| Owner | Filings | Most Recent |
|---|---|---|
| TRINTY MORRIS CORP | 625 | 09/25/2026 |
| ROCK GROUP NY | 10 | 07/08/2026 |
| STRUCTURAL PRESFRY SYSTEM | 1 | 03/22/2026 |
| TRINITY MORRIS CORP JEFFR | 8 | 03/22/2026 |
| CONSULTING ENTERPRISE WOR | 1 | 03/22/2026 |
| CHARTER COMMUNICATIONS | 1 | 03/22/2026 |
| TRINITY MORRIS CORP C O29 BRDWAY | 14 | 03/21/2026 |
| TRINITY MORRIS CORP 29 BROADWAY | 5 | 03/21/2026 |
| TRINITY MORRIS CORP C O JEFFRIES | 17 | 03/21/2026 |
| TRINITY MORRIS CORP C O 29 BROAD | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 1 | 07/01/2026 |
| ASIF JAMIL, RA | 3 | 05/12/2020 |
| MG ENGINEERING D.P.C. | 4 | 12/10/2019 |
| KM ENGINEERING, D.P.C | 7 | 10/23/2019 |
| Z.S. ENGINEERING PC | 1 | 06/04/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN STUDIO | 6 | 03/21/2026 |
| BIG CITY EXPEDITING | 20 | 03/21/2026 |
| C6 | 2 | 03/21/2026 |
| SMEP DESIGN & CONSULTATION LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ENOBRAC PLUMBING, INC | Fire Protection | 6 | 07/08/2026 |
| COBURN PROJECT INTERIORS | General Contractor | 3 | 03/21/2026 |
| WESBUILT CONSTRUCTION MAN | General Contractor | 2 | 03/21/2026 |
| REEM PLBG & HTG CORP | Plumbing | 2 | 07/08/2026 |
| REEM PLBG & HTG CORP | Fire Protection | 2 | 07/08/2026 |
| ROCK GROUP NY CORP | General Contractor | 2 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 2 | 09/25/2026 |
| TRISTATE PLBG SVCS CORP | Plumbing | 1 | 07/08/2026 |
| ROBERT CHIMENTI | Electrical | 1 | 03/22/2026 |
| ROBERT LOGOZIO | Electrical | 1 | 03/21/2026 |
| YEVGENY KOLTUNOV | Electrical | 1 | 03/21/2026 |
| FIVE BOROUGH NYC LLC | Fire Protection | 1 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 1 | 07/08/2026 |
| BARRY SAXE | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PCS ENGINEERING | 3745 | 1 | 07/06/2026 |
| SPECIAL INSPECTION SERVIC | 1200 | 4 | 12/10/2019 |
| KM ENGINEERING, D.P.C. | 5745 | 7 | 10/23/2019 |
| CROSSCHECK INSPECTION SER | 544 | 1 | 06/04/2019 |
| ZS ENGINEERING PC | 919 | 2 | 06/04/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 09/24/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | 4 STAR CONTRACTING INC | 07/14/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 07/01/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 05/19/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 07/16/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 09/27/2021 |
| DOB NOW | Mechanical Systems | Signed-off | COBURN PROJECT INTERIORS | 11/17/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCK GROUP NY CORP | 09/29/2020 |
| DOB NOW | Mechanical Systems | Signed-off | WESBUILT CONSTRUCTION MAN | 03/20/2020 |
| DOB NOW | Plumbing | Signed-off | REEM PLBG & HTG CORP | 03/02/2020 |
| DOB NOW | Plumbing | Signed-off | TRISTATE PLBG SVCS CORP | 02/14/2020 |
| DOB NOW | Plumbing | Signed-off | REEM PLUMBING & HEATING C | 02/11/2020 |
| DOB NOW | Sprinklers | Signed-off | FIVE BOROUGH NYC LLC | 01/31/2020 |
| DOB NOW | Sprinklers | Signed-off | REEM PLBG & HTG CORP | 12/03/2019 |
| DOB NOW | Sprinklers | Signed-off | REEM PLUMBING & HEATING C | 12/03/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCK GROUP NY CORP | 10/31/2019 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 10/29/2019 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 08/02/2019 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 07/17/2019 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 06/12/2019 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 05/09/2019 |
