← Back
Office with commercial, 7-19 stories
350 HUDSON STREET
MANHATTAN · BIN 1009750
💬 Discuss this project
1930Year Built
9Stories
O6Building Class
M1-6Zoning
259,427 sfGross Floor Area
11Units
LL97 Covered0 Open ViolationsFISP: SWARMPFDNY Report ↗
Office with commercial, 7-19 stories · Owner of record: NEW REMAINDERMAN 350 HUDSON LLC · 30,057 sf lot · 8.63 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneralOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 2 filings · 5 docs
Floor 412p · 1 filing · 20 docs
Floor 40
Floor 39
Floor 38
Floor 37
Floor 36
Floor 35
Floor 34
Floor 33
Floor 32
Floor 31
Floor 30
Floor 29
Floor 28
Floor 27
Floor 26
Floor 25
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 93p · 2 filings · 9 docs
Floor 8
Floor 7
Floor 6
Floor 53p · 3 filings · 20 docs
Floor 41p · 1 filing · 8 docs
Floor 3
Floor 211p · 7 filings · 20 docs
Floor 152p · 19 filings · 20 docs
Mezzanine4p · 4 filings · 20 docs
Cellar15p · 7 filings · 20 docs
Basement1p · 1 filing · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TRINITY HUDSON HOLDING25907/08/2026
HINES2006/28/2026
NEW REMAINDERMAN 350 HUDSON LLC103/22/2026
TRINITY REAL ESTATE18803/22/2026
ELI ACQUISITION LLC103/22/2026
TRINITY CHURCH1903/22/2026
NYCAN BUILDERS103/22/2026
SOHO CONTRACTING303/21/2026
BARONE MANAGEMENT103/21/2026
HINES LIMITED PARTNERSHIP803/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RIZZO GROUP5003/21/2026
HTX BUILDING CONSULTING1103/21/2026
LOUIS STRIAR203/21/2026
RIP CC1403/21/2026
NEW YORK DESIGN ARHICTECTS1203/21/2026
A1 EXPEDITING SERVICE CORP.403/21/2026
NEW YORK SIGN CONSULTANTS403/21/2026
GEORGE E BERGER ASS1403/21/2026
CORNERSTONE CONSULTING303/21/2026
A1 EXPEDITING SERVICE403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYCAN BUILDERS LLCGeneral Contractor2607/08/2026
DGC CAPITAL CONTRACTING CORPGeneral Contractor603/21/2026
BEST PRICE RENOVATIONS LLGeneral Contractor507/08/2026
PAR FIRE PROTECTION LLCFire Protection407/08/2026
COOPER WORKS INCGeneral Contractor403/21/2026
T LONG LLCGeneral Contractor407/08/2026
CLUNE CONSTRUCTION CO LPGeneral Contractor407/08/2026
SOHO CONTRACTING CORPGeneral Contractor304/09/2026
STRUCTURE TONE, LLCGeneral Contractor307/08/2026
FRANKLIN SQUARE CONTRACTOGeneral Contractor303/21/2026
FRANKIE PLBG & HTG L.L.CPlumbing307/08/2026
JRM CONSTRUCTION MGMT LLCGeneral Contractor307/08/2026
YATES EXTERIOR RESTORATIONGeneral Contractor303/21/2026
NU-WAY HEATING & COOLINGGeneral Contractor203/21/2026
ARTHUR GROSSMANElectrical203/21/2026
MASS CONTRACTING CORPGeneral Contractor203/21/2026
W5 GROUP LLCGeneral Contractor203/21/2026
SEAN COAKLEY P & H INCFire Protection207/08/2026
PLUMBING NYC, INCFire Protection207/08/2026
CREATIVE INSTALLATIONS INGeneral Contractor207/08/2026
ANTIS MAINTENANCE CORPGeneral Contractor204/09/2026
CUAN CORPGeneral Contractor203/21/2026
ATLAS-ACON ELEC. SERVICEElectrical203/22/2026
KAIZEN NY CONTRACTING INCGeneral Contractor203/21/2026
EVERGREEN MECHANICAL CORPFire Protection207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TSF ENGINEERING, PC1274312/19/2025
ASSURE PROFESSIONAL ENGIN6962210/29/2025
SAG ENGINEERING & CONSULT6081709/04/2025
ALAN MARGOLIN & ASSOC423711/15/2024
VIBRANALYSIS INC., DBA VT6864208/26/2024
AKS ARCHITECTURAL & ENGIN1957608/26/2024
CODEGREEN510407/27/2024
ENTHINK ENGINEERS LLC6247301/08/2024
RYAN SPECIAL ENGINEERING2018508/02/2023
MILROSE CONSULTANTS LLC2003106/28/2023
Building Lifecycle
All (300)Filed (72)Permit Issued (67)Signed Off (50)Facade (FISP) (3)Violation (11)Inspection (59)Objection (8)Special Inspection (30)
09/10/2026
Permit issued — Suspended Scaffold
M01440794-I1-SC
08/19/2026
Filed — Alteration
FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola
M01440794-I1
07/24/2026
Signed off — Alteration
Modifications to the existing HVAC System: Removal of existing HVAC unit, and Install new Unit and associated ductwork and fans on the 1st Floor as per plans (Tenant Work - Simo Pizza Renovations.) No change to use, egress or occupancy.
