← Back
Elevator cooperative
30 EAST 72 STREET
MANHATTAN · Upper East Side-Carnegie Hill · BIN 1041368
💬 Discuss this project
1926Year Built
16Stories
D4Building Class
C5-1Zoning
64,874 sfGross Floor Area
24Units
LL97 CoveredRent Stabilized3 Open Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: 72ND ST OWNERSS INC · 5,491 sf lot · 11.81 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingGeneralOther
Floor 1411p · 2 filings · 10 docs
Floor 13
Floor 12
Floor 11
Floor 1038p · 2 filings · 20 docs
Floor 924p · 2 filings · 20 docs
Floor 8
Floor 7
Floor 69p · 3 filings · 20 docs
Floor 55p · 2 filings · 10 docs
Floor 4
Floor 325p · 3 filings · 20 docs
Floor 24p · 1 filing · 3 docs
Floor 14p · 2 filings · 20 docs
Site & exterior23p · 4 filings · 18 docs
Filed — no permit issued9p · 1 filing · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
72ND STREET OWNERS PH6203/22/2026
WALLACK MANAGEMENT903/21/2026
30 EAST 72ND STREET OWNERS803/21/2026
STEEL SYSTEMS LLC503/22/2026
30 E 72 ST OWNERS403/21/2026
BROWN HARRIS STEVENS403/21/2026
50 RIVERSIDE DRIVE TENANTS203/21/2026
T-MOBILE103/21/2026
72 STREET OWNERS103/21/2026
36 EAST 72ND STREET103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JESTCOR CONTRACTING INCGeneral Contractor907/08/2026
SCHNELLBACHER-SENDON GRO*General Contractor403/21/2026
JOHN HUMMEL CUSTOM BLD INGeneral Contractor407/08/2026
CREO PROJECTS LLCGeneral Contractor303/21/2026
EH PLUMBING & HEATING CORPlumbing307/08/2026
PREMIER FLOW PLBG AND HTGPlumbing307/08/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor303/21/2026
STEEL SYSTEMS LLCGeneral Contractor303/21/2026
WCM GROUP USA LLCGeneral Contractor303/21/2026
UNIPIPE PLBG&HTG CORPPlumbing207/08/2026
ABR PLBG&HTG CONTR INCPlumbing207/08/2026
K & K RENOVATION INCGeneral Contractor107/08/2026
FALCO ELEC'L SERVICES INCElectrical103/22/2026
MACKENZIE, DOUGLASElectrical103/21/2026
POWER SURGE ELECTRIC, INCElectrical103/22/2026
RODRIGUEZ, GIANFRANCOElectrical103/21/2026
ADVANCED SCAFFOLD SER.LLCGeneral Contractor104/09/2026
EINSTEIN ELEC'L CORPElectrical103/22/2026
BENT MECHANICAL CORPPlumbing107/08/2026
PROCORE MECHANICAL CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SONI ENGINEERING CONSULTI9819101/08/2026
SETH P ROYE ARCHITECT PC8554112/11/2024
SAG ENGINEERING & CONSULT608112/11/2024
SCHERER DESIGN GROUP7921211/25/2024
CHEN ENGINEERING SERVICES1826611/14/2024
JMV CONSULTING ENGINEERIN804210/30/2024
LEO Y LEE ASSOCIATES2481110/08/2024
O'ROURKE ENGINEERING, LLC5873302/15/2023
OUTSOURCE SPECIAL INSPECT2827402/03/2023
ARCT ARCHITECTURE, P.C.3329512/02/2022
Building Lifecycle
All (236)Filed (36)Permit Issued (32)Signed Off (18)Facade (FISP) (12)Violation (44)Inspection (16)Objection (48)Special Inspection (30)
04/21/2026
Filed — Alteration
INSTALLATION OF SIDEWALK SHED IN ACCORDANCE WITH NYCC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
M01163328-P1
01/21/2026
Permit issued — Suspended Scaffold
M01343936-I1-SC
01/08/2026
Filed — Alteration
M01343936-I1
11/13/2025
Signed off — Alteration
Plumbing work for Apt 9ab. No change to occupancy use or egress under this application.
