| Owner | Filings | Most Recent |
|---|---|---|
| LARGAVISTA COMPANIES | 32 | 07/08/2026 |
| LINCO USA INC. | 5 | 03/22/2026 |
| LARGAVISTA 41ST HOLDINGS, LLC | 12 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| FOGARTY FINGER ARCHITECTURE PLLC | 2 | 12/03/2024 |
| MG ENGINEERING D.P.C. | 6 | 11/21/2024 |
| MW PROFESSIONAL ENGINEERING, P.C. | 1 | 08/22/2022 |
| GILSANZ MURRAY STEFICEK LLP | 2 | 05/04/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| METROPOLIS GROUP INC | 20 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LINCO USA INC | General Contractor | 37 | 07/08/2026 |
| CROSSFIELD PLBG.&HTG | Plumbing | 2 | 07/08/2026 |
| SALAZAR, PEDRO | Electrical | 1 | 03/21/2026 |
| SUGARMAN, IRA | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PSI AGENCY INC. | 254 | 10 | 12/03/2024 |
| GILSANZ MURRAY STEFICEK | 240 | 1 | 04/07/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | LINCO USA INC | 02/10/2025 |
| DOB NOW | General Construction | Permit Issued | LINCO USA INC | 02/07/2025 |
| DOB NOW | Structural | Permit Issued | LINCO USA INC | 02/04/2025 |
| DOB NOW | Foundation | Permit Issued | LINCO USA INC | 02/04/2025 |
| DOB NOW | Plumbing | Permit Issued | CROSSFIELD PLBG.&HTG | 10/23/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | LINCO USA INC | 04/19/2024 |
| DOB NOW | Foundation | Permit Issued | LINCO USA INC | 04/18/2024 |
| DOB NOW | General Construction | Permit Issued | LINCO USA INC | 04/18/2024 |
| DOB NOW | Structural | Permit Issued | LINCO USA INC | 04/18/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | LINCO USA INC | 05/12/2023 |
| DOB NOW | General Construction | Permit Issued | LINCO USA INC | 05/11/2023 |
| DOB NOW | Foundation | Permit Issued | LINCO USA INC | 05/11/2023 |
| DOB NOW | Structural | Permit Issued | LINCO USA INC | 05/11/2023 |
| DOB NOW | Plumbing | Permit Issued | CROSSFIELD PLBG.&HTG | 03/01/2023 |
| DOB NOW | Construction Fence | Permit Issued | LINCO USA INC | 08/29/2022 |
| DOB NOW | Structural | Permit Issued | LINCO USA INC | 05/24/2022 |
| DOB NOW | General Construction | Permit Issued | LINCO USA INC | 05/24/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | LINCO USA INC | 05/24/2022 |
| DOB NOW | Foundation | Permit Issued | LINCO USA INC | 05/24/2022 |
| DOB NOW | General Construction | Permit Issued | LINCO USA INC | 10/06/2021 |
| DOB NOW | Foundation | Permit Issued | LINCO USA INC | 10/06/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | LINCO USA INC | 10/04/2021 |
| BIS | — | ISSUED | LINCO USA INC | 05/24/2024 |
| BIS | — | ISSUED | LINCO USA INC | 07/27/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/21/2024 | Permit Issued | LINCO USA INC | Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/20/2024 | — | — | 98 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/20/2024 | Permit Issued | CROSSFIELD PLBG.&HTG | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2024 | Permit Issued | LINCO USA INC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/22/2022 | Permit Issued | LINCO USA INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/05/2024 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 12/05/2024 | Mechanical Systems | MAURICIO ANDRADE | special |
| 12/05/2024 | Post-installed Anchors | Ramon Gilsanz | special |
| 12/05/2024 | Energy Code Compliance Inspections | MAURICIO ANDRADE | progress |
| 12/05/2024 | Final | MAURICIO ANDRADE | progress |
| 12/05/2024 | Permanent certificate | MAURICIO ANDRADE | energy_progress |
| 12/05/2024 | Shutoff dampers | MAURICIO ANDRADE | energy_progress |
| 12/05/2024 | HVAC insulation and sealing | MAURICIO ANDRADE | energy_progress |
| 12/05/2024 | Maintenance information | MAURICIO ANDRADE | energy_progress |
| 12/05/2024 | HVAC and service water heating equipment | MAURICIO ANDRADE | energy_progress |
| 12/05/2024 | HVAC and service water heating system controls | MAURICIO ANDRADE | energy_progress |
| 12/05/2024 | Duct leakage testing | MAURICIO ANDRADE | energy_progress |
| 12/02/2024 | Sprinkler Systems | MAURICIO ANDRADE | special |
| 12/02/2024 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 12/02/2024 | Post-installed Anchors | Ramon Gilsanz | special |
| 11/21/2024 | Subgrade Inspections | — | special |
| 11/21/2024 | Sprayed fire-resistant materials | — | special |
| 11/21/2024 | Exterior lighting power | — | energy_progress |
| 11/21/2024 | Concrete - Cast-In-Place | — | special |
| 11/08/2024 | Final | MAURICIO ANDRADE | progress |
| 11/08/2024 | Fire-Resistance Rated Construction | MAURICIO ANDRADE | progress |
| 11/08/2024 | Air barrier - visual inspection | MAURICIO ANDRADE | energy_progress |
| 11/08/2024 | Metering | MAURICIO ANDRADE | energy_progress |
| 11/08/2024 | Fenestration air leakage | MAURICIO ANDRADE | energy_progress |
| 11/08/2024 | Masonry | MAURICIO ANDRADE | special |