRISES LLC | 03/02/2023 |
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 03/01/2023 |
| DOB NOW | Construction Fence | Permit Issued | SKYWORX CONTRACTING INC | 11/08/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | SKYWORX CONTRACTING INC | 11/02/2022 |
| DOB NOW | Boiler Equipment | Signed-off | DYNAMIC CONTRACTING CORP | 10/17/2022 |
| DOB NOW | Plumbing | Signed-off | DYNAMIC CONTRACTING CORP | 06/06/2022 |
| DOB NOW | Boiler Equipment | Signed-off | DOUGLAS SIMMONS | 05/28/2022 |
| DOB NOW | Boiler Equipment | Signed-off | DOUGLAS SIMMONS | 05/12/2022 |
| DOB NOW | Mechanical Systems | Signed-off | DYNAMIC US, INC | 04/21/2022 |
| DOB NOW | Boiler Equipment | Signed-off | DOUGLAS SIMMONS | 10/05/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | STEEL CONSTRUCTION LLC | 11/27/2020 |
| DOB NOW | Supported Scaffold | Signed-off | STEEL CONSTRUCTION LLC | 11/19/2020 |
| DOB NOW | Construction Fence | Signed-off | STEEL CONSTRUCTION LLC | 06/24/2020 |
| DOB NOW | Supported Scaffold | Signed-off | STEEL CONSTRUCTION LLC | 11/22/2019 |
| DOB NOW | Construction Fence | Signed-off | P & K CONTRACTING INC | 11/21/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | STEEL CONSTRUCTION LLC | 11/21/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | STEEL CONSTRUCTION LLC | 09/06/2019 |
| DOB NOW | Construction Fence | Signed-off | P & K CONTRACTING INC | 10/19/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | STEEL CONSTRUCTION LLC | 09/18/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | STEEL CONSTRUCTION LLC | 08/23/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | STEEL CONSTRUCTION LLC | 06/26/2018 |
| BIS | OT | ISSUED | P & K CONTRACTING INC | 07/14/2020 |
| BIS | OT | ISSUED | P & K CONTRACTING INC | 01/13/2020 |
| BIS | EQ | ISSUED | S & N BUILDERS INC | 06/30/2015 |
| BIS | EQ | ISSUED | S & N BUILDERS INC | 06/22/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/05/2026 | Permit Issued | LIT MODE ELECL CONTG INC | — |
| 06/05/2026 | Permit Issued | LIT MODE ELECL CONTG INC | — |
| 03/06/2025 | Permit Issued | LIT MODE ELECL CONTG INC | — |
| 05/18/2023 | Complete | TRI-STATE ELECL & MECHL I | General Wiring |
| 10/18/2022 | Complete | OHM'S ELECTRICAL CORP | General Wiring |
| 06/22/2020 | Permit Issued | AMIN ELECTRICAL CORP | — |
| 04/04/2019 | Complete | MAC FHIONNGHAILE & SONS | General Wiring |
| 06/14/2018 | Permit Issued | AMIN ELECTRICAL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2026 | Permit Issued | MNK ENTERPRISES LLC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | Permit Issued | P&K CONTRACTING INC | Suspended Scaffold (SC) |
| 12/16/2025 | Permit Issued | WALL CONTRACTOR CORP | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/15/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/15/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/28/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/23/2023 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 10/16/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/03/2022 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 07/19/2022 | Administrative Rejection Boiler Certification | Administrative Rejection | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/17/2026 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 08/17/2026 | Alternative Materials - OTCR Buildings Bulletin Number | MAHFUZAR RAHMAN | special |
| 08/07/2026 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 08/07/2026 | Alternative Materials - OTCR Buildings Bulletin Number | MAHFUZAR RAHMAN | special |
| 08/02/2026 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 08/02/2026 | Alternative Materials - OTCR Buildings Bulletin Number | MAHFUZAR RAHMAN | special |
| 07/06/2026 | Alternative Materials - OTCR Buildings Bulletin Number | MAHFUZAR RAHMAN | special |
| 07/06/2026 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 06/15/2026 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 06/15/2026 | Alternative Materials - OTCR Buildings Bulletin Number | MAHFUZAR RAHMAN | special |
| 12/29/2025 | Structural Stability – Alterations of existing buildings | IBRAHIM MOURAD | special |
| 12/29/2025 | Tenant Protection Plan Compliance | IBRAHIM MOURAD | special |
| 12/29/2025 | Final | IBRAHIM MOURAD | progress |
| 12/29/2025 | Masonry | IBRAHIM MOURAD | special |
| 12/29/2025 | Concrete - Cast-In-Place | IBRAHIM MOURAD | special |
| 12/29/2025 | Post-installed Anchors | IBRAHIM MOURAD | special |
| 12/15/2025 | Alternative Materials - OTCR Buildings Bulletin Number | MAHFUZAR RAHMAN | special |
| 12/15/2025 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 07/15/2025 | Post-installed Anchors | JOEL PHAGOO | special |
| 10/10/2023 | HVAC-R and service water piping design and insulation | GEORGE GHEBRYAL | energy_progress |
| 10/10/2023 | HVAC-R and service water heating equipment | GEORGE GHEBRYAL | energy_progress |
| 10/10/2023 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 10/10/2023 | HVAC-R and service water heating system controls | GEORGE GHEBRYAL | energy_progress |
| 10/10/2023 | Maintenance information | GEORGE GHEBRYAL | energy_progress |
| 09/28/2023 | HVAC-R and service water heating equipment | GEORGE GHEBRYAL | energy_progress |