M01082258-I1
05/28/2025
Signed off — Alteration
M01140318-I1
05/22/2025
Permit issued — General Construction
M01089922-I1-GC
05/13/2025
Signed off — Alteration
INSTALLATION OF SIDEWALK SHED AS PER PLANS.
M00038608-I1
04/30/2025
Signed off — Alteration
Renovation of kitchen in apt 9AB. Demolition of maid bathroom. Plumbing filed under separate application. No change in occupancy use or egress under this application.
M01064437-I1
04/02/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
04/02/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/20/2025
Permit issued — General Construction
M01089922-I1-GC
01/27/2025
Permit issued — Suspended Scaffold
M01140318-I1-SC
01/15/2025
Permit issued — Sidewalk Shed
M01163328-I1-SH
01/14/2025
Filed — Alteration
INSTALLATION OF SIDEWALK SHED IN ACCORDANCE WITH NYCC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
M01163328-I1
12/26/2024
Objection resolved — Addressed
12/11/2024
Filed — Alteration
Facade repairs as per plans. No change to use, egress, or occupancy.
M01089922-I1
12/02/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/26/2024
Special inspection requirement — Fire-Resistance Rated Construction
John Wettling
11/26/2024
Special inspection requirement — Lighting in dwelling units
John Wettling
11/26/2024
Special inspection requirement — Final
John Wettling
11/25/2024
Filed — Alteration
Replace 2 air handlers in existing equipment room in basement. Replace related condensers on the roof. No change in use, egress, or occupancy.
M01040236-S1
11/22/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENLIA CHEN
11/14/2024
Filed — Alteration
Renovation of kitchen in apt 9AB. Demolition of maid bathroom. Plumbing filed under separate application. No change in occupancy use or egress under this application.
M01064437-P2
11/14/2024
Filed — Alteration
Plumbing work for Apt 9ab. No change to occupancy use or egress under this application.
M01082258-P1
11/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENLIA CHEN
11/14/2024
Special inspection requirement — Mechanical Systems
Joseph Vuto
11/14/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Joseph Vuto
11/14/2024
Special inspection requirement — HVAC-R and service water heating equipment
Joseph Vuto
11/14/2024
Special inspection requirement — Final
Joseph Vuto
11/14/2024
Special inspection requirement — Maintenance information
Joseph Vuto
11/14/2024
Special inspection requirement — Energy Code Compliance Inspections
Joseph Vuto
11/14/2024
Special inspection requirement — HVAC-R and service water heating system controls
Joseph Vuto
11/12/2024
Special inspection requirement — Fire-Resistance Rated Construction
John Wettling
11/12/2024
Special inspection requirement — Lighting in dwelling units
John Wettling
11/12/2024
Special inspection requirement — Final
John Wettling
11/11/2024
Filed — Alteration
M01140318-I1
11/11/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENLIA CHEN
10/31/2024
Special inspection requirement — Energy Code Compliance Inspections
Seth Roye
10/31/2024
Special inspection requirement — Tenant Protection Plan Compliance
Chester Kowalski
10/31/2024
Special inspection requirement — Masonry
Seth Roye
10/31/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Seth Roye
10/30/2024
Filed — Alteration
Install 4 a/c units interior. Filed in conjunction with Architectural m00851678. No change to occupancy use or egress under this application.
