| Owner | Filings | Most Recent |
|---|---|---|
| HAOR BEACON SCHOOL | 63 | 09/13/2026 |
| CONSOLIDATED SCAFFOLDING INC. | 10 | 06/28/2026 |
| SENTRY ELEVATOR CORP | 1 | 03/22/2026 |
| 30-32 NOSTRAND REALTY LLC | 1 | 03/22/2026 |
| DELTA ELEVATOR INSP CORP | 1 | 03/22/2026 |
| CHABAD | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/19/2024 | $6.8M | — | 3030 NOSTRAND AVENUE REALTY LLC → 3030 NOSTRAND AVE LLC | $453/sf building |
| 08/15/2022 | $6.3M | — | 30-32 NOSTRAND REALTY LLC → 3030 NOSTRAND AVENUE REALTY LLC | $423/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| EDIFICE DRAFTING AND SERVICES | 20 | 08/14/2026 |
| MOHAMMAD AHEAD, PE | 1 | 07/07/2026 |
| PAUL G. JONES, P.E. | 2 | 07/10/2025 |
| LMW ENGINEERING GROUP LLC | 5 | 02/14/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| 4444 PPPP CORP | 40 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PLATINUM COMMERCIAL CONST | General Contractor | 23 | 07/08/2026 |
| CONSOLIDATED SCAFFOLDING | General Contractor | 7 | 06/28/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 2 | 07/17/2026 |
| TARGET PIPING NY LLC | Fire Protection | 2 | 07/17/2026 |
| BENJAMIN DREBIN | Electrical | 2 | 03/21/2026 |
| SOLAR STRING INC | General Contractor | 1 | 07/17/2026 |
| WINDSTAR COOLING INC | General Contractor | 1 | 04/09/2026 |
| OHR CHODOSH ELEC'L CONT I | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STRUCTURAL ENGINEERING & | 5699 | 17 | 08/14/2026 |
| MOHAMMAD AHEAD - PROFESSI | 9286 | 1 | 07/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | SOLAR STRING INC | 07/16/2026 |
| DOB NOW | Plumbing | Permit Issued | B&B MECH PLBG & HTG LLC | 07/16/2026 |
| DOB NOW | Plumbing | Signed-off | TARGET PIPING NY LLC | 07/16/2026 |
| DOB NOW | Construction Fence | Signed-off | PLATINUM COMMERCIAL CONST | 02/25/2026 |
| DOB NOW | General Construction | Permit Issued | PLATINUM COMMERCIAL CONST | 11/06/2025 |
| DOB NOW | General Construction | Permit Issued | PLATINUM COMMERCIAL CONST | 09/04/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 07/11/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 07/11/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CONSOLIDATED SCAFFOLDING | 07/11/2025 |
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 05/27/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | WINDSTAR COOLING INC | 05/27/2025 |
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 05/27/2025 |
| DOB NOW | Curb Cut | Signed-off | PLATINUM COMMERCIAL CONST | 05/23/2025 |
| DOB NOW | Construction Fence | Signed-off | PLATINUM COMMERCIAL CONST | 03/06/2025 |
| DOB NOW | Structural | Signed-off | PLATINUM COMMERCIAL CONST | 11/19/2024 |
| DOB NOW | Earth Work | Signed-off | PLATINUM COMMERCIAL CONST | 11/19/2024 |
| DOB NOW | General Construction | Permit Issued | PLATINUM COMMERCIAL CONST | 11/13/2024 |
| DOB NOW | Support of Excavation | Signed-off | PLATINUM COMMERCIAL CONST | 11/13/2024 |
| DOB NOW | General Construction | Signed-off | PLATINUM COMMERCIAL CONST | 05/03/2024 |
| DOB NOW | Construction Fence | Signed-off | PLATINUM COMMERCIAL CONST | 05/01/2024 |
| BIS | PL | ISSUED | HEADQUARTERS MECH INC | 12/31/2007 |
| BIS | — | ISSUED | K & R CONSTRUCTION CORP. | 01/24/1996 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/14/2026 | Permit Issued | PLATINUM COMMERCIAL CONST | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Signed-off | TARGET PIPING NY LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | B&B MECH PLBG & HTG LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Permit Issued | OHR CHODOSH ELEC'L CONT I | — |
| 05/11/2026 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| 05/10/2026 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| 07/10/2025 | Complete | SOLAS ELECTRICAL CORP | — |
| 05/27/2025 | Permit Issued | OHR CHODOSH ELEC'L CONT I | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | B&B MECH PLBG & HTG LLC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | SOLAR STRING INC | 8 panels, 4.4 kw, 6,678 roof_area_sqft |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2025 | Signed-off | CONSOLIDATED SCAFFOLDING | Scaffold, Sidewalk Shed |
| 05/08/2024 | Signed-off | PLATINUM COMMERCIAL CONST | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | B&B MECH PLBG & HTG LLC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/04/2026 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 09/03/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/01/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/07/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/04/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 07/21/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 04/22/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/30/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/28/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 12/18/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 12/18/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 10/10/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 10/10/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/13/2026 | Fire-Resistant Penetrations and Joints | ROBERT SIQECA | special |
| 08/13/2026 | Maintenance information | ROBERT SIQECA | energy_progress |
| 08/13/2026 | Sprinkler Systems | ROBERT SIQECA | special |
| 08/13/2026 | Seismic Isolation Systems | ROBERT SIQECA | special |
| 08/13/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | ROBERT SIQECA | special |
| 08/13/2026 | Post-installed Anchors | ROBERT SIQECA | special |
| 08/13/2026 | HVAC-R and service water piping design and insulation | ROBERT SIQECA | energy_progress |
| 08/13/2026 | HVAC-R and service water heating equipment | ROBERT SIQECA | energy_progress |
| 08/13/2026 | HVAC-R and service water heating system controls | ROBERT SIQECA | energy_progress |
| 07/05/2026 | Public Assembly Emergency Lighting | ROBERT SIQECA | progress |
| 07/05/2026 | Public Assembly Emergency Lighting | ROBERT SIQECA | progress |
| 07/03/2026 | Fire-Resistant Penetrations and Joints | MOHAMMAD AHEAD | special |
| 07/03/2026 | Energy Code Compliance Inspections | MOHAMMAD AHEAD | progress |
| 07/03/2026 | Final | ADITYA DESAI | progress |
| 06/22/2026 | Fire-Resistance Rated Construction | ROBERT SIQECA | progress |
| 06/22/2026 | Insulation placement and R values | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Fenestration and door U-factor and product ratings | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Exterior lighting power | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Maintenance information | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Metering | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Vestibules | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Fenestration areas | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Air barrier — testing | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Fenestration air leakage | ROBERT SIQECA | energy_progress |
| 06/22/2026 | Lighting controls | ROBERT SIQECA | energy_progress |