| Owner | Filings | Most Recent |
|---|---|---|
| Times Circle Associates | 25 | 03/22/2026 |
| Abramson Brothers | 23 | 10/04/2026 |
| Olde Good Things | 1 | 03/22/2026 |
| Fifty East Forty Second Company | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Cetraruddy Architecture | 4 | 10/20/2026 |
| Gea Consulting Engineers | 6 | 09/21/2026 |
| Kiefer & Schuster Engineering | 2 | 08/19/2026 |
| Surface Design | 1 | 12/30/2025 |
| Ashraf | 1 | 06/21/2025 |
| Aht Engineering | 1 | 02/26/2024 |
| Howard L Zimmerman Arch & Engineering | 3 | 05/10/2022 |
| NB&C | 1 | 12/18/2019 |
| TW Engineering | 1 | 11/14/2019 |
| Scherer Design Group | 1 | 04/16/2018 |
| Direct Access Expediting | 1 | 02/12/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| DVA Advisors | 7 | 03/21/2026 |
| NYPL | 3 | 03/21/2026 |
| CCM Services Group | 1 | 03/21/2026 |
| Construction Permit Services | 1 | 03/21/2026 |
| KM Associates of New York | 1 | 03/21/2026 |
| K & M Associates | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| West New York Restoration of CT | Scaffold | 4 | 07/08/2026 |
| Bayside Contracting | General Contractor | 3 | 07/08/2026 |
| Sac Wireless | General Contractor | 3 | 03/21/2026 |
| Phoenix Sutton STR | Scaffold | 3 | 09/03/2026 |
| P.I. Mechanical | specialty_contractor | 2 | 03/21/2026 |
| Speakeasy Inter and Electric | Electrical | 1 | 03/22/2026 |
| I.K.E. Electrical | Electrical | 1 | 03/21/2026 |
| Digital Construction Technologies | General Contractor | 1 | 07/08/2026 |
| Press Builders | General Contractor | 1 | 07/08/2026 |
| Arch Electric | Electrical | 1 | 03/21/2026 |
| Reem Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Crocitto, Jr., William | Electrical | 1 | 03/21/2026 |
| Deluca John | Electrical | 1 | 03/21/2026 |
| A/C Electric of New York | Electrical | 1 | 03/21/2026 |
| Delco Electrical | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Domani Inspection Service | 843 | 6 | 09/21/2026 |
| Howard L Zimmerman Architects | 1712 | 3 | 05/10/2022 |
| Burtner Engineering Services | 5910 | 1 | 12/18/2019 |
| Crosscheck Inspection Services | 544 | 1 | 11/14/2019 |
| Scherer Design Group | 6303 | 1 | 04/16/2018 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | Phoenix Sutton STR | 09/02/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Phoenix Sutton STR | 06/15/2026 |
| DOB NOW | General Construction | Permit Issued | Press Builders | 06/02/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Phoenix Sutton STR | 06/24/2025 |
| DOB NOW | Plumbing | Signed-off | Reem Plumbing & Heating | 05/16/2024 |
| DOB NOW | General Construction | Signed-off | Bayside Contracting | 07/14/2022 |
| DOB NOW | General Construction | Signed-off | Bayside Contracting | 02/04/2022 |
| DOB NOW | Antenna | Permit Issued | Sac Wireless | 12/20/2019 |
| DOB NOW | Mechanical Systems | Permit Issued | P.I. Mechanical | 11/27/2019 |
| DOB NOW | Antenna | Signed-off | Digital Construction Technologies | 08/30/2018 |
| DOB NOW | Supported Scaffold | Signed-off | A. Peter Luger Construction | 05/31/2018 |
| DOB NOW | Supported Scaffold | Signed-off | A. Peter Luger Construction | 04/23/2018 |
| DOB NOW | Supported Scaffold | Signed-off | A. Peter Luger Construction | 02/13/2018 |
| BIS | OT | ISSUED | MTD Renovation | 03/10/2020 |
| BIS | OT | ISSUED | Digital Construction Technologies | 12/30/2016 |
| BIS | PL | ISSUED | Dell Mechanical | 12/15/2016 |
| BIS | MH | ISSUED | New York Construction Associates | 12/07/2016 |
| BIS | OT | ISSUED | Digital Construction Technologies | 06/27/2016 |
| BIS | OT | ISSUED | Aliantel | 08/27/2015 |
| BIS | MH | ISSUED | Empire Telecom USA | 01/15/2015 |
| BIS | MH | ISSUED | Empire Telecom USA | 09/05/2014 |
| BIS | OT | ISSUED | Xinos Construction | 03/04/2014 |
| BIS | EQ | ISSUED | Xinos Construction | 03/03/2014 |