M00863055-P1
10/21/2024
Permit issued — Suspended Scaffold
M01117808-I1-SC
10/21/2024
Objection raised — Other
10/21/2024
Objection resolved — Addressed
10/18/2024
Objection raised — Other
10/18/2024
Objection resolved — Addressed
10/08/2024
Filed — Alteration
Installation of suspended scaffold for facade work
M01117808-I1
09/30/2024
Special inspection requirement — Final
Seth Roye
09/26/2024
Special inspection requirement — Final
Joseph Vuto
09/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENLIA CHEN
09/26/2024
Special inspection requirement — Mechanical Systems
Joseph Vuto
09/26/2024
Special inspection requirement — Energy Code Compliance Inspections
Joseph Vuto
09/26/2024
Special inspection requirement — HVAC-R and service water heating equipment
Joseph Vuto
09/26/2024
Special inspection requirement — Maintenance information
Joseph Vuto
09/26/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Joseph Vuto
09/26/2024
Special inspection requirement — HVAC-R and service water heating system controls
Joseph Vuto
09/26/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Leo Lee
09/24/2024
Filed — Alteration
Renovation of kitchen in apt 9AB. Demolition of maid bathroom. Plumbing filed under separate application. No change in occupancy use or egress under this application.
M01064437-P1
08/19/2024
Objection resolved — Addressed
Latest 60 of 236 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSCHNELLBACHER-SENDON GROU01/21/2026
DOB NOWGeneral ConstructionPermit IssuedSCHNELLBACHER-SENDON GRO*05/22/2025
DOB NOWGeneral ConstructionPermit IssuedSCHNELLBACHER-SENDON GRO*03/20/2025
DOB NOWSuspended ScaffoldSigned-offB & H RESTORATION, INC01/27/2025
DOB NOWSidewalk ShedPermit IssuedADVANCED SCAFFOLD SER.LLC01/15/2025
DOB NOWSuspended ScaffoldPermit IssuedSCHNELLBACHER-SENDON GROU10/21/2024
DOB NOWPlumbingSigned-offBENT MECHANICAL CORP08/15/2024
DOB NOWGeneral ConstructionSigned-offK K RENOVATION08/14/2024
DOB NOWSuspended ScaffoldPermit IssuedPPM TELECOM LLC12/12/2023
DOB NOWPlumbingSigned-offABR PLBG&HTG CONTR INC11/06/2023
DOB NOWMechanical SystemsPermit IssuedJOHN HUMMEL CUSTOM BLD IN07/21/2023
DOB NOWPlumbingSigned-offABR PLBG&HTG CONTR INC06/26/2023
DOB NOWMechanical SystemsSigned-offJESTCOR CONTRACTING05/24/2023
DOB NOWGeneral ConstructionSigned-offJOHN HUMMEL CUSTOM BLD IN05/09/2023
DOB NOWGeneral ConstructionSigned-offJOHN HUMMEL CUSTOM BLD IN04/27/2023
DOB NOWGeneral ConstructionSigned-offJESTCOR CONTRACTING02/15/2023
DOB NOWStructuralSigned-offJESTCOR CONTRACTING02/07/2023
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC02/02/2023
DOB NOWGeneral ConstructionSigned-offJESTCOR CONTRACTING02/02/2023
DOB NOWPlumbingSigned-offEH PLUMBING & HEATING COR12/22/2022
DOB NOWPlumbingSigned-offPROCORE MECHANICAL CORP11/21/2022
DOB NOWGeneral ConstructionSigned-offCREO PROJECTS LLC11/20/2022
DOB NOWMechanical SystemsSigned-offWCM GROUP USA LLC10/21/2021
DOB NOWPlumbingSigned-offEH PLUMBING & HEATING COR09/14/2021
DOB NOWPlumbingSigned-offUNIPIPE PLBG&HTG CORP07/22/2021
DOB NOWPlumbingSigned-offEH PLUMBING & HEATING COR04/28/2021
DOB NOWGeneral ConstructionSigned-offJESTCOR CONTRACTING04/26/2021
DOB NOWPlumbingSigned-offUNIPIPE PLBG&HTG CORP11/19/2020
DOB NOWPlumbingSigned-offGALICJA PLBG AND HTG.CORP06/16/2020
DOB NOWPlumbingSigned-offGALICJA PLBG AND HTG.CORP12/12/2019
DOB NOWPlumbingSigned-offGALICJA PLBG AND HTG.CORP10/25/2019
DOB NOWSidewalk ShedSigned-offSTEEL SYSTEMS LLC05/01/2018