M01319256-I1
06/17/2026
Signed off — Alteration
M01319214-I1
06/03/2026
Permit issued — Sign
M01382344-I1-SG
05/05/2026
Filed — Alteration
INSTALL EXTERIOR ILLUMINATED WALL SIGN (PURE PAWS VETERINARY CARE)
M01382344-I1
04/02/2026
Signed off — Alteration
Modifications to the existing sprinkler system: Remove (17) existing sprinkler heads and associated piping, install (17) new sprinklers and associated sprinkler piping on the 1st Floor as per plans (Studio Pilates.) No change to use, egress or occupancy.
M01299272-I1
04/01/2026
Signed off — Alteration
M01299228-I1
03/17/2026
Signed off — Alteration
Installation of new plumbing fixtures: (1) water cooler, (1) hot water heater, (1) water closet, (1) lavatory, (1) floor drain and associated CW/sanitary piping on the 1st Floor as per plans (Studio Pilates.) No change to use, egress or occupancy.
M01297435-I1
03/17/2026
Signed off — Alteration
M01297413-I1
03/16/2026
Signed off — Alteration
ILLUMINATED NON ADVERTISING ACCESSORY WALL SIGN - INSIDE PROPERTY LINE - PURE PAWS VETERINARY CARE. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
M00805973-I1
03/12/2026
Permit issued — Sign
M00805973-I1-SG
03/03/2026
Filed — Alteration
ILLUMINATED NON ADVERTISING ACCESSORY WALL SIGN - INSIDE PROPERTY LINE - PURE PAWS VETERINARY CARE. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
M00805973-I1
02/24/2026
Signed off — Alteration
M01274235-I1
02/04/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/30/2026
Permit issued — Sprinklers
M01319283-I1-EW-SP
01/30/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/27/2026
Permit issued — Plumbing
M01319277-I1-PL
01/12/2026
Permit issued — General Construction
M01319214-I1-GC
01/06/2026
Permit issued — Mechanical Systems
M01319256-I1-MS
01/05/2026
Filed — Alteration
M01319214-I1
12/19/2025
Filed — Alteration
Modifications to the existing HVAC System: Removal of existing HVAC unit, and Install new Unit and associated ductwork and fans on the 1st Floor as per plans (Tenant Work - Simo Pizza Renovations.) No change to use, egress or occupancy.
M01319256-I1
12/19/2025
Filed — Alteration
Modifications to the existing sprinkler system: Relocate (17) sprinkler heads and associated sprinkler piping on the 1st Floor as per plans (Tenant Work - Simo Pizza.) No change to use, egress or occupancy.
M01319283-I1
12/19/2025
Filed — Alteration
Install (1) DW, (1) HWH, (1) BFP, (1) Expansion Tank, (1) Grease Interceptor, (1) IM, (1) Lavatory, (1) WC, (4) FD, (1) FS, (3) sinks and associated CW/sanitary piping on the 1st Floor as per plans (Tenant Work - Simo Pizza Renovation.)
