| Owner | Filings | Most Recent |
|---|---|---|
| HANNAH SENESH COMMUNITY DAY SCHOOL | 42 | 07/08/2026 |
| PARK CONTRACTING GROUP | 4 | 04/09/2026 |
| COMM SCHOLL DIST 15 | 1 | 03/22/2026 |
| DVIR MOG 18 | 3 | 03/21/2026 |
| TALICO CONTRACTING | 3 | 03/21/2026 |
| HANNAH SENESH COMM DAY SCHOOL | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 1 | 02/17/2026 |
| EMTG CONSULTANTS INC | 8 | 07/12/2023 |
| PELLOVERTON LLC | 6 | 07/12/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM ZONING, LLC. | 28 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KING ROSE OF NY, INC | General Contractor | 17 | 07/08/2026 |
| NY SHEET METAL INC | General Contractor | 3 | 03/21/2026 |
| FIREQUEST CORP | Fire Protection | 2 | 07/08/2026 |
| EURO ART CONSTRUCTION COR | General Contractor | 2 | 07/08/2026 |
| TORRES IVAN | Electrical | 1 | 03/21/2026 |
| ACCESS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| ZIN ELECTRICAL, INC | Electrical | 1 | 03/22/2026 |
| ORBIT SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| PARK CONTRACTING GROUP | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ACE STRUCTURAL ENGINEERIN | 496 | 10 | 07/12/2023 |
| EMTG CONSULTANTS | 4222 | 2 | 08/03/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Signed-off | PARK CONTRACTING GROUP | 02/19/2026 |
| DOB NOW | General Construction | Signed-off | KING ROSE OF NY, INC | 01/25/2024 |
| DOB NOW | General Construction | Signed-off | KING ROSE OF NY, INC | 01/17/2024 |
| DOB NOW | Sprinklers | Signed-off | FIREQUEST CORP | 07/20/2023 |
| DOB NOW | Sprinklers | Signed-off | FIREQUEST CORP | 07/20/2023 |
| DOB NOW | Plumbing | Signed-off | ACCESS PLUMBING CORP | 07/19/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KING ROSE OF NY, INC | 07/18/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KING ROSE OF NY, INC | 07/18/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KING ROSE OF NY, INC | 07/18/2023 |
| DOB NOW | General Construction | Signed-off | KING ROSE OF NY, INC | 06/15/2023 |
| DOB NOW | General Construction | Signed-off | KING ROSE OF NY, INC | 06/15/2023 |
| DOB NOW | Sprinklers | Signed-off | ORBIT SPRINKLER CORP | 08/11/2022 |
| DOB NOW | Mechanical Systems | Signed-off | NY SHEET METAL INC | 08/11/2022 |
| DOB NOW | Mechanical Systems | Signed-off | EURO ART CONSTRUCTION COR | 08/10/2022 |
| DOB NOW | General Construction | Signed-off | EURO ART CONSTRUCTION COR | 08/09/2022 |
| BIS | EQ | ISSUED | TALICO CONTRACTING INC | 03/18/2016 |
| BIS | EQ | ISSUED | DVIR MOG 18 INC | 03/17/2016 |
| BIS | OT | ISSUED | AFNA GENERAL CONSTR LLC | 06/11/2013 |
| BIS | PL | ISSUED | KAPNAG HTG & PLBG CORP. | 02/23/2007 |
| BIS | PL | ISSUED | KAPNAG HTG & PLBG CORP. | 11/22/2006 |
| BIS | EQ | ISSUED | COLGATE SCAFFOLDING | 06/21/2006 |
| BIS | EQ | ISSUED | COLGATE SCAFFOLDING | 05/15/2006 |
| BIS | — | ISSUED | A.W. & S. CONSTRUCTION CO | 03/31/2006 |
| BIS | OT | ISSUED | A.W. & S. CONSTRUCTION CO | 03/31/2006 |
| BIS | SP | ISSUED | FIVE BORO ASSOCIATES INC | 01/10/2006 |
| BIS | PL | ISSUED | KAPNAG HTG & PLBG CORP. | 11/18/2005 |
| BIS | — | ISSUED | A.W. & S. CONSTRUCTION CO | 11/18/2005 |
| BIS | EQ | ISSUED | COLGATE SCAFFOLDING | 09/21/2005 |
| BIS | EQ | RE-ISSUED | COLGATE SCAFFOLDING | 09/21/2005 |
| BIS | OT | ISSUED | A.W. & S. CONSTRUCTION CO | 06/07/2005 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/12/2023 | Signed-off | FIREQUEST CORP | — |
| 07/12/2023 | Signed-off | FIREQUEST CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/16/2026 | Complete | RICHARD NEU | — |
| 01/28/2024 | Complete | ZIN ELECTRICAL, INC | General Wiring |
| 01/19/2024 | Complete | ACCURATE ELEC'L CONTR'S C | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/10/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/08/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/08/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/07/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/02/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/30/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/12/2023 | Energy Code Compliance Inspections | ANTHONY UGBEBOR | progress |
| 07/12/2023 | Shutoff dampers | ANTHONY UGBEBOR | energy_progress |
| 07/12/2023 | HVAC-R and service water piping design and insulation | ANTHONY UGBEBOR | energy_progress |
| 07/12/2023 | Fire-Resistant Penetrations and Joints | ANTHONY UGBEBOR | special |
| 07/11/2023 | HVAC-R and service water heating equipment | ANTHONY UGBEBOR | energy_progress |
| 07/11/2023 | HVAC-R and service water piping design and insulation | ANTHONY UGBEBOR | energy_progress |
| 07/11/2023 | Fire-Resistant Penetrations and Joints | ANTHONY UGBEBOR | special |
| 07/11/2023 | HVAC-R and service water piping design and insulation | ANTHONY UGBEBOR | energy_progress |
| 07/11/2023 | Energy Code Compliance Inspections | ANTHONY UGBEBOR | progress |
| 07/11/2023 | Shutoff dampers | ANTHONY UGBEBOR | energy_progress |
| 07/11/2023 | Energy Code Compliance Inspections | ANTHONY UGBEBOR | progress |
| 07/11/2023 | HVAC-R and service water heating system controls | ANTHONY UGBEBOR | energy_progress |
| 07/11/2023 | Shutoff dampers | ANTHONY UGBEBOR | energy_progress |
| 07/10/2023 | Mechanical Systems | ANTHONY UGBEBOR | special |
| 07/10/2023 | Final | ANTHONY UGBEBOR | progress |
| 07/10/2023 | Mechanical Systems | ANTHONY UGBEBOR | special |
| 07/10/2023 | Final | ANTHONY UGBEBOR | progress |
| 07/10/2023 | Sprinkler Systems | ANTHONY UGBEBOR | special |
| 07/10/2023 | Fire-Resistant Penetrations and Joints | ANTHONY UGBEBOR | special |
| 07/10/2023 | Fire-Resistance Rated Construction | ANTHONY UGBEBOR | progress |
| 07/10/2023 | Final | ANTHONY UGBEBOR | progress |
| 06/27/2023 | Sprinkler Systems | ANTHONY UGBEBOR | special |
| 06/27/2023 | Mechanical Systems | ANTHONY UGBEBOR | special |
| 06/27/2023 | Final | ANTHONY UGBEBOR | progress |
| 04/19/2023 | Fire-Resistant Penetrations and Joints | ANTHONY UGBEBOR | special |