Elevator apt, fireproof without stores
Parkside (NYCHA)
2968 BRONX PARK EAST · BIN 2101746
💬 Discuss this project
1950Year Built
14Stories
D3Building Class
R6Zoning
791,000 sfGross Floor Area
9,669Units
LL97 Covered1 Active Violation ▸FISP: No Report FiledFDNY Report ↗
Elevator apt, fireproof without stores · Owner of record: NYC Housing Authority · 397,864 sf lot · 1.99 FAR built · Flood zone X
Locations of Work
StructuralGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 11 filing · 20 docs
Sub-BasementNYC Housing Authority1 filing · 9 docs
Filed — no permit issuedNYC Housing Authority12p · 1 filing · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
New York City Housing Authority3210/04/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NYCHA1208/12/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
New York City Housing Authority603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Power Surge ElectricElectrical103/21/2026
Selectric Electrical Cont Co IElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Bureau Veritas Na6902308/06/2026
Building Lifecycle
All (78)Filed (12)Facade (FISP) (12)Violation (20)Objection (4)Special Inspection (30)
09/24/2026
Objection resolved — Resolved
09/24/2026
Objection resolved — Resolved
08/25/2026
Objection raised — Other
08/25/2026
Objection raised — Other
08/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/17/2026
Special inspection requirement — Mechanical Systems
08/17/2026
Special inspection requirement — Final
08/17/2026
Special inspection requirement — Maintenance information
08/17/2026
Special inspection requirement — Shutoff dampers
08/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
08/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
08/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
08/12/2026
Filed — Alteration
Replace existing HVAC Systems with new. Provide Variable Refrigerant Flow (VRF) system to serve occupied areas. Provide a make up air unit for ventilation in the occupied area. Provide exhaust fans to serve restroom and kitchen.
X00508048-P4
08/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/11/2026
Special inspection requirement — Mechanical Systems
08/11/2026
Special inspection requirement — Final
08/11/2026
Special inspection requirement — Maintenance information
08/11/2026
Special inspection requirement — HVAC-R and service water heating equipment
08/11/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
08/11/2026
Special inspection requirement — Shutoff dampers
08/11/2026
Special inspection requirement — HVAC-R and service water heating system controls
08/10/2026
Filed — Alteration
Replacement of two compartment sink with 3 compartment sink and kitchen range (domestic type). Providing a new grease interceptor.
X00517532-P2
08/07/2026
Special inspection requirement — Final
IBRAHIM MOURAD
08/07/2026
Special inspection requirement — Post-installed Anchors
IBRAHIM MOURAD
08/07/2026
Special inspection requirement — Structural Steel - Details
IBRAHIM MOURAD
08/07/2026
Special inspection requirement — Concrete - Cast-In-Place
IBRAHIM MOURAD
08/06/2026
Filed — Alteration
TO PROVIDE AN INCREASED SIZE OF EXISTING CONCRETE PAD ON GRADE FOR NEW MECHANICAL UNIT AND PROVIDE METAL FENCE WITH MESH AND GATE AROUND THE NEW MECHANICAL UNIT AT CONCRETE PAD
X00514816-P7
08/03/2026
Special inspection requirement — Final
IBRAHIM MOURAD
08/03/2026
Special inspection requirement — Structural Steel - Details
IBRAHIM MOURAD
08/03/2026
Special inspection requirement — Post-installed Anchors
IBRAHIM MOURAD
08/03/2026
Special inspection requirement — Concrete - Cast-In-Place
IBRAHIM MOURAD
11/26/2025
Violation issued (FDNY_ORDER, closed)
11/26/2025
Violation issued (FDNY_ORDER, closed)
02/27/2025
Violation issued (FDNY_ORDER, closed)
08/26/2024
Violation issued (FDNY_NOV, closed)
02/22/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/17/2024
Violation issued (FDNY_NOV, closed)
07/28/2022
Filed — Alteration
Replacement of two compartment sink with 3 compartment sink and kitchen range (domestic type). Providing a new grease interceptor.
X00517532-P1
05/02/2022
Filed — Alteration
TO PROVIDE AN INCREASED SIZE OF EXISTING CONCRETE PAD ON GRADE FOR NEW MECHANICAL UNIT AND PROVIDE METAL FENCE WITH MESH AND GATE AROUND THE NEW MECHANICAL UNIT AT CONCRETE PAD
X00514816-P6
05/02/2022
Special inspection requirement — Concrete - Cast-In-Place
05/02/2022
Special inspection requirement — Post-installed Anchors
05/02/2022
Special inspection requirement — Structural Steel - Details
05/02/2022
Special inspection requirement — Final
04/15/2022
Filed — Alteration
Replace existing HVAC Systems with new. Provide Variable Refrigerant Flow (VRF) system to serve occupied areas. Provide a make up air unit for ventilation in the occupied area. Provide exhaust fans to serve restroom and kitchen.
