← Back
Elevator apt, fireproof without stores
Brevoort (NYCHA)
291 PATCHEN AVENUE · BIN 3325171
💬 Discuss this project
1980Year Built
7Stories
D3Building Class
R5Zoning
875,875 sfGross Floor Area
896Units
LL97 Covered14 Open Violations 1 unresolved · 13 paperwork only ▸FISP: No Report FiledFDNY Report ↗
Elevator apt, fireproof without stores · Owner of record: NYC HOUSING AUTHORITY · 747,200 sf lot · 1.17 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction3p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 81p · 1 filing · 20 docs
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA3807/08/2026
T-MOBILE303/22/2026
NYC HOUSING AUTHORITY 9103/22/2026
NYCHA 99503/22/2026
NYC HOUSING AUTHORITY603/21/2026
ZORIA HOUSING303/21/2026
OFFICE OF DESIGN-NYCHA203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BILTMORE GROUP203/21/2026
JENNY FLORES EXPEDITING503/21/2026
AK CONSULTING SERVICES803/21/2026
SMEP DESIGN & CONSULTATION LLC203/21/2026
PURCELL EVERETT ARCHITECTS803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ROMA SCAFFOLDING INCGeneral Contractor607/08/2026
KORDUN CONSTRUCTION CORPGeneral Contractor407/08/2026
GOTHAM COMMUNICATIONS LLCGeneral Contractor303/21/2026
FOY, REMERElectrical203/21/2026
H&F IRON WORKSElectrical203/21/2026
RYBURN PHILLIPSElectrical203/21/2026
KORDUN CONSTRUCTION CORPPlumbing207/08/2026
STANTON, TElectrical103/21/2026
RIVERA, EDWARDElectrical103/21/2026
JEFF SKOWRONSKIElectrical103/21/2026
HYLAN DATACOM & ELECL LLCElectrical103/22/2026
SKOWRONSKI JEFFElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ALAN MARGOLIN & ASSOC423403/07/2023
BITOPI CONSULTANTS LLC7036101/18/2023
GBN ENGINEERING LLC4670101/06/2022
BUREAU VERITAS NA6902206/08/2021
Building Lifecycle
All (93)Filed (15)Permit Issued (12)Signed Off (7)Facade (FISP) (10)Violation (16)Inspection (5)Special Inspection (28)
06/30/2026
Permit issued — Suspended Scaffold
B01155542-I1-SC
03/04/2026
Signed off — Alteration
HEREBY FILING FOR THE REPLACEMENT OF HOT WATER HEATERS. NO CHANGE TO USE OCCUPANCY OR EGRESS.
B00472716-I1
01/16/2026
Signed off — Alteration
B00484780-I1
11/28/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
IBRAHIM MOURAD
11/28/2025
Special inspection requirement — HVAC-R and service water heating equipment
IBRAHIM MOURAD
11/28/2025
Special inspection requirement — Energy Code Compliance Inspections
IBRAHIM MOURAD
11/28/2025
Special inspection requirement — HVAC-R and service water heating system controls
IBRAHIM MOURAD
11/26/2025
Filed — Alteration
HEREBY FILING FOR THE REPLACEMENT OF HOT WATER HEATERS. NO CHANGE TO USE OCCUPANCY OR EGRESS.
