Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofMechanical systemsUnder Construction45p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
STRUCTURAL WORK HORIZONTAL AND VERTICAL EXTENSION, REINFORCE EXISTING WOOD JOISTS IN CONJUNCTION WITHALT-1 JOB #B01320238-I1
On file for this project
107 documents · 6 drawing sheets
INSTALLATION OF A VRF HEAT PUMP SYSTEM COMPLETE WITH ROOF MOUNTED CONDENSING UNIT AND FULLY DUCTED INDOOR AIR HANDLING UNITS AND CONTROLS, MECHANICAL VENTILATION AND EXHAUST SYSTEMS FOR KITCHENS, BATHROOMS, AND LAUNDRY.
On file for this project
10 documents · 1 drawing sheet
PROPOSE TO VERTICALLY ENLARGE EXISTING 3-STORY BUILDING BY ADDING A NEW 4TH FLOOR AND EXTENDING HORIZONTALLY INTO THE REAR YARD. MAINTAIN RESIDENTIAL USE (U.G. 2A) REQUEST REVIEW UNDER 2022 BUILDING CODE. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED.
On file for this project
24 documents
Floor 3Mechanical systemsUnder Construction40p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
STRUCTURAL WORK HORIZONTAL AND VERTICAL EXTENSION, REINFORCE EXISTING WOOD JOISTS IN CONJUNCTION WITHALT-1 JOB #B01320238-I1
On file for this project
107 documents · 2 drawing sheets
INSTALLATION OF A VRF HEAT PUMP SYSTEM COMPLETE WITH ROOF MOUNTED CONDENSING UNIT AND FULLY DUCTED INDOOR AIR HANDLING UNITS AND CONTROLS, MECHANICAL VENTILATION AND EXHAUST SYSTEMS FOR KITCHENS, BATHROOMS, AND LAUNDRY.
On file for this project
10 documents
PROPOSE TO VERTICALLY ENLARGE EXISTING 3-STORY BUILDING BY ADDING A NEW 4TH FLOOR AND EXTENDING HORIZONTALLY INTO THE REAR YARD. MAINTAIN RESIDENTIAL USE (U.G. 2A) REQUEST REVIEW UNDER 2022 BUILDING CODE. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED.
On file for this project
24 documents · 1 drawing sheet
Floor 2Mechanical systemsUnder Construction39p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
STRUCTURAL WORK HORIZONTAL AND VERTICAL EXTENSION, REINFORCE EXISTING WOOD JOISTS IN CONJUNCTION WITHALT-1 JOB #B01320238-I1
On file for this project
107 documents · 1 drawing sheet
INSTALLATION OF A VRF HEAT PUMP SYSTEM COMPLETE WITH ROOF MOUNTED CONDENSING UNIT AND FULLY DUCTED INDOOR AIR HANDLING UNITS AND CONTROLS, MECHANICAL VENTILATION AND EXHAUST SYSTEMS FOR KITCHENS, BATHROOMS, AND LAUNDRY.
On file for this project
10 documents
PROPOSE TO VERTICALLY ENLARGE EXISTING 3-STORY BUILDING BY ADDING A NEW 4TH FLOOR AND EXTENDING HORIZONTALLY INTO THE REAR YARD. MAINTAIN RESIDENTIAL USE (U.G. 2A) REQUEST REVIEW UNDER 2022 BUILDING CODE. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED.
On file for this project
24 documents
Floor 1Mechanical systemsUnder Construction38p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
STRUCTURAL WORK HORIZONTAL AND VERTICAL EXTENSION, REINFORCE EXISTING WOOD JOISTS IN CONJUNCTION WITHALT-1 JOB #B01320238-I1
On file for this project
107 documents
INSTALLATION OF A VRF HEAT PUMP SYSTEM COMPLETE WITH ROOF MOUNTED CONDENSING UNIT AND FULLY DUCTED INDOOR AIR HANDLING UNITS AND CONTROLS, MECHANICAL VENTILATION AND EXHAUST SYSTEMS FOR KITCHENS, BATHROOMS, AND LAUNDRY.
On file for this project
10 documents
PROPOSE TO VERTICALLY ENLARGE EXISTING 3-STORY BUILDING BY ADDING A NEW 4TH FLOOR AND EXTENDING HORIZONTALLY INTO THE REAR YARD. MAINTAIN RESIDENTIAL USE (U.G. 2A) REQUEST REVIEW UNDER 2022 BUILDING CODE. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED.
On file for this project
24 documents
CellarMechanical systemsUnder Construction43p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers
STRUCTURAL WORK HORIZONTAL AND VERTICAL EXTENSION, REINFORCE EXISTING WOOD JOISTS IN CONJUNCTION WITHALT-1 JOB #B01320238-I1
On file for this project
107 documents · 4 drawing sheets
INSTALLATION OF A VRF HEAT PUMP SYSTEM COMPLETE WITH ROOF MOUNTED CONDENSING UNIT AND FULLY DUCTED INDOOR AIR HANDLING UNITS AND CONTROLS, MECHANICAL VENTILATION AND EXHAUST SYSTEMS FOR KITCHENS, BATHROOMS, AND LAUNDRY.
On file for this project
10 documents · 1 drawing sheet
PROPOSE TO VERTICALLY ENLARGE EXISTING 3-STORY BUILDING BY ADDING A NEW 4TH FLOOR AND EXTENDING HORIZONTALLY INTO THE REAR YARD. MAINTAIN RESIDENTIAL USE (U.G. 2A) REQUEST REVIEW UNDER 2022 BUILDING CODE. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED.
On file for this project
24 documents · 1 drawing sheet
BasementUnder Construction36p · 1 filing · 20 docs
ArchitectureFire ProtectionPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sprinklers · Structural
STRUCTURAL WORK HORIZONTAL AND VERTICAL EXTENSION, REINFORCE EXISTING WOOD JOISTS IN CONJUNCTION WITHALT-1 JOB #B01320238-I1
On file for this project
107 documents · 1 drawing sheet
Sub-BasementMechanical systems14p · 2 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
INSTALLATION OF A VRF HEAT PUMP SYSTEM COMPLETE WITH ROOF MOUNTED CONDENSING UNIT AND FULLY DUCTED INDOOR AIR HANDLING UNITS AND CONTROLS, MECHANICAL VENTILATION AND EXHAUST SYSTEMS FOR KITCHENS, BATHROOMS, AND LAUNDRY.
On file for this project
10 documents
PROPOSE TO VERTICALLY ENLARGE EXISTING 3-STORY BUILDING BY ADDING A NEW 4TH FLOOR AND EXTENDING HORIZONTALLY INTO THE REAR YARD. MAINTAIN RESIDENTIAL USE (U.G. 2A) REQUEST REVIEW UNDER 2022 BUILDING CODE. NO CHANGE TO USE, OCCUPANCY OR EGRESS PROPOSED.
On file for this project
24 documents
Site & exteriorProposed Heavy Duty Sidewalk Shed (live Load - 300 Psf)4p · 1 filing · 2 docs
EquipmentGeneralMechanicalStructural
Issued Permit Scope
Sidewalk Shed
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
On file for this project
2 documents · 4 drawing sheets