X00508048-P3
03/31/2022
Filed — Alteration
Replace existing HVAC Systems with new. Provide Variable Refrigerant Flow (VRF) system to serve occupied areas. Provide a make up air unit for ventilation in the occupied area. Provide exhaust fans to serve restroom and kitchen.
X00508048-P2
03/18/2022
Filed — Alteration
TO PROVIDE AN INCREASED SIZE OF EXISTING CONCRETE PAD ON GRADE FOR NEW MECHANICAL UNIT AND PROVIDE METAL FENCE WITH MESH AND GATE AROUND THE NEW MECHANICAL UNIT AT CONCRETE PAD
X00514816-P1
02/09/2022
Special inspection requirement — Final
02/09/2022
Special inspection requirement — Post-installed Anchors
01/20/2022
Filed — Alteration
Replace existing HVAC Systems with new. Provide Variable Refrigerant Flow (VRF) system to serve occupied areas. Provide a make up air unit for ventilation in the occupied area. Provide exhaust fans to serve restroom and kitchen.
X00508048-P1
12/17/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/07/2021
Filed — Alteration
Replace existing HVAC Systems with new. Provide Variable Refrigerant Flow (VRF) system to serve occupied areas. Provide a make up air unit for ventilation in the occupied area. Provide exhaust fans to serve restroom and kitchen.
X00508048-I1
05/07/2021
Filed — Alteration
Replacement of two compartment sink with 3 compartment sink and kitchen range (domestic type). Providing a new grease interceptor.
X00517532-I1
05/03/2021
Filed — Alteration
TO PROVIDE AN INCREASED SIZE OF EXISTING CONCRETE PAD ON GRADE FOR NEW MECHANICAL UNIT AND PROVIDE METAL FENCE WITH MESH AND GATE AROUND THE NEW MECHANICAL UNIT AT CONCRETE PAD
X00514816-I1
12/04/2017
Violation issued (FDNY_ORDER, closed)
03/20/2017
Cycle 8 facade report submitted
03/03/2017
Cycle 8 facade report signed — SAFE
02/23/2017
Cycle 8 facade inspection completed
01/03/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/07/2016
Cycle 7 facade report submitted
11/18/2016
Cycle 7 facade report signed — SAFE
Latest 60 of 78 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDAccord Power11/17/2023
BISEQISSUEDNavillus Tile11/01/2016
BISEQISSUEDNavillus Tile10/26/2016
BISOTISSUEDNavillus Tile05/13/2016
BISOTISSUEDNavillus Tile03/07/2016
BISEQISSUEDNavillus Tile03/07/2016
BISEQISSUEDNavillus Tile11/02/2015
BISEQISSUEDNavillus Tile11/02/2015
BISEQISSUEDFarh Construction10/09/2003
BISPLISSUEDOlympia Mechanical02/12/2003
BIS—ISSUEDA.A.D. Construction10/29/2002
BISPLISSUEDLafata Corallo P & H05/28/2002
BIS—ISSUEDA.A.D. Construction04/18/2002
BISEQISSUEDA.A.D. Construction04/18/2002
BISPLISSUEDLafata-Corallo PLG & Heating05/22/2001
BISEQISSUEDA.A.D. Construction04/25/2001
BIS—ISSUEDA.A.D. Construction04/25/2001
1 project · most recent 08/12/2026
Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/12/2026——Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
Cooling
Mitsubishi Electric PUHY-P312 SKMU-A (-BS) 312,000 BTU · Vrf Outdoor ×8
Heating
Rupp Air RARTU1-E-302-13-7.5T-DOAS 102,000 BTU · Makeup Air ×8
Ventilation
Rupp Air M017EL RARTU1-E-302-13-7.5T-DOAS 1,600 CFM · Ahu ×8
1 project · most recent 08/10/2026
Gas Water/Sanitary
FiledStatusContractorScope
08/10/2026——Gas, Water/Sanitary
4 projects · most recent 04/16/2026
General Wiring
FiledStatusContractorScope
04/16/2026CompleteTri-State Electrical & Mechanical IGeneral Wiring
08/06/2024CompleteJemco Electric Contractors—
03/07/2024CompleteJemco Electric Contractors—
01/02/2024CompletePower Surge Electric2 meters, 1 new_meters
1 project · most recent 08/06/2026
Steel Concrete
FiledStatusContractorScope
08/06/2026——Steel, Concrete
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
08/17/2026Fire-Resistant Penetrations and Joints—special
08/17/2026Mechanical Systems—special
08/17/2026Final—progress
08/17/2026Maintenance information—energy_progress
08/17/2026Shutoff dampers—energy_progress
08/17/2026HVAC-R and service water piping design and insulation—energy_progress
08/17/2026HVAC-R and service water heating system controls—energy_progress
08/17/2026HVAC-R and service water heating equipment—energy_progress
08/11/2026Fire-Resistant Penetrations and Joints—special
08/11/2026Mechanical Systems—special
08/11/2026Final—progress
08/11/2026Maintenance information—energy_progress
08/11/2026HVAC-R and service water heating equipment—energy_progress
08/11/2026HVAC-R and service water piping design and insulation—energy_progress
08/11/2026Shutoff dampers—energy_progress
08/11/2026HVAC-R and service water heating system controls—energy_progress
08/07/2026FinalIBRAHIM MOURADprogress
08/07/2026Post-installed AnchorsIBRAHIM MOURADspecial
08/07/2026Structural Steel - DetailsIBRAHIM MOURADspecial
08/07/2026Concrete - Cast-In-PlaceIBRAHIM MOURADspecial
08/03/2026FinalIBRAHIM MOURADprogress
08/03/2026Structural Steel - DetailsIBRAHIM MOURADspecial
08/03/2026Post-installed AnchorsIBRAHIM MOURADspecial
08/03/2026Concrete - Cast-In-PlaceIBRAHIM MOURADspecial
05/02/2022Concrete - Cast-In-Place—special
Latest 25 of 32.