| BIS | OT | ISSUED | Xinos Construction | 08/06/2013 |
| BIS | EQ | ISSUED | Xinos Construction | 06/11/2013 |
| BIS | FS | ISSUED | Ace Atlas | 02/01/2012 |
| BIS | EQ | ISSUED | West New York Restoration of CT | 03/29/2010 |
| BIS | MH | ISSUED | Kings Mechanical | 04/23/2009 |
| BIS | PL | ISSUED | The Plumbing Company | 12/08/2008 |
| BIS | OT | ISSUED | Kings Mechanical | 12/04/2008 |
| BIS | FB | ISSUED | Ace Atlas | 06/08/2007 |
| BIS | OT | ISSUED | Architron Designer & Builders | 03/21/2006 |
| BIS | PL | ISSUED | The Right Connection P&H | 03/02/2006 |
| BIS | OT | ISSUED | Architron Designer & Builders | 02/21/2006 |
| BIS | PL | ISSUED | Reem PLG & Heating | 09/27/2005 |
| BIS | OT | ISSUED | Integra Construction Ofnew York | 06/10/2005 |
| BIS | OT | ISSUED | Reld Deve | 01/21/2005 |
| BIS | OT | ISSUED | West New York Restoration of CT | 06/28/2004 |
| BIS | EQ | ISSUED | West New York Restoration of CT | 06/28/2004 |
| BIS | EQ | ISSUED | West New York Restoration of CT | 06/28/2004 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/21/2026 | Permit Issued | Press Builders | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Captiveaire CAS-HVAC3 188,200 BTU · Rooftop Unit ×1 Ventilation Greenheck AX-72-190-0425-A50 11,500 CFM · Exhaust Fan ×2 |
| 11/14/2019 | Permit Issued | P.I. Mechanical | Air Conditioning Systems, Associated Ducts and Piping | Cooling Armstrong Air 4SCU13LE160P-5 60,000 BTU · Condensing Unit ×4 4SCU13LE148P-5 48,000 BTU · Condensing Unit ×2 Ducts & Piping |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/21/2026 | — | — | Sprinkler System |
| 08/19/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/21/2026 | — | — | Storm, Water/Sanitary |
| 02/26/2024 | Signed-off | Reem Plumbing & Heating | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2025 | Permit Issued | Richard Neu | — |
| 09/28/2020 | Complete | Speakeasy Inter and Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/21/2026 | Permit Issued | Press Builders | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/21/2025 | Permit Issued | Phoenix Sutton STR | Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/13/2026 | Final | JOHN MCMONAGLE | progress |
| 07/13/2026 | Mechanical Systems | JOHN MCMONAGLE | special |
| 06/29/2026 | Standpipe Systems | JOHN MCMONAGLE | special |
| 03/16/2026 | Post-installed Anchors | — | special |
| 11/27/2025 | Structural Steel - Details | JOHN MCMONAGLE | special |
| 11/27/2025 | Structural Steel - Welding | JOHN MCMONAGLE | special |
| 11/27/2025 | Structural Stability – Alterations of existing buildings | JOHN MCMONAGLE | special |
| 11/27/2025 | Concrete - Cast-In-Place | JOHN MCMONAGLE | special |
| 11/27/2025 | Post-installed anchors in masonry | JOHN MCMONAGLE | special |
| 11/27/2025 | Structural Steel - High Strength Bolting | JOHN MCMONAGLE | special |
| 11/17/2025 | Final | — | progress |
| 11/17/2025 | Mechanical Systems | — | special |
| 11/17/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 11/06/2025 | Final | — | progress |
| 11/04/2025 | Final | JOHN MCMONAGLE | progress |
| 11/04/2025 | Footing and Foundation | — | progress |
| 11/04/2025 | Final | — | progress |
| 11/04/2025 | Post-installed Anchors | — | special |
| 11/04/2025 | Concrete - Cast-In-Place | — | special |
| 02/14/2024 | HVAC-R and service water piping design and insulation | ABRAHAM TAWIL | energy_progress |
| 05/13/2022 | Concrete - Cast-In-Place | Howard Zimmerman | special |
| 05/13/2022 | Structural Steel - Details | Howard Zimmerman | special |
| 05/13/2022 | Structural Stability – Alterations of existing buildings | Howard Zimmerman | special |
| 05/13/2022 | Post-installed Anchors | Howard Zimmerman | special |
| 05/13/2022 | Sprayed fire-resistant materials | Howard Zimmerman | special |