| DOB NOW | Sprinklers | Signed-off | ENOBRAC PLUMBING, INC | 02/14/2019 |
| BIS | OT | ISSUED | STRUCTURAL PRESERV SYSTEM | 06/30/2021 |
| BIS | OT | ISSUED | ZYCH&SONS CONSTRUCTION * | 07/23/2020 |
| BIS | OT | ISSUED | VARIANT SERVICES INC | 07/09/2020 |
| BIS | OT | ISSUED | STRUCTURAL PRESERV SYSTEM | 06/19/2020 |
| BIS | OT | ISSUED | STRUCTURAL PRESERV SYSTEM | 01/03/2020 |
| BIS | OT | ISSUED | COBURN PROJECT INTERIORS | 12/27/2019 |
| BIS | OT | ISSUED | WESBUILT CONSTRUCTION MAN | 09/26/2019 |
| BIS | OT | ISSUED | LIBERTY CONTRACTING CORP | 09/12/2019 |
| BIS | OT | ISSUED | LIBERTY CONTRACTING CORP | 06/18/2019 |
| BIS | SP | ISSUED | ENOBRAC PLUMBING, INC | 08/24/2018 |
| BIS | MH | ISSUED | ON-TRAC CONSTRUCTION ASSO | 06/29/2018 |
| BIS | OT | ISSUED | ON-TRAC CONSTRUCTION ASSO | 06/29/2018 |
| BIS | PL | ISSUED | M&M PLBG & HTG INC | 06/29/2018 |
| BIS | MH | ISSUED | ON-TRAC CONSTRUCTION ASSO | 06/21/2018 |
| BIS | OT | ISSUED | ON-TRAC CONSTRUCTION ASSO | 06/21/2018 |
| BIS | SP | ISSUED | ENOBRAC PLUMBING, INC | 06/18/2018 |
| BIS | SP | ISSUED | CAPITOL FIRE SPRINKLER CO | 06/05/2018 |
| BIS | OT | ISSUED | LIBERTY CONTRACTING CORP | 06/04/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | Permit Issued | BOROWIDE ELECT'L CONTR'S | — |
| 03/12/2026 | Permit Issued | T. DIRUSSO ELEC'L CONT IN | General Wiring |
| 09/30/2022 | Permit Issued | ROBERT CHIMENTI | 11 meters, 1 new_meters |
| 04/21/2021 | Complete | CEDAR ELEC'L CONT'RS INC. | General Wiring |
| 08/17/2020 | Permit Issued | GENMAR ELECT. CONT'G CORP | General Wiring |
| 07/30/2020 | Complete | TROON ELECTRIC OF NEW YOR | General Wiring |
| 10/23/2019 | Permit Issued | B.P. ELECTRIC CORP | — |
| 10/07/2019 | Complete | NOVA ELECTRIC LLC | General Wiring |
| 07/08/2018 | Complete | C.Q. ELECTR'L CONTRG CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | ANDAMIO SCAFFOLDING LLC | Sidewalk Shed |
| 05/12/2020 | Signed-off | PLATINUM SERVICES NY LLC | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/06/2026 | Permit Issued | 4 STAR CONTRACTING INC | Suspended Scaffold (SC) |
| 07/09/2024 | Signed-off | STRUCTUAL PRESV SYSTEM | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/02/2019 | HVAC insulation and sealing | Christopher Drutjons | energy_progress |
| 10/02/2019 | HVAC and service water heating equipment | Christopher Drutjons | energy_progress |
| 10/02/2019 | Duct leakage testing | Christopher Drutjons | energy_progress |
| 10/02/2019 | HVAC and service water heating system controls | Christopher Drutjons | energy_progress |
| 09/12/2019 | Sprinkler Systems | Christopher Drutjons | special |
| 09/12/2019 | Mechanical Systems | Christopher Drutjons | special |
| 09/12/2019 | Final | Christopher Drutjons | progress |
| 07/11/2019 | Sprinkler Systems | KRZYSZTOF MURAWSKI | special |
| 07/10/2019 | Sprinkler Systems | KRZYSZTOF MURAWSKI | special |
| 07/10/2019 | Final | KRZYSZTOF MURAWSKI | progress |
| 06/03/2019 | Post-installed Anchors | EUGENE BIFULCO | special |
| 06/02/2019 | Fire-Resistant Penetrations and Joints | OVIDIU IORGOVAN | special |
| 06/02/2019 | Final | KRZYSZTOF MURAWSKI | progress |
| 05/25/2019 | Sprinkler Systems | OVIDIU IORGOVAN | special |
| 04/15/2019 | Sprinkler Systems | KRZYSZTOF MURAWSKI | special |
| 04/15/2019 | Final | KRZYSZTOF MURAWSKI | progress |