| Firm | Filings | Most Recent |
|---|---|---|
| GCF CONSULTING ENGINEERS | 4 | 01/23/2026 |
| D'HUY ENGINEERING, INC. | 4 | 09/13/2024 |
| ERIC ANDREASEN ARCHITECT, PLLC | 3 | 04/18/2023 |
| GEO | 1 | 07/26/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| GAMILL ENGINEERING, PC | 24 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| UNITED BUILDERS GROUP LLC | General Contractor | 25 | 07/08/2026 |
| DV PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| POWER SURGE ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| GSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GFC CONSULTING ENGINEER P | 4127 | 4 | 01/23/2026 |
| MACIA INSPECTION & TESTIN | 402 | 11 | 09/13/2024 |
| ERIC ANDREASEN ARCHITECT | 4483 | 3 | 04/18/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | GSTRUCTION CORP | 06/18/2026 |
| DOB NOW | Structural | Permit Issued | UNITED BUILDERS GROUP LLC | 07/30/2025 |
| DOB NOW | General Construction | Signed-off | UNITED BUILDERS GROUP LLC | 07/25/2025 |
| DOB NOW | Foundation | Permit Issued | UNITED BUILDERS GROUP LLC | 06/24/2025 |
| DOB NOW | General Construction | Signed-off | UNITED BUILDERS GROUP LLC | 06/24/2025 |
| DOB NOW | Plumbing | Signed-off | DV PLUMBING INC | 01/21/2025 |
| DOB NOW | General Construction | Permit Issued | UNITED BUILDERS GROUP LLC | 07/29/2024 |
| DOB NOW | General Construction | Signed-off | UNITED BUILDERS GROUP LLC | 07/29/2024 |
| DOB NOW | Plumbing | Signed-off | DV PLUMBING INC | 10/17/2023 |
| DOB NOW | Structural | Permit Issued | UNITED BUILDERS GROUP LLC | 08/11/2023 |
| DOB NOW | General Construction | Signed-off | UNITED BUILDERS GROUP LLC | 08/11/2023 |
| DOB NOW | General Construction | Signed-off | UNITED BUILDERS GROUP LLC | 06/13/2023 |
| DOB NOW | General Construction | Permit Issued | UNITED BUILDERS GROUP LLC | 05/24/2023 |
| DOB NOW | General Construction | Signed-off | UNITED BUILDERS GROUP LLC | 04/29/2023 |
| BIS | PL | ISSUED | SMART PLBG & HTG CORP | 05/26/2004 |
| BIS | OT | ISSUED | A. ROBENSON INC | 05/10/2004 |
| BIS | OT | ISSUED | A. ROBENSON INC | 05/10/2004 |
| BIS | PL | ISSUED | THE PLUMB CO FLUSH PLBG | 12/09/2003 |
| BIS | OT | ISSUED | RITE-WAY WOOD-CRAFTS CO | 10/28/2003 |
| BIS | — | ISSUED | RITE-WAY WOOD-CRAFTS CO | 10/28/2003 |
| BIS | — | ISSUED | RITE-WAY WOOD-CRAFTS CO | 03/06/2003 |
| BIS | EQ | ISSUED | COLGATE SCAFFOLDING & EQUIP CO | 02/14/2003 |
| BIS | EQ | RE-ISSUED | COLGATE SCAFF EQUIP. | 02/13/2003 |
| BIS | OT | RE-ISSUED | RITE-WAY WOOD-CRAFTS CO | 01/07/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/21/2023 | Permit Issued | POWER SURGE ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/13/2024 | Permit Issued | GSTRUCTION CORP | Steel, Concrete, Masonry, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/07/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/15/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 07/03/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/22/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/25/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/05/2026 | Fire-Resistant Penetrations and Joints | Giap Flores | special |
| 02/05/2026 | HVAC-R and service water piping design and insulation | Giap Flores | energy_progress |
| 01/12/2026 | Fire-Resistant Penetrations and Joints | Giap Flores | special |
| 01/12/2026 | HVAC-R and service water piping design and insulation | Giap Flores | energy_progress |
| 09/13/2024 | Final | ERIC ANDREASEN | progress |
| 09/13/2024 | Subgrade Inspections | Jeffrey Stones | special |
| 09/13/2024 | Structural Steel - Welding | Jeffrey Stones | special |
| 09/13/2024 | Structural Steel - High Strength Bolting | Jeffrey Stones | special |
| 09/13/2024 | Structural Steel - Details | Jeffrey Stones | special |
| 09/13/2024 | Post-installed Anchors | Jeffrey Stones | special |
| 09/13/2024 | Concrete - Cast-In-Place | Jeffrey Stones | special |
| 09/13/2024 | Footing and Foundation | Jeffrey Stones | progress |
| 04/28/2023 | Energy Code Compliance Inspections | ERIC ANDREASEN | progress |
| 04/28/2023 | Structural Stability – Alterations of existing buildings | CHUNG CHING JEN | special |
| 04/28/2023 | Fire-Resistant Penetrations and Joints | ERIC ANDREASEN | special |
| 04/28/2023 | Final | ERIC ANDREASEN | progress |
| 04/28/2023 | Fire-Resistance Rated Construction | CHUNG CHING JEN | progress |
| 04/28/2023 | Insulation placement and R values | ERIC ANDREASEN | energy_progress |
| 04/28/2023 | Air barrier - visual inspection | ERIC ANDREASEN | energy_progress |
| 04/28/2023 | Fenestration areas | ERIC ANDREASEN | energy_progress |
| 04/28/2023 | Lighting in dwelling units | ERIC ANDREASEN | energy_progress |
| 04/28/2023 | Fenestration and door U-factor and product ratings | ERIC ANDREASEN | energy_progress |
| 04/28/2023 | Fenestration air leakage | ERIC ANDREASEN | energy_progress |
| 11/08/2022 | Structural Stability – Alterations of existing buildings | Jeffrey Stones | special |
| 11/08/2022 | Insulation placement and R values | ERIC ANDREASEN | energy_progress |