B00472716-P1
11/12/2025
Signed off — Alteration
B00484771-I1
10/17/2025
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
10/14/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/06/2025
Permit issued — Structural
B00484771-I1-ST
05/06/2025
Permit issued — Mechanical Systems
B00484780-I1-MS
05/05/2025
Permit issued — Plumbing
B00472716-I1-PL
04/02/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/03/2025
Permit issued — Suspended Scaffold
B01155542-I1-SC
01/30/2025
Filed — Alteration
FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site Supervisor: Jesus Decola
B01155542-I1
01/22/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/02/2025
Violation issued (FDNY_NOV, closed)
09/05/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
05/06/2024
Permit issued — Mechanical Systems
B00484780-I1-MS
05/06/2024
Permit issued — Plumbing
B00472716-I1-PL
05/06/2024
Permit issued — Structural
B00484771-I1-ST
04/11/2024
Violation issued (ECB, open)
Local Law
11/17/2023
Special inspection requirement — Concrete - Cast-In-Place
IBRAHIM MOURAD
11/17/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
IBRAHIM MOURAD
11/17/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
IBRAHIM MOURAD
11/17/2023
Special inspection requirement — Final
IBRAHIM MOURAD
11/17/2023
Special inspection requirement — Sprayed fire-resistant materials
IBRAHIM MOURAD
11/14/2023
Filed — Alteration
B00484771-P1
09/04/2023
Signed off — Alteration
INSTALLATION OF PIPE SCAFFOLD AT 234 RALPH AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B00814241-I1
09/04/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 234 RALPH AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B08046224-I1
08/31/2023
Signed off — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 234 RALPH AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B08046217-I1
05/23/2023
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 234 RALPH AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B08046217-P1
03/17/2023
Violation issued (FDNY_NOV, closed)
03/07/2023
Filed — Alteration
BLDG #13 ROOFING REPLACEMENT AND RAILING REMOVAL WITH ASSOCIATED BULKHEAD ALTERATIONS. ALL AS PER PLANS SUBMITTED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B08053472-P1
02/28/2023
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
Young Suh
02/28/2023
Special inspection requirement — Post-installed Anchors
Young Suh
02/28/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Young Suh
02/28/2023
Special inspection requirement — Structural Cold-Formed Steel
Young Suh
02/28/2023
Special inspection requirement — Final
Young Suh
02/28/2023
Special inspection requirement — Tenant Protection Plan Compliance
02/28/2023
Special inspection requirement — Structural Steel - Welding
Young Suh
02/28/2023
Special inspection requirement — Structural Steel - High Strength Bolting
Young Suh
02/28/2023
Special inspection requirement — Structural Steel - Details
Young Suh
02/28/2023
Special inspection requirement — Concrete - Cast-In-Place
Young Suh
02/28/2023
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Young Suh
02/28/2023
Special inspection requirement — Masonry
Young Suh
02/22/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/13/2023
Permit issued — General Construction
B08053472-I1-GC
01/18/2023
Filed — Alteration
INSTALLATION OF PIPE SCAFFOLD AT 234 RALPH AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B00814241-I1
01/17/2023
Special inspection requirement — Post-installed Anchors
KAMRUL AHSAN
12/29/2022
Permit issued — Construction Fence
B08046224-I1-FN
12/28/2022
Filed — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 234 RALPH AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B08046224-I1
12/28/2022
Permit issued — Sidewalk Shed
B08046217-I1-SH
12/27/2022
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 234 RALPH AVENUE, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B08046217-I1
12/23/2022
Filed — Alteration
BLDG #13 ROOFING REPLACEMENT AND RAILING REMOVAL WITH ASSOCIATED BULKHEAD ALTERATIONS. ALL AS PER PLANS SUBMITTED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B08053472-S2
12/20/2022
Filed — Alteration
BLDG #13 ROOFING REPLACEMENT AND RAILING REMOVAL WITH ASSOCIATED BULKHEAD ALTERATIONS. ALL AS PER PLANS SUBMITTED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B08053472-S1
12/19/2022