M01319277-I1
12/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Nicholas Tucci
12/17/2025
Special inspection requirement — HVAC-R and service water heating equipment
Nicholas Tucci
12/17/2025
Special inspection requirement — Shutoff dampers
Nicholas Tucci
12/17/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Nicholas Tucci
12/17/2025
Special inspection requirement — Maintenance information
Nicholas Tucci
12/17/2025
Special inspection requirement — HVAC-R and service water heating system controls
Nicholas Tucci
12/17/2025
Special inspection requirement — Energy Code Compliance Inspections
Nicholas Tucci
12/03/2025
Signed off — Alteration
Structural Modifications; Slab infill of an existing stair opening on the 1st Floor as per plans (Hines/ Yoga Studio.) No change to use, egress or occupancy.
M01274197-I1
11/26/2025
Signed off — Alteration
Structural Modifications; Installation of structural steel on the roof as per plans (Hines - Steel Installation.) No change to use, egress or occupancy.
M01095629-I1
11/21/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/17/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
11/17/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/14/2025
Special inspection requirement — Final
Nicholas Tucci
11/14/2025
Special inspection requirement — Mechanical Systems
Nicholas Tucci
11/14/2025
Special inspection requirement — Sprinkler Systems
Nicholas Tucci
11/07/2025
Permit issued — Sprinklers
M01299272-I1-EW-SP
10/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/29/2025
Filed — Alteration
Modifications to the existing sprinkler system: Remove (17) existing sprinkler heads and associated piping, install (17) new sprinklers and associated sprinkler piping on the 1st Floor as per plans (Studio Pilates.) No change to use, egress or occupancy.
M01299272-I1
10/29/2025
Permit issued — General Construction
M01299228-I1-GC
10/27/2025
Special inspection requirement — Post-installed Anchors
GUNJAN KHANDWALA
10/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GUNJAN KHANDWALA
10/21/2025
Permit issued — Plumbing
M01297435-I1-PL
10/20/2025
Filed — Alteration
M01299228-I1
10/20/2025
Permit issued — Mechanical Systems
M01297413-I1-MS
10/17/2025
Filed — Alteration
Installation of new plumbing fixtures: (1) water cooler, (1) hot water heater, (1) water closet, (1) lavatory, (1) floor drain and associated CW/sanitary piping on the 1st Floor as per plans (Studio Pilates.) No change to use, egress or occupancy.
M01297435-I1
10/17/2025
Filed — Alteration
M01297413-I1
10/07/2025
Special inspection requirement — Final
GUNJAN KHANDWALA
10/07/2025
Special inspection requirement — Sprinkler Systems
GUNJAN KHANDWALA
10/03/2025
Special inspection requirement — Mechanical Systems
GUNJAN KHANDWALA
10/03/2025
Special inspection requirement — Final
GUNJAN KHANDWALA
09/10/2025
Violation issued (FDNY_ORDER, closed)
09/10/2025
Violation issued (FDNY_ORDER, closed)
09/10/2025
Violation issued (FDNY_ORDER, closed)
09/10/2025
Violation issued (FDNY_ORDER, closed)
09/10/2025
Violation issued (FDNY_ORDER, closed)
09/10/2025
Violation issued (FDNY_ORDER, closed)
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSTRUCTUAL PRESV SYSTEM09/10/2026
DOB NOWSignPermit IssuedNATIONAL MAINTENANCE, INC06/03/2026
DOB NOWSignSigned-offACTIVE SIGNS INC03/12/2026
DOB NOWSprinklersPermit IssuedDEPENDABLE MECHANICAL COR01/30/2026
DOB NOWPlumbingPermit IssuedA&H EXPRESS PLBG&HTG CORP01/27/2026
DOB NOWGeneral ConstructionSigned-offANTIS MAINTENANCE CORP01/12/2026