BISOTISSUEDWCM GROUP USA LLC09/03/2020
BISOTISSUEDKLDNY INC10/01/2019
BISOTISSUEDDT CABINETS & INTERIOR RE01/24/2019
BISPLISSUEDFERKO PLUMBING & HEATING07/25/2018
BISOTISSUEDGALICIA CONTRACTING & REST.07/20/2018
BISOTISSUEDDT CABINETS & INTERIOR RE07/11/2018
BISOTISSUEDGALICIA CONTRACTING & REST.05/22/2018
BISOTISSUEDTHE RENOVATED HOME 1 LTD12/28/2017
+ 42 more permits on file
2 projects · most recent 11/25/2024
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
11/25/2024——Air Conditioning Systems—
10/30/2024Permit IssuedJOHN HUMMEL CUSTOM BLD INAir Conditioning Systems
Cooling
National Comfort National Comfort NCPE-430-4010/D 30,000 BTU · Condensing Unit ×4
National Comfort NCPE-418-4010/D 1,800 BTU ×2
National Comfort NCPE-424-4010/D 24,000 BTU · Condensing Unit ×2
15 projects · most recent 06/26/2026
General Wiring
FiledStatusContractorScope
06/26/2026Permit IssuedWMS ELECTRICAL CONTNG LTDGeneral Wiring
04/29/2025CompleteGAUGE TECH ELECTRIC INCGeneral Wiring
01/18/2024CompletePOWER SURGE ELECTRIC, INCGeneral Wiring
05/03/2023Permit IssuedEINSTEIN ELEC'L CORP—
05/03/2023Permit IssuedEINSTEIN ELEC'L CORPGeneral Wiring
02/02/2023CompleteBOROWIDE ELECT'L CONTR'S—
12/28/2022CompleteSTELLMANN ELECTRICAL CORPGeneral Wiring
03/27/2022CompleteFALCO ELEC'L SERVICES INCGeneral Wiring
09/16/2021CompleteSTELLMANN ELECTRICAL CORPGeneral Wiring
09/26/2020Permit IssuedTM SELECT ELECTRIC CORPGeneral Wiring
05/18/2019CompleteA.C. MORGAN ELECTRIC—
10/01/2018CompleteS.A.L. ELECTRIC CO INC.—
08/02/2018CompleteA.C. MORGAN ELECTRICGeneral Wiring
04/12/2018Permit IssuedTOP SHELF ELECTRIC CORP—
03/07/2018CompleteALEF ELEC'L CONTR'G INCGeneral Wiring
1 project · most recent 04/21/2026
Sidewalk Shed
FiledStatusContractorScope
04/21/2026Permit IssuedADVANCED SCAFFOLD SER.LLCSidewalk Shed
2 projects · most recent 10/08/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
10/08/2024Permit Issued—Suspended Scaffold (SC)
11/28/2023Permit Issued——
▾Field Inspections (DOB CAP) — 16
DateTypeResultReport
04/02/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/02/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/02/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/15/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/09/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/08/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/16/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/19/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/19/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/12/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/12/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/20/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/14/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/04/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/23/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 51
DateRequirementInspectorRole
11/26/2024Fire-Resistance Rated ConstructionJohn Wettlingprogress
11/26/2024Lighting in dwelling unitsJohn Wettlingenergy_progress
11/26/2024FinalJohn Wettlingprogress
11/22/2024Fire-Resistant Penetrations and JointsHENLIA CHENspecial
11/14/2024Fire-Resistant Penetrations and JointsHENLIA CHENspecial
11/14/2024Mechanical SystemsJoseph Vutospecial
11/14/2024HVAC-R and service water piping design and insulationJoseph Vutoenergy_progress
11/14/2024HVAC-R and service water heating equipmentJoseph Vutoenergy_progress