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
12/15/2022
Filed — Alteration
BLDG #13 ROOFING REPLACEMENT AND RAILING REMOVAL WITH ASSOCIATED BULKHEAD ALTERATIONS. ALL AS PER PLANS SUBMITTED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B08053472-I1
Latest 60 of 93 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM06/30/2026
DOB NOWStructuralSigned-offKORDUN CONSTRUCTION CORP05/06/2025
DOB NOWMechanical SystemsSigned-offKORDUN CONSTRUCTION CORP05/06/2025
DOB NOWPlumbingSigned-offKORDUN CONSTRUCTION CORP05/05/2025
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM02/03/2025
DOB NOWMechanical SystemsSigned-offKORDUN CONSTRUCTION CORP05/06/2024
DOB NOWPlumbingSigned-offKORDUN CONSTRUCTION CORP05/06/2024
DOB NOWStructuralSigned-offKORDUN CONSTRUCTION CORP05/06/2024
DOB NOWGeneral ConstructionSigned-offROMA SCAFFOLDING INC02/13/2023
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC12/29/2022
DOB NOWSidewalk ShedSigned-offROMA SCAFFOLDING INC12/28/2022
DOB NOWAntennaSigned-offGOTHAM COMMUNICATIONS LLC08/09/2022
BISEQISSUEDVIKRANT CONTRACTING & BUILDER05/16/2014
BISEQISSUEDVIKRANT CONTRACTING & BUILDER05/16/2014
BISEQISSUEDZORIA HOUSING, LLC03/20/2014
BISOTISSUEDZORIA HOUSING, LLC03/19/2014
BISEQISSUEDMETROPOLITAN ENTERPRISES02/26/2014
BISEQISSUEDVIKRANT CONTRACTING & BUILDER02/18/2014
BISOTISSUEDVERTICAL SOLUTIONS INC01/06/2014
BISEQISSUEDMETROPOLITAN ENTERPRISES05/07/2013
BISEQISSUEDMETROPOLITAN ENTERPRISES05/08/2012
BISEQISSUEDMETROPOLITAN ENTERPR INC05/20/2011
BISEQISSUEDMETROPOLITAN ENTERPR INC08/02/2010
BISOTISSUEDCELLULAR CONTRACTING SERVICES11/01/2006
BISOTISSUEDCELLULAR CONTRACTING SERVICES10/05/2006
1 project · most recent 03/07/2023
Storm
FiledStatusContractorScope
03/07/2023——Storm
7 projects · most recent 12/17/2025
General Wiring
FiledStatusContractorScope
12/17/2025Permit IssuedACCORD POWER ELECTRIC LLC2 meters, 1 new_meters
02/09/2025CompletePOLARIS ELEC'L CONST CORP—
02/09/2025CompletePOLARIS ELEC'L CONST CORP—
04/25/2024CompleteA.T.J. ELECTRICAL CO.INC.General Wiring
01/01/2024CompleteHYLAN DATACOM & ELECL LLC—
01/01/2024CompleteHYLAN DATACOM & ELECL LLC—
06/26/2023Permit IssuedMECO ELECTRIC CO. INC.General Wiring
1 project · most recent 03/07/2023
Steel Concrete Masonry
FiledStatusContractorScope
03/07/2023Signed-offROMA SCAFFOLDING INCSteel, Concrete, Masonry
1 project · most recent 01/30/2025
FiledStatusContractorScope
01/30/2025Permit IssuedSTRUCTUAL PRESV SYSTEM—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
10/17/2025Pass-Final PL - UndergroundPassView ↗
10/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/02/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/22/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/05/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
11/28/2025HVAC-R and service water piping design and insulationIBRAHIM MOURADenergy_progress
11/28/2025HVAC-R and service water heating equipmentIBRAHIM MOURADenergy_progress
11/28/2025Energy Code Compliance InspectionsIBRAHIM MOURADprogress
11/28/2025HVAC-R and service water heating system controlsIBRAHIM MOURADenergy_progress
11/17/2023Concrete - Cast-In-PlaceIBRAHIM MOURADspecial
11/17/2023Structural Stability – Alterations of existing buildingsIBRAHIM MOURADspecial
11/17/2023Fire-Resistant Penetrations and JointsIBRAHIM MOURADspecial
11/17/2023FinalIBRAHIM MOURADprogress
11/17/2023Sprayed fire-resistant materialsIBRAHIM MOURADspecial
02/28/2023Mastic and Intumescent Fire-resistant CoatingsYoung Suhspecial
02/28/2023Post-installed AnchorsYoung Suhspecial
02/28/2023Structural Stability – Alterations of existing buildingsYoung Suhspecial
02/28/2023Structural Cold-Formed SteelYoung Suhspecial
02/28/2023FinalYoung Suhprogress
02/28/2023Tenant Protection Plan Compliance—special
02/28/2023Structural Steel - WeldingYoung Suhspecial
02/28/2023Structural Steel - High Strength BoltingYoung Suhspecial
02/28/2023Structural Steel - DetailsYoung Suhspecial
02/28/2023Concrete - Cast-In-PlaceYoung Suhspecial
02/28/2023Construction Operations Influencing Adjacent StructuresYoung Suhspecial
02/28/2023MasonryYoung Suhspecial
01/17/2023Post-installed AnchorsKAMRUL AHSANspecial
12/19/2022Tenant Protection Plan ComplianceYoung Suhspecial
12/12/2022Insulation placement and R valuesYoung Suhenergy_progress
12/12/2022FinalYoung Suhprogress
Latest 25 of 28.