DOB NOWMechanical SystemsSigned-offANTIS MAINTENANCE CORP01/06/2026
DOB NOWSprinklersSigned-offARIANA CONTRACTING INC11/07/2025
DOB NOWGeneral ConstructionSigned-offCREATIVE INSTALLATIONS IN10/29/2025
DOB NOWPlumbingSigned-offCOPPER MECHANICAL INC10/21/2025
DOB NOWMechanical SystemsSigned-offCREATIVE INSTALLATIONS IN10/20/2025
DOB NOWGeneral ConstructionSigned-offSOHO CONTRACTING CORP09/09/2025
DOB NOWStructuralSigned-offSOHO CONTRACTING CORP09/09/2025
DOB NOWStructuralSigned-offFRANKLIN SQUARE CONTRACTO10/08/2024
DOB NOWPlumbingSigned-offPROSTAR PLUMBING AND HEAT08/06/2024
DOB NOWSprinklersSigned-offMORA FIRE PROTECTION LLC07/30/2024
DOB NOWGeneral ConstructionSigned-offCLUNE CONSTRUCTION CO LP07/30/2024
DOB NOWMechanical SystemsSigned-offCLUNE CONSTRUCTION CO LP07/29/2024
DOB NOWPlumbingSigned-offFRANKIE PLBG & HTG L.L.C05/23/2024
DOB NOWStructuralSigned-offDGC CAPITAL CONTRACTING CORP02/26/2024
DOB NOWStandpipeSigned-offEVERGREEN MECHANICAL CORP11/22/2023
DOB NOWStandpipeSigned-offEVERGREEN MECHANICAL CORP11/20/2023
DOB NOWPlumbingSigned-offFRANKIE PLBG & HTG L.L.C11/01/2023
DOB NOWGeneral ConstructionSigned-offYATES EXTERIOR RESTORATIO08/29/2023
DOB NOWMechanical SystemsSigned-offNU-WAY HEATING & COOLING08/23/2023
DOB NOWPlumbingSigned-offVILLAGE P & H NY INC08/01/2023
DOB NOWGeneral ConstructionSigned-offCUAN07/05/2023
DOB NOWMechanical SystemsSigned-offBEST PRICE RENOVATIONS LL06/09/2023
DOB NOWBoiler EquipmentSigned-offEAST COAST PETROLEUM INC05/19/2023
DOB NOWPlumbingSigned-offSKH MECHANICAL CORP05/02/2023
DOB NOWSprinklersSigned-offVILLAGE P & H NY INC04/29/2023
DOB NOWPlumbingSigned-offCITYWIDE PLBG, HTG &SPRKL04/17/2023
DOB NOWPlumbingSigned-offCITYWIDE PLBG HTG & SPKLS04/17/2023
DOB NOWSignSigned-offMAUCERI SIGN CO., INC04/13/2023
DOB NOWSignSigned-offMAUCERI SIGN CO., INC04/12/2023
DOB NOWGeneral ConstructionSigned-offBEST PRICE RENOVATIONS LL03/27/2023
DOB NOWGeneral ConstructionSigned-offNYCAN BUILDERS LLC03/23/2023
DOB NOWStructuralSigned-offNYCAN BUILDERS LLC03/23/2023
DOB NOWStructuralSigned-offDGC CAPITAL CONTRACTING CORP03/22/2023
DOB NOWStructuralSigned-offDGC CAPITAL CONTRACTING CORP02/22/2023
+ 60 more permits on file
1 project · most recent 12/19/2025
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
12/19/2025Signed-offANTIS MAINTENANCE CORPAir Conditioning Systems
Cooling
Skypeak SDSH096D2 8 tons · Rooftop Unit ×1
1 project · most recent 12/19/2025
FiledStatusContractorScope
12/19/2025Permit IssuedA&H EXPRESS PLBG&HTG CORP17 heads
2 projects · most recent 12/19/2025
Water/Sanitary
FiledStatusContractorScope
12/19/2025———
12/19/2025Permit IssuedA&H EXPRESS PLBG&HTG CORPWater/Sanitary
20 projects · most recent 05/26/2026
General Wiring Lighting
FiledStatusContractorScope
05/26/2026Permit IssuedDAVEN ELECTRIC CORPGeneral Wiring
05/10/2026Permit IssuedRAINBOW ELECTRIC CO., INC—
03/03/2026Permit IssuedALL PURPOSE ELECTRIC CORPGeneral Wiring
10/24/2025Permit IssuedBIG ANT ELECTRIC, INCGeneral Wiring, Lighting
04/02/2024CompleteATLAS-ACON ELEC. SERVICE1 meters
01/16/2024Permit IssuedROBERT CHIMENTI2 meters, 1 new_meters
09/13/2023CompleteATLAS-ACON ELEC. SERVICEGeneral Wiring
08/28/2023CompleteEMPIRE LIC ELECL CONTRSGeneral Wiring
07/13/2023CompleteJAS ELEC'L SERVICES, INCGeneral Wiring
05/18/2023CompleteNEAD ELECTRIC INC.General Wiring
05/08/2023CompleteCONDE ELECTRIC INCGeneral Wiring
04/08/2023CompleteGREEN APPLE ELECL SVCS LLGeneral Wiring
03/08/2023CompleteELPO ELECTRICAL CONTG INCGeneral Wiring
06/16/2022CompleteH. & L. ELECTRIC INCGeneral Wiring