11/14/2024FinalJoseph Vutoprogress
11/14/2024Maintenance informationJoseph Vutoenergy_progress
11/14/2024Energy Code Compliance InspectionsJoseph Vutoprogress
11/14/2024HVAC-R and service water heating system controlsJoseph Vutoenergy_progress
11/12/2024Fire-Resistance Rated ConstructionJohn Wettlingprogress
11/12/2024Lighting in dwelling unitsJohn Wettlingenergy_progress
11/12/2024FinalJohn Wettlingprogress
11/11/2024Fire-Resistant Penetrations and JointsHENLIA CHENspecial
10/31/2024Energy Code Compliance InspectionsSeth Royeprogress
10/31/2024Tenant Protection Plan ComplianceChester Kowalskispecial
10/31/2024MasonrySeth Royespecial
10/31/2024Fire-Resistant Penetrations and JointsSeth Royespecial
09/30/2024FinalSeth Royeprogress
09/26/2024FinalJoseph Vutoprogress
09/26/2024Fire-Resistant Penetrations and JointsHENLIA CHENspecial
09/26/2024Mechanical SystemsJoseph Vutospecial
09/26/2024Energy Code Compliance InspectionsJoseph Vutoprogress
Latest 25 of 51.
▾Documents — 633 on file (BIS + DOB NOW)
▸Plans & Drawings37
▸DOB NOWPlans/Sketch34
09/06/2026M00038608-I1Request digital key ↗
09/03/2026M00494532-I1Request digital key ↗
09/03/2026M00494503-I1Request digital key ↗
Showing 3 of 34 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
09/04/2026M00303478-I1Request digital key ↗
08/14/2026M00223158-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00304223-I1Request digital key ↗
▸Applications & Permits128
▸BISWORK PERMIT APPLICATION53
09/03/2020123791646Open ↗
10/02/2019123815620Open ↗
01/24/2019123550246Open ↗
Showing 3 of 53 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION47
04/13/2020123791646Open ↗
02/24/2020123791646Open ↗
02/24/2020123791646Open ↗
Showing 3 of 47 on file for this type
▸DOB NOWLPC Approval/Permit28
09/04/2026M00304223-I1Open ↗
08/31/2026M08017390-I1Open ↗
08/25/2026M00863055-I1Open ↗
Showing 3 of 28 on file for this type
▸Seals & Professional Certifications155
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION69
09/02/2020123791646Open ↗
09/02/2020123791646Open ↗
09/02/2020123791646Open ↗
Showing 3 of 69 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature32
09/05/2026M00223158-I1Open ↗
09/04/2026M00304223-I1Open ↗
09/01/2026M08039563-I1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWProgress Inspector Seal & Signature30
09/05/2026M01089922-I1Open ↗
09/05/2026M01089922-I1Open ↗
09/02/2026M01064437-P1Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/05/2026M01089922-I1Open ↗
09/05/2026M01089922-I1Open ↗
09/05/2026M01089922-I1Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
03/23/2018123410175Open ↗
Showing 1 of 2 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
03/23/2018123410175Open ↗
▸Trade Schedules & Equipment38
▸BISSELF-CERT PLUMBING NOTICE15
02/23/2015121987458Open ↗
Showing 1 of 15 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE9
05/03/2019123550246Open ↗
06/19/2018123550246Open ↗
03/26/2018123013808Open ↗
Showing 3 of 9 on file for this type
▸BISSCHEDULE B - PLUMBING9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION2
09/07/2021123791646Open ↗
04/17/2018122743399Open ↗
▸BISBOILERS - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
09/07/2021123791646Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection8
▸BISTenant Protection Plan and Notes6
02/12/2020123791646Open ↗
09/06/2019123815620Open ↗
06/29/2018123550246Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWTenant Protection Plan2
