| Owner | Filings | Most Recent |
|---|---|---|
| HKS CONSTRUCTION | 3 | 03/21/2026 |
| BKYN PROSPECT CHARTER SCHOOL | 3 | 03/21/2026 |
| IMMACULATE HEART MARY RC CHURCH | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KIEFER & SCHUSTER ENGINEERING PLLC | 3 | 09/14/2026 |
| LOCI ARCHITECTURE PLLC | 4 | 08/11/2026 |
| FNA ENGINEERING SERVICES PC | 3 | 05/28/2026 |
| DERIVE ENGINEERS | 2 | 03/29/2026 |
| THOMAS BARRY ARCHITECT | 1 | 08/26/2019 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WESBUILT CONSTRUCTION MAN | General Contractor | 6 | 09/15/2026 |
| ROOPCHAND SINGH | Electrical | 1 | 03/21/2026 |
| TORRES IVAN | Electrical | 1 | 03/21/2026 |
| SP PLUMBING AND HEATING | Plumbing | 1 | 07/08/2026 |
| ZEREGA CONTRACTING CORP | Plumbing | 1 | 07/16/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SPECIAL TESTING & CONSULT | 1688 | 5 | 08/11/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | WESBUILT CONSTRUCTION MAN | 09/14/2026 |
| DOB NOW | Earth Work | Permit Issued | WESBUILT CONSTRUCTION MAN | 09/10/2026 |
| DOB NOW | General Construction | Permit Issued | WESBUILT CONSTRUCTION MAN | 09/10/2026 |
| DOB NOW | Plumbing | Permit Issued | ZEREGA CONTRACTING CORP | 07/15/2026 |
| DOB NOW | Structural | Permit Issued | WESBUILT CONSTRUCTION MAN | 07/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | WESBUILT CONSTRUCTION MAN | 07/09/2026 |
| DOB NOW | General Construction | Permit Issued | WESBUILT CONSTRUCTION MAN | 07/08/2026 |
| DOB NOW | Plumbing | Signed-off | JORGE ESPEJO | 09/10/2019 |
| BIS | EQ | ISSUED | HKS CONSTRUCTION CORP | 07/08/2016 |
| BIS | OT | ISSUED | RAIN GUARD CONSTRUCTION C | 06/29/2016 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 06/10/2015 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 08/01/2014 |
| BIS | MH | ISSUED | TALISEN CONSTRUCTION CORP | 08/01/2014 |
| BIS | — | ISSUED | TALISEN CONSTRUCTION CORP | 08/01/2014 |
| BIS | — | ISSUED | TALISEN CONSTRUCTION CORP | 07/08/2014 |
| BIS | PL | ISSUED | WILLIAM C. GERAKARIS P&H | 06/25/2014 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 06/17/2014 |
| BIS | MH | ISSUED | TALISEN CONSTRUCTION CORP | 06/17/2014 |
| BIS | PL | ISSUED | MAC FELDER INC | 07/02/2013 |
| BIS | PL | ISSUED | MAC FELDER INC | 07/02/2013 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 06/27/2013 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 06/27/2013 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 06/27/2013 |
| BIS | — | ISSUED | GOING SIGN & SVCNG CO,INC | 08/10/2012 |
| BIS | PL | ISSUED | DUMONT PLBG & HTG CORP | 07/12/2012 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 07/11/2012 |
| BIS | MH | ISSUED | TALISEN CONSTRUCTION CORP | 07/11/2012 |
| BIS | OT | ISSUED | NICHOLSON & GALLOWAY, INC. | 09/11/2002 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/11/2026 | Permit Issued | WESBUILT CONSTRUCTION MAN | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric TUHYE1683AMM0AN 168,000 BTU · Vrf Outdoor ×2 MXZ-SM60NAM2 60,000 BTU · Vrf Outdoor ×1 TUHYE1443AMM0AN 144,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/11/2026 | Permit Issued | ZEREGA CONTRACTING CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2026 | Permit Issued | CLOONAGH ELECTRICAL CORP | General Wiring |
| 09/05/2019 | Permit Issued | SWITCH ELECT OF THE FIVE | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/14/2026 | Permit Issued | WESBUILT CONSTRUCTION MAN | 3 scope_items |
| 08/11/2026 | Permit Issued | ZEREGA CONTRACTING CORP | Steel, Concrete |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/10/2026 | Final | SEBASTIAN SETTEDUCATE JR., P.E | progress |
| 09/10/2026 | Footing and Foundation | SEBASTIAN SETTEDUCATE JR., P.E | progress |
| 08/10/2026 | Fire-Resistant Penetrations and Joints | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 08/10/2026 | Exterior Insulation and Finish Systems (EIFS) | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 08/10/2026 | Fenestration and door U-factor and product ratings | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 08/10/2026 | Fenestration air leakage | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 08/10/2026 | Air barrier - visual inspection | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 08/10/2026 | Insulation placement and R values | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 08/10/2026 | Fire-Resistance Rated Construction | SEBASTIAN SETTEDUCATE JR., P.E | progress |
| 08/10/2026 | Final | SEBASTIAN SETTEDUCATE JR., P.E | progress |
| 08/10/2026 | Energy Code Compliance Inspections | SEBASTIAN SETTEDUCATE JR., P.E | progress |
| 05/18/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 04/16/2026 | Final | — | progress |
| 04/08/2026 | Concrete - Cast-In-Place | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 04/08/2026 | Final | SEBASTIAN SETTEDUCATE JR., P.E | progress |
| 04/08/2026 | Structural Steel - Welding | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 04/08/2026 | Structural Steel - Details | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 04/08/2026 | Structural Steel - High Strength Bolting | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 04/08/2026 | Structural Stability – Alterations of existing buildings | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 04/08/2026 | Post-installed Anchors | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 02/26/2026 | Fire-Resistant Penetrations and Joints | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 02/26/2026 | Post-installed Anchors | SEBASTIAN SETTEDUCATE JR., P.E | special |
| 02/26/2026 | HVAC-R and service water heating equipment | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 02/26/2026 | Shutoff dampers | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |
| 02/26/2026 | Maintenance information | SEBASTIAN SETTEDUCATE JR., P.E | energy_progress |