| Owner | Filings | Most Recent |
|---|---|---|
| RYBAK DEVELOPMENT CON | 6 | 07/08/2026 |
| OWNERS REP | 16 | 07/08/2026 |
| RYBAK DEVELOPMENT AND CON | 5 | 03/22/2026 |
| CORE SCAFFOLD SYSTEMS | 3 | 03/21/2026 |
| 331-337 E82ST | 9 | 03/21/2026 |
| 335 EAST 82ND STREET | 4 | 03/21/2026 |
| 337 EAST 82ND STREET | 4 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/19/2018 | $5.0M | — | 331 EAST 82ND STREET, LLC → 333 EAST 82ND STREET DEVELOPMENT LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| LILKER ASSOCIATES CONSULTING ENGINE | 5 | 09/28/2023 |
| OGAWA DEPARDON | 3 | 06/19/2023 |
| ZPROEKT ARCHITECTURE | 3 | 03/17/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 04/14/2021 |
| SCALAR ARCHITECTURE PC | 1 | 02/14/2020 |
| BAILEYS ENGINEERING PC | 4 | 01/28/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADAM BERGMAN CONSTRUCTION AND DEVEL | 4 | 03/21/2026 |
| RYBAK DEVELOPMENT | 12 | 03/21/2026 |
| JUST ARCHITECTURE | 3 | 03/21/2026 |
| AE DESIGN SOLUTION | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 11 | 07/08/2026 |
| RYBAK DEVELOPMENT AND CONSTRUCT | General Contractor | 6 | 07/08/2026 |
| STEVEN SNYDER | Electrical | 4 | 03/21/2026 |
| RYBAK DEVELOPMENT CORP | General Contractor | 3 | 07/08/2026 |
| ALEXANDER LEVIN | Electrical | 3 | 03/21/2026 |
| V. VASS ELECTRIC CORP | Electrical | 2 | 03/22/2026 |
| STARLITE PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| FIREQUEST CORP | Fire Protection | 1 | 07/08/2026 |
| FINE CONSTRUCTION SERVICE | General Contractor | 1 | 07/08/2026 |
| IMPACT PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| METRIC CONSULTING AND INS | 1803 | 7 | 09/28/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | IMPACT PLUMBING INC | 06/21/2023 |
| DOB NOW | General Construction | Signed-off | RYBAK DEVELOPMENT CORP | 04/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | RYBAK DEVELOPMENT CORP | 04/20/2023 |
| DOB NOW | General Construction | Signed-off | FINE CONSTRUCTION SERVICE | 04/13/2023 |
| DOB NOW | Sprinklers | Signed-off | FIREQUEST CORP | 03/14/2023 |
| DOB NOW | Sprinklers | Signed-off | STARLITE PLBG & HTG CORP | 03/14/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 02/19/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 02/08/2022 |
| DOB NOW | Construction Fence | Signed-off | RYBAK DEVELOPMENT AND CON | 10/31/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 02/19/2021 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 02/12/2021 |
| DOB NOW | Construction Fence | Signed-off | RYBAK DEVELOPMENT AND CON | 11/12/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 02/22/2020 |
| DOB NOW | Construction Fence | Signed-off | RYBAK DEVELOPMENT AND CON | 12/27/2019 |
| DOB NOW | Curb Cut | Signed-off | RYBAK DEVELOPMENT AND CON | 01/17/2019 |
| BIS | — | ISSUED | RYBAK DEVELOPMENT AND CONSTRUCT | 02/07/2022 |
| BIS | PL | ISSUED | STARLITE PLBG & HTG CORP | 11/01/2021 |
| BIS | — | ISSUED | RYBAK DEVELOPMENT AND CONSTRUCT | 10/29/2021 |
| BIS | EQ | ISSUED | CORE SCAFFOLD SYSTEMS INC. | 10/21/2021 |
| BIS | — | ISSUED | RYBAK DEVELOPMENT AND CONSTRUCT | 12/08/2020 |
| BIS | PL | ISSUED | STARLITE PLBG & HTG CORP | 11/03/2020 |
| BIS | EQ | ISSUED | CORE SCAFFOLD SYSTEMS INC. | 10/22/2020 |
| BIS | EQ | ISSUED | CORE SCAFFOLD SYSTEMS INC. | 02/18/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/18/2023 | Complete | A.L. ELECTRICAL CORP. | General Wiring |
| 08/09/2022 | Complete | A.L. ELECTRICAL CORP. | General Wiring |
| 12/16/2020 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 02/12/2020 | Complete | V. VASS ELECTRIC CORP | — |
| 01/31/2020 | Complete | V. VASS ELECTRIC CORP | — |
| 01/22/2019 | Complete | V. VASS ELECTRIC CORP | — |
| 01/22/2019 | Complete | V. VASS ELECTRIC CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/05/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/26/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/15/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/10/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/05/2023 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 10/05/2023 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |
| 10/05/2023 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 10/05/2023 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 10/05/2023 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 10/05/2023 | Tenant Protection Plan Compliance | — | special |
| 10/05/2023 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 10/05/2023 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 09/28/2023 | Tenant Protection Plan Compliance | — | special |
| 09/22/2023 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 09/22/2023 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 09/22/2023 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 06/20/2023 | Final | Gilles Depardon | progress |
| 06/20/2023 | Fire-Resistance Rated Construction | Gilles Depardon | progress |
| 06/14/2023 | Final | Gilles Depardon | progress |
| 06/14/2023 | Fire-Resistance Rated Construction | Gilles Depardon | progress |
| 02/23/2023 | Maintenance information | SAMI HAJJAR P.E | energy_progress |
| 02/23/2023 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 02/23/2023 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |
| 02/23/2023 | HVAC-R and service water piping design and insulation | SAMI HAJJAR P.E | energy_progress |
| 02/23/2023 | Ventilation and air distribution system | SAMI HAJJAR P.E | energy_progress |
| 02/16/2023 | Final | SAMI HAJJAR P.E | progress |
| 02/16/2023 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 02/04/2020 | Final | JULIO SALCEDO-FERNANDEZ | progress |
| 01/18/2019 | Final | PAUL BAILEY | progress |