▾Documents — 180 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch13
09/01/2026B00484780-I1Request digital key ↗
08/31/2026B00641707-I1Request digital key ↗
08/28/2026B08053472-I1Request digital key ↗
Showing 3 of 13 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
09/01/2026B00472716-I1Request digital key ↗
08/15/2026B00472716-P1Request digital key ↗
▸Applications & Permits23
▸BISPLAN / WORK APPROVAL APPLICATION13
12/28/2023340682924Open ↗
05/29/2020320869271Open ↗
03/27/2020340682924Open ↗
Showing 3 of 13 on file for this type
▸BISWORK PERMIT APPLICATION10
06/11/2014340119552Open ↗
05/31/2014320198031Open ↗
03/20/2014340128533Open ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications47
▸DOB NOWDPL-1: Design Professional Seal & Signature14
09/01/2026B00472716-I1Open ↗
09/01/2026B00472716-P1Open ↗
09/01/2026B00484780-I1Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
08/07/2015320198031Open ↗
08/07/2015320198031Open ↗
04/22/2015340118483Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/17/2026B00814241-I1Open ↗
08/29/2026B00484771-I1Open ↗
08/29/2026B00484771-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
08/29/2026B00484771-I1Open ↗
08/28/2026B08053472-P1Open ↗
08/25/2026B00472716-I1Open ↗
Showing 3 of 6 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
03/20/2014340128533Open ↗
03/18/2014340118483Open ↗
02/14/2014340119552Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
03/20/2014340128533Open ↗
03/18/2014340118483Open ↗
02/14/2014340119552Open ↗
▸BISAPPLICANT OWNER SIGNATURE3
08/08/2019340682924Open ↗
06/03/2019340671632Open ↗
05/03/2019340668753Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
03/20/2014340128533Open ↗
03/18/2014340118483Open ↗
02/14/2014340119552Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
08/03/2010320198031Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
08/03/2010320198031Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
08/08/2019340682924Open ↗
▸Safety & Tenant Protection3
▸BISTENANT PROTECTION PLAN AND NOTES3
08/08/2019340682924Open ↗
06/03/2019340671632Open ↗
05/03/2019340668753Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
09/01/2026B00472716-I1Open ↗
09/01/2026B00484780-I1Open ↗
08/26/2026B00484771-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
08/03/2010320198031Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/18/2014340118483Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/31/2026B00641707-I1Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
10/12/2022340668753Open ↗
02/19/2021340671632Open ↗
04/30/2020340682924Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
12/18/2020302233394Open ↗
09/20/2020302233394Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026B00484780-I1Open ↗
08/13/2026B00472716-I1Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
02/14/2014340119552Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/30/2013320869271Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
03/18/2014340118483Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY11
02/08/2023340671632Open ↗
10/12/2022340668753Open ↗
02/23/2021340671632Open ↗
Showing 3 of 11 on file for this type
▸Approvals, Objections & Sign-offs28
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter14
09/01/2026B00472716-I1Open ↗
09/01/2026B00472716-P1Open ↗
09/01/2026B00484780-I1Open ↗
Showing 3 of 14 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
12/18/2020302233394Open ↗
08/07/2015320198031Open ↗
04/22/2015340118483Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
08/07/2015320198031Open ↗
04/22/2015340118483Open ↗
01/08/2015340119552Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
12/30/2013320869271Open ↗
08/03/2010320198031Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)2
08/13/2026B00484780-I1Open ↗
08/13/2026B00641707-I1Open ↗
▸BISLETTERS - APPRVD FAB CERT-COMPLIANCE1
01/08/2015340128533Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT9
12/18/2020302233394Open ↗
09/20/2020302233394Open ↗
04/10/2020340682924Open ↗
Showing 3 of 9 on file for this type
▸Filing & Intake Forms22
▸BISADDITIONAL INFORMATION15
02/19/2021340671632Open ↗
12/03/2020340671632Open ↗
12/03/2020340671632Open ↗
Showing 3 of 15 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
08/08/2019340682924Open ↗
06/03/2019340671632Open ↗
05/03/2019340668753Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET1
08/03/2010320198031Open ↗
▸Other Documents1
▸DOB NOWIRA Certification1
08/13/2026B01155542-I1Open ↗