| Owner | Filings | Most Recent |
|---|---|---|
| NYCHA | 32 | 07/08/2026 |
| NYC HOUSING AUTHORITY | 9 | 03/22/2026 |
| NYCHA 99 | 2 | 03/22/2026 |
| D.O.E. 0 | 1 | 03/22/2026 |
| PS 284 DOE | 2 | 03/22/2026 |
| P.S. 284 DEPT. OF EDUCATI | 3 | 03/22/2026 |
| OSBORNE TOWERS HDFC | 2 | 03/22/2026 |
| DEPARTMENT OF EDUCATION | 1 | 03/22/2026 |
| NEW YORK CITY HOUSING AUTHORITY | 4 | 03/22/2026 |
| NYC HOUSING AUTH | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SYNERGIC DESIGN ARCHITECTS | 1 | 05/13/2026 |
| LAKHANI & JORDAN | 2 | 09/10/2024 |
| JOEL PHAGOO P.E. PLLC | 4 | 08/24/2022 |
| SUPERSTRUCTURES ENG. + ARCH. | 2 | 07/06/2022 |
| AK CONSULTING SERVICES, INC | 4 | 04/14/2022 |
| BITOPI CONSULTANTS LLC | 2 | 03/30/2022 |
| IKRA CONSULTING LLC | 1 | 02/03/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| AK CONSULTING SERVICES | 14 | 03/21/2026 |
| SUPERSTRUCTURES ENG + ARCH | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ROMA SCAFFOLDING INC | General Contractor | 14 | 07/08/2026 |
| J & N CONSTRUCTION GROUP | General Contractor | 7 | 07/08/2026 |
| RICHARDS PLUM & HTG CO,IN | General Contractor | 3 | 03/21/2026 |
| FOY, REMER | Electrical | 1 | 03/21/2026 |
| H&F IRON WORKS | Electrical | 1 | 03/21/2026 |
| ACCORD POWER INC | General Contractor | 1 | 07/08/2026 |
| A1 EXPEDITING SERVICE COR | Electrical | 1 | 03/21/2026 |
| RICHARDS P AND H CO, INC | Plumbing | 1 | 07/08/2026 |
| ACCORD POWER ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| AMIN ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SYNERGIC DESIGN LLC | 8561 | 1 | 05/13/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 3 | 09/10/2024 |
| BUREAU VERITAS NA | 6902 | 2 | 04/14/2022 |
| IKRA CONSULTING LLC | 7032 | 1 | 02/03/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | ACCORD POWER INC | 06/01/2026 |
| DOB NOW | Plumbing | Signed-off | RICHARDS P AND H CO, INC | 10/25/2024 |
| DOB NOW | Mechanical Systems | Signed-off | RICHARDS PLUM & HTG CO,IN | 10/17/2024 |
| DOB NOW | General Construction | Signed-off | J & N CONSTRUCTION GROUP | 08/11/2022 |
| DOB NOW | Construction Fence | Signed-off | ROMA SCAFFOLDING INC | 07/07/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ROMA SCAFFOLDING INC | 06/21/2022 |
| DOB NOW | Construction Fence | Signed-off | J & N CONSTRUCTION GROUP | 05/12/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | J & N CONSTRUCTION GROUP | 05/03/2022 |
| DOB NOW | Supported Scaffold | Signed-off | ROMA SCAFFOLDING INC | 02/04/2022 |
| DOB NOW | General Construction | Signed-off | ROMA SCAFFOLDING INC | 12/29/2021 |
| DOB NOW | Construction Fence | Signed-off | ROMA SCAFFOLDING INC | 07/07/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | ROMA SCAFFOLDING INC | 06/21/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | ROMA SCAFFOLDING INC | 06/16/2020 |
| DOB NOW | Construction Fence | Signed-off | ROMA SCAFFOLDING INC | 05/11/2020 |
| DOB NOW | Construction Fence | Signed-off | ROMA SCAFFOLDING INC | 04/19/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | ROMA SCAFFOLDING INC | 02/25/2019 |
| BIS | OT | ISSUED | ZORIA HOUSING, LLC | 12/26/2013 |
| BIS | EQ | ISSUED | VIKRANT CONTRACTING & BUILDER | 10/22/2013 |
| BIS | PL | ISSUED | KORDUN CONSTRUCTION CORP | 06/14/2011 |
| BIS | EQ | ISSUED | AGFA CONSTRUCTION INC | 10/01/2009 |
| BIS | EQ | ISSUED | AGFA CONSTRUCTION INC | 04/16/2009 |
| BIS | PL | ISSUED | KORDUN CONSTRUCTION CORP | 04/14/2008 |
| BIS | PL | ISSUED | AMK CONT CORP | 10/05/2005 |
| BIS | OT | ISSUED | A.M.K. CONTRACTING CORP | 10/05/2005 |
| BIS | EQ | ISSUED | AMC UNITED INC | 04/26/2001 |
| BIS | EQ | ISSUED | PSG | 02/24/1998 |
| BIS | EQ | ISSUED | PSG CONSTRUCTION CO.INC | 03/24/1997 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/29/2025 | Permit Issued | ACCORD POWER ELECTRIC LLC | 2 meters, 1 new_meters |
| 07/16/2025 | Complete | GILSTON ELEC'L CONTNG LLC | General Wiring |
| 04/28/2022 | Permit Issued | LCJ ELEC'L CONTR'S INC | — |
| 07/19/2021 | Permit Issued | EIA ELECTRIC, INC | General Wiring |
| 04/19/2021 | Complete | HYLAN DATACOM & ELECL LLC | — |
| 09/11/2020 | Complete | AMIN ELECTRICAL CORP | — |
| 02/05/2019 | Complete | USA ELECT'L SERVICES CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Permit Issued | ACCORD POWER INC | 74 panels, 40.33 kw, 6,462.09 roof_area_sqft |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/02/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/11/2026 | Structural Stability – Alterations of existing buildings | Malathi Ananthakrishnan | special |
| 08/22/2025 | Air barrier - visual inspection | Malathi Ananthakrishnan | energy_progress |
| 08/22/2025 | Final | Malathi Ananthakrishnan | progress |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | Malathi Ananthakrishnan | special |
| 08/22/2025 | Energy Code Compliance Inspections | Malathi Ananthakrishnan | progress |
| 09/05/2024 | HVAC-R and service water piping design and insulation | Young Suh | energy_progress |
| 09/05/2024 | Maintenance information | Young Suh | energy_progress |
| 09/04/2024 | Energy Code Compliance Inspections | Young Suh | progress |
| 09/04/2024 | Tenant Protection Plan Compliance | Young Suh | special |
| 09/04/2024 | HVAC-R and service water piping design and insulation | Young Suh | energy_progress |
| 09/04/2024 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 09/04/2024 | Tenant Protection Plan Compliance | Young Suh | special |
| 08/23/2024 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 08/22/2024 | Final | Young Suh | progress |
| 08/22/2024 | Mechanical Systems | Young Suh | special |
| 07/07/2022 | Post-installed Anchors | Young Suh | special |
| 07/07/2022 | Final | Paul Millman | progress |
| 07/07/2022 | Insulation placement and R values | Young Suh | energy_progress |
| 07/07/2022 | Masonry | Young Suh | special |
| 05/26/2022 | Final | Paul Millman | progress |
| 05/26/2022 | Insulation placement and R values | — | energy_progress |
| 05/26/2022 | Post-installed Anchors | — | special |
| 05/26/2022 | Masonry | — | special |
| 04/14/2022 | Final | IBRAHIM MOURAD | progress |
| 04/14/2022 | Masonry | IBRAHIM MOURAD | special |