| Owner | Filings | Most Recent |
|---|---|---|
| HAWK CONTRACTING OF NY IN | 6 | 03/22/2026 |
| HOLOK CONTRACTING OF NY I | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/11/2024 | $4.9M | — | Private party → Private party | $1,727/sf building |
| 03/23/2023 | $4.7M | — | — → — | $1,650/sf building |
| 06/19/2019 | $1.9M | — | Private party → EYE EL OH WORKS LLC | $658/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PWR ENGINEERING DESIGN DPC | 1 | 05/27/2026 |
| HAMANN ENGINEERING, PLLC | 3 | 12/20/2022 |
| CSANAD BODNAR ARCHITECT | 7 | 06/28/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| BIG ORANGE EXPEDITING | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HAWK CONTRACTING OF NY IN | General Contractor | 3 | 07/08/2026 |
| AIR DEPOT COMM. REFR. COR | General Contractor | 2 | 03/21/2026 |
| GO GREENER PLUMBING LLC | Plumbing | 2 | 03/22/2026 |
| QMB PLUMBING & HEATING INC | Plumbing | 2 | 03/22/2026 |
| TM SELECT ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| FULL CIRCLE PLUMBING CORP. | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HAMANN ENGINEERING, PLLC | 4949 | 2 | 12/20/2022 |
| CBA | 5091 | 7 | 11/01/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | AIR DEPOT COMM REFR COR | 07/28/2022 |
| DOB NOW | Plumbing | Signed-off | FULL CIRCLE PLUMBING CORP | 06/01/2021 |
| DOB NOW | Construction Fence | Signed-off | HAWK CONTRACTING OF NY IN | 05/21/2021 |
| BIS | — | ISSUED | N/A | 11/07/1996 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/21/2022 | Complete | TM SELECT ELECTRIC CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/08/2026 | Air barrier — testing | — | energy_progress |
| 05/22/2026 | Fenestration areas | — | energy_progress |
| 05/22/2026 | Insulation placement and R values | — | energy_progress |
| 05/22/2026 | Maintenance information | — | energy_progress |
| 05/22/2026 | Air barrier - visual inspection | — | energy_progress |
| 05/22/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 05/22/2026 | Permanent certificate | — | energy_progress |
| 05/22/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 05/22/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 05/22/2026 | Energy Code Compliance Inspections | — | progress |
| 05/22/2026 | Fire-Resistance Rated Construction | — | progress |
| 05/22/2026 | Interior lighting power | — | energy_progress |
| 05/22/2026 | Fenestration air leakage | — | energy_progress |
| 12/20/2022 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 12/20/2022 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 12/20/2022 | Fire-Resistance Rated Construction | CARL HAMANN | progress |
| 12/20/2022 | Fire-Resistance Rated Construction | CARL HAMANN | progress |
| 10/25/2022 | Fire-Resistance Rated Construction | CSANAD BODNAR | progress |
| 10/25/2022 | Fire-Resistant Penetrations and Joints | CSANAD BODNAR | special |
| 06/24/2022 | Fire-Resistant Penetrations and Joints | CSANAD BODNAR | special |
| 06/24/2022 | Fire-Resistance Rated Construction | CSANAD BODNAR | progress |
| 05/09/2022 | Fire-Resistance Rated Construction | CSANAD BODNAR | progress |
| 05/09/2022 | Fire-Resistant Penetrations and Joints | CSANAD BODNAR | special |
| 09/08/2021 | Fire-Resistant Penetrations and Joints | CSANAD BODNAR | special |
| 09/08/2021 | Fire-Resistance Rated Construction | CSANAD BODNAR | progress |