▾Documents — 136 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/25/2026X00514816-P1Request digital key ↗
08/25/2026X00514816-P6Request digital key ↗
08/25/2026X00514816-P7Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits19
▸BISPLAN / WORK APPROVAL APPLICATION11
11/16/2023240356048Open ↗
03/29/2017220471969Open ↗
12/06/2016240118154Open ↗
Showing 3 of 11 on file for this type
▸BISWORK PERMIT APPLICATION6
11/17/2023240356048Open ↗
11/07/2016240118154Open ↗
03/07/2016220471969Open ↗
Showing 3 of 6 on file for this type
▸BISPLACE OF ASSEMBLY1
12/11/2018220680939Open ↗
▸BISAFTER-HOUR WORK PERMIT APPLICATION1
04/19/2016220471969Open ↗
▸Seals & Professional Certifications45
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION12
09/17/2021220680939Open ↗
12/11/2018220680939Open ↗
02/09/2017240118163Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/25/2026X00514816-I1Open ↗
08/25/2026X00514816-P1Open ↗
08/25/2026X00514816-P6Open ↗
Showing 3 of 12 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT6
12/06/2016240118154Open ↗
12/06/2016240118163Open ↗
03/06/2016240133930Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
11/16/2023240356048Open ↗
03/06/2016240133930Open ↗
11/01/2015240118163Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
03/06/2016240133930Open ↗
11/01/2015240118163Open ↗
11/01/2015240118154Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
12/06/2016240118154Open ↗
12/06/2016240118163Open ↗
09/09/2015220471969Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/28/2026X00514816-P7Open ↗
08/24/2026X00514816-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026X00514816-P7Open ↗
08/24/2026X00514816-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
11/16/2023240356048Open ↗
▸Safety & Tenant Protection1
▸BISTPP1: TENANT PROTECTION PLAN1
11/17/2023240356048Open ↗
▸Environmental & Asbestos4
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
02/07/2017220471969Open ↗
03/07/2016220471969Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/16/2023240356048Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
02/07/2017220471969Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
02/07/2017220471969Open ↗
02/03/2016220471969Open ↗
09/09/2015220471969Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
11/16/2023240356048Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/07/2017220471969Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
11/01/2015240118154Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
11/16/2023240356048Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY6
11/16/2023240356048Open ↗
09/07/2021220680939Open ↗
08/16/2021220680939Open ↗
Showing 3 of 6 on file for this type
▸Approvals, Objections & Sign-offs30
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter12
08/25/2026X00514816-P7Open ↗
08/25/2026X00508048-P1Open ↗
08/25/2026X00508048-I1Open ↗
Showing 3 of 12 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
04/04/2017220471969Open ↗
03/07/2017220471969Open ↗
02/27/2017220471969Open ↗
Showing 3 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
09/16/2021220680939Open ↗
09/16/2021220680939Open ↗
09/16/2021220680939Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
08/25/2026X00508048-P4Open ↗
08/13/2026X00508048-P1Open ↗
08/13/2026X00508048-P3Open ↗
Showing 3 of 5 on file for this type
▸BISFLAME SPREAD/FIRE LETTER1
09/16/2021220680939Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
11/16/2023240356048Open ↗
02/07/2017220471969Open ↗
09/09/2015220471969Open ↗
▸Filing & Intake Forms9
▸BISADDITIONAL INFORMATION4
11/16/2023240356048Open ↗
02/06/2017220471969Open ↗
11/23/2015220471969Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
11/16/2023240356048Open ↗
03/06/2016240133930Open ↗
11/01/2015240118163Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET1
09/09/2015220471969Open ↗