04/07/2022CompleteADCO ELEC'L CORPGeneral Wiring
2 projects · most recent 01/20/2023
Steel
FiledStatusContractorScope
01/20/2023——Steel
05/06/2022Signed-offNYCAN BUILDERS LLCSteel
1 project · most recent 08/19/2026
Suspended Scaffold
FiledStatusContractorScope
08/19/2026Permit IssuedSTRUCTUAL PRESV SYSTEMSuspended Scaffold
1 project · most recent 08/19/2026
FiledStatusContractorScope
08/19/2026Permit IssuedSTRUCTUAL PRESV SYSTEM—
▾Field Inspections (DOB CAP) — 61
DateTypeResultReport
02/04/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/30/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/21/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/17/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/17/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/31/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/13/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/10/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/10/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/30/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/02/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/27/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/12/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/30/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/16/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/28/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/27/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/19/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/04/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/02/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/02/2024Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
12/28/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/28/2023Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
12/15/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/11/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
Latest 25 of 61.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
12/17/2025Maintenance informationNicholas Tuccienergy_progress
12/17/2025Energy Code Compliance InspectionsNicholas Tucciprogress
12/17/2025Shutoff dampersNicholas Tuccienergy_progress
12/17/2025HVAC-R and service water heating system controlsNicholas Tuccienergy_progress
12/17/2025HVAC-R and service water heating equipmentNicholas Tuccienergy_progress
12/17/2025HVAC-R and service water piping design and insulationNicholas Tuccienergy_progress
12/17/2025Fire-Resistant Penetrations and JointsNicholas Tuccispecial
11/14/2025FinalNicholas Tucciprogress
11/14/2025Mechanical SystemsNicholas Tuccispecial
11/14/2025Sprinkler SystemsNicholas Tuccispecial
10/27/2025Post-installed AnchorsGUNJAN KHANDWALAspecial
10/27/2025Fire-Resistant Penetrations and JointsGUNJAN KHANDWALAspecial
10/07/2025FinalGUNJAN KHANDWALAprogress
10/07/2025Sprinkler SystemsGUNJAN KHANDWALAspecial
10/03/2025FinalGUNJAN KHANDWALAprogress
10/03/2025Mechanical SystemsGUNJAN KHANDWALAspecial
08/19/2025Post-installed AnchorsChester Kowalskispecial
08/19/2025Concrete - Cast-In-PlaceChester Kowalskispecial
08/19/2025FinalChester Kowalskiprogress
11/13/2024Fire-Resistant Penetrations and JointsYoung Suhspecial
08/27/2024Post-installed AnchorsJoseph Smerinaspecial
08/27/2024Structural Stability – Alterations of existing buildingsREZA KHAMCYspecial
08/27/2024Structural Steel - High Strength BoltingJUAN GOMEZspecial
08/27/2024Structural Steel - WeldingJUAN GOMEZspecial
08/27/2024Mechanical SystemsJoseph Smerinaspecial
Latest 25 of 150.