09/04/2026M00304223-I1Open ↗
08/13/2026M00303478-I1Open ↗
▸Environmental & Asbestos55
▸DOB NOWDEP ACP-5: Asbestos Assessment Report27
09/04/2026M00304223-I1Open ↗
09/01/2026M08039563-S1Open ↗
09/01/2026M08039563-I1Open ↗
Showing 3 of 27 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)17
02/12/2020123791646Open ↗
09/06/2019123815620Open ↗
06/19/2018123550246Open ↗
Showing 3 of 17 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸Energy Compliance34
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS16
07/11/2019123550246Open ↗
12/05/2018123410175Open ↗
10/24/2018123013808Open ↗
Showing 3 of 16 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
12/05/2018123410175Open ↗
10/24/2018123013808Open ↗
04/30/2018121810059Open ↗
Showing 3 of 8 on file for this type
▸BISTR8: Energy Code Progress Inspections6
02/11/2015121987458Open ↗
Showing 1 of 6 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00494532-I1Open ↗
08/13/2026M00494503-I1Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISENERGY CODE 1ST REVIEW COMPLETE1
09/06/2019123815620Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
09/03/2021123791646Open ↗
07/19/2020123791646Open ↗
07/19/2020123791646Open ↗
Showing 3 of 4 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
09/07/2021123791646Open ↗
▸Approvals, Objections & Sign-offs61
▸BISLANDMARKS APPROVAL20
05/22/2020123791646Open ↗
01/28/2020123815620Open ↗
12/05/2018123410175Open ↗
Showing 3 of 20 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST17
09/07/2021123791646Open ↗
01/28/2020123815620Open ↗
07/11/2019123550246Open ↗
Showing 3 of 17 on file for this type
▸BISADMINISTRATIVE OBJECTIONS13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
01/28/2020123815620Open ↗
Showing 1 of 5 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISLANDMARKS SIGNOFF2
09/07/2021123791646Open ↗
10/24/2018123013808Open ↗
▸BISFINAL1
09/07/2021123791646Open ↗
▸Cost, Insurance & Ownership42
▸BISCOST AFFIDAVIT40
02/12/2020123791646Open ↗
02/12/2020123791646Open ↗
01/28/2020123815620Open ↗
Showing 3 of 40 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT1
06/14/2017123013808Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
09/07/2021123791646Open ↗
▸Filing & Intake Forms52
▸BISADDITIONAL INFORMATION22
09/03/2021123791646Open ↗
02/12/2020123791646Open ↗
09/06/2019123815620Open ↗
Showing 3 of 22 on file for this type
▸BISEFILING COVER SHEET17
02/12/2020123791646Open ↗
02/12/2020123791646Open ↗
09/06/2019123815620Open ↗
Showing 3 of 17 on file for this type
▸BISBOROUGH INTAKE FORM12
04/13/2020123791646Open ↗
01/28/2020123815620Open ↗
07/11/2019123550246Open ↗
Showing 3 of 12 on file for this type
▸BISeFiling Job Application Cover Sheet1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Other Documents18
▸DOB NOWProof of Historic Building6
08/13/2026M08017385-I1Open ↗
08/13/2026M08017385-P1Open ↗
08/13/2026M08017385-P2Open ↗
Showing 3 of 6 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form4
07/11/2018123550246Open ↗
01/02/2018123013808Open ↗
01/02/2018123013808Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWManufacturer's Specifications3
08/13/2026M01140318-I1Open ↗
08/13/2026M01117808-I1Open ↗
08/13/2026M01343936-I1Open ↗
▸DOB NOWCalculations3
08/13/2026M01117808-I1Open ↗
08/13/2026M01140318-I1Open ↗
08/13/2026M01343936-I1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
06/15/2016122743399Open ↗
▸DOB NOWIRA Certification1
08/13/2026M00963759-I1Open ↗