| Owner | Filings | Most Recent |
|---|---|---|
| TIMES CONSTRUCTION AND DE | 3 | 03/22/2026 |
| BAY 221 MANAGEMENT | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/20/2021 | $425K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ABC ENGINEERING PLLC | 11 | 04/04/2025 |
| TIMES BUILDINGS ENGINEERING SER PC | 3 | 12/04/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| ABC ENGINEERING PLLC | 22 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TIMES CONSTRUCTION & DEV | General Contractor | 15 | 07/08/2026 |
| PLUMBING NYC INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PAUL ENGINEERING INSPECTI | 4672 | 2 | 04/04/2025 |
| PETER R TAUBERER, PE PLLC | 3510 | 7 | 04/04/2025 |
| PROFESSIONAL SOLUTIONS GR | 1756 | 2 | 04/04/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | TIMES CONSTRUCTION & DEV | 03/13/2025 |
| DOB NOW | Construction Fence | Signed-off | TIMES CONSTRUCTION & DEV | 01/14/2025 |
| DOB NOW | Plumbing | Signed-off | PLUMBING WORKS NYC INC | 06/26/2024 |
| DOB NOW | Plumbing | Signed-off | PLUMBING WORKS NYC INC | 06/26/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TIMES CONSTRUCTION & DEV | 06/20/2024 |
| DOB NOW | General Construction | Permit Issued | TIMES CONSTRUCTION & DEV | 03/20/2024 |
| DOB NOW | Foundation | Signed-off | TIMES CONSTRUCTION & DEV | 01/24/2024 |
| DOB NOW | Support of Excavation | Signed-off | TIMES CONSTRUCTION & DEV | 01/24/2024 |
| DOB NOW | Structural | Signed-off | TIMES CONSTRUCTION & DEV | 01/23/2024 |
| DOB NOW | Construction Fence | Signed-off | TIMES CONSTRUCTION & DEV | 01/19/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/04/2025 | Signed-off | TIMES CONSTRUCTION & DEV | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/04/2025 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/04/2025 | Signed-off | PLUMBING NYC INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2025 | Complete | ERIC & NG ELEC'L, INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/04/2025 | Signed-off | TIMES CONSTRUCTION & DEV | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/19/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/18/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/13/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/05/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 02/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/28/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 10/25/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/04/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/04/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/10/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/03/2025 | Metering | PETER TAUBERER | energy_progress |
| 06/03/2025 | Fenestration air leakage | PETER TAUBERER | energy_progress |
| 06/03/2025 | Fenestration areas | PETER TAUBERER | energy_progress |
| 06/03/2025 | Fire-Resistance Rated Construction | PETER TAUBERER | progress |
| 06/03/2025 | Energy Code Compliance Inspections | PETER TAUBERER | progress |
| 06/03/2025 | Insulation placement and R values | PETER TAUBERER | energy_progress |
| 06/03/2025 | Fenestration and door U-factor and product ratings | PETER TAUBERER | energy_progress |
| 06/03/2025 | Maintenance information | PETER TAUBERER | energy_progress |
| 06/03/2025 | Air barrier — testing | PETER TAUBERER | energy_progress |
| 06/03/2025 | Interior lighting power | PETER TAUBERER | energy_progress |
| 06/03/2025 | Permanent certificate | PETER TAUBERER | energy_progress |
| 06/03/2025 | Electric vehicle service equipment requirements | PETER TAUBERER | energy_progress |
| 06/03/2025 | Protection of exposed foundation insulation | PETER TAUBERER | energy_progress |
| 06/03/2025 | Air barrier - visual inspection | PETER TAUBERER | energy_progress |
| 04/23/2025 | Energy Code Compliance Inspections | PETER TAUBERER | progress |
| 04/23/2025 | HVAC-R and service water heating equipment | PETER TAUBERER | energy_progress |
| 04/23/2025 | HVAC-R and service water heating system controls | PETER TAUBERER | energy_progress |
| 04/23/2025 | Duct leakage testing, insulation and design | PETER TAUBERER | energy_progress |
| 04/23/2025 | Ventilation and air distribution system | PETER TAUBERER | energy_progress |
| 04/23/2025 | HVAC-R and service water piping design and insulation | PETER TAUBERER | energy_progress |
| 04/23/2025 | Maintenance information | PETER TAUBERER | energy_progress |
| 04/23/2025 | Mechanical Systems | PETER TAUBERER | special |
| 04/23/2025 | Final | PETER TAUBERER | progress |
| 03/28/2025 | Energy Code Compliance Inspections | PETER TAUBERER | progress |
| 03/28/2025 | Fire-Resistant Penetrations and Joints | PETER TAUBERER | special |