▾Documents — 2,641 on file (BIS + DOB NOW)
▸Plans & Drawings97
▸DOB NOWPlans/Sketch83
09/03/2026M00519163-I1Request digital key ↗
09/03/2026M00519163-P1Request digital key ↗
09/03/2026M00519250-I1Request digital key ↗
Showing 3 of 83 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems5
09/05/2026M00194511-I1Request digital key ↗
09/05/2026M00195607-I1Request digital key ↗
09/05/2026M00258438-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
09/05/2026M00258445-I1Request digital key ↗
09/04/2026M00342680-I1Request digital key ↗
Showing 2 of 3 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler2
09/05/2026M00258452-I1Request digital key ↗
09/04/2026M00342698-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Standpipe1
09/05/2026M00271772-I1Request digital key ↗
▸Applications & Permits404
▸BISPLAN / WORK APPROVAL APPLICATION230
11/20/2025121686185Open ↗
07/11/2025121475037Open ↗
07/01/2025121686185Open ↗
Showing 3 of 230 on file for this type
▸BISWORK PERMIT APPLICATION169
10/28/2020140965347Open ↗
06/10/2020123912891Open ↗
01/17/2020123752947Open ↗
Showing 3 of 169 on file for this type
▸BISPLACE OF ASSEMBLY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
08/29/2022121872198Open ↗
▸Zoning, Tax Lot & Property Records4
▸BISZONING RESOLUTION DETERMINATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISZONING EXHIBIT I: CERTIFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications754
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION302
05/15/2020123912891Open ↗
05/15/2020123912891Open ↗
01/22/2020123891672Open ↗
Showing 3 of 302 on file for this type
▸DOB NOWProgress Inspector Seal & Signature116
09/30/2026M00798133-P1Open ↗
09/30/2026M00798133-P1Open ↗
09/23/2026M01319256-I1Open ↗
Showing 3 of 116 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature96
09/05/2026M00194511-I1Open ↗
09/05/2026M00195607-I1Open ↗
09/05/2026M00258445-P1Open ↗
Showing 3 of 96 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST78
08/29/2022121872198Open ↗
05/15/2020123912891Open ↗
11/26/2019123793715Open ↗
Showing 3 of 78 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature72
09/30/2026M00887586-I1Open ↗
09/30/2026M00887586-I1Open ↗
09/30/2026M00887586-I1Open ↗
Showing 3 of 72 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM53
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 53 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT35
10/14/2020140965347Open ↗
05/15/2020123912891Open ↗
11/26/2019123793715Open ↗
Showing 3 of 35 on file for this type
▸BISPC FULL REPORT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Trade Schedules & Equipment269
▸BISSELF-CERT PLUMBING NOTICE83
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 83 on file for this type
▸BISSCHEDULE B - PLUMBING56
11/03/2021123752947Open ↗
Showing 1 of 56 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT35
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 35 on file for this type
▸BISEQUIPMENT USE PERMITS34
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 34 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE22
12/31/2019123752947Open ↗
12/31/2019123752947Open ↗
Showing 2 of 22 on file for this type
▸BISSPRINKLER INSP REPORT : FP-8512
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMITEQUIPMENT USE PERMITS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Environmental & Asbestos230
▸DOB NOWDEP ACP-5: Asbestos Assessment Report89
09/05/2026M00194511-I1Open ↗
09/05/2026M00195607-I1Open ↗
09/05/2026M00258445-P1Open ↗
Showing 3 of 89 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)73
10/14/2020140965347Open ↗
05/15/2020123912891Open ↗
11/26/2019123793715Open ↗
Showing 3 of 73 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'52
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 52 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORM PRIOR TO SIGN OFF: TRU1512MN191
03/09/2021123688535Open ↗
▸Energy Compliance131
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS76
05/15/2020123912891Open ↗
05/15/2020123912891Open ↗
01/22/2020123891672Open ↗
Showing 3 of 76 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS26
10/01/2021120973679Open ↗
09/22/2021120973679Open ↗
06/10/2021120973679Open ↗
Showing 3 of 26 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY10
08/15/2022121872198Open ↗
10/01/2021120973679Open ↗
09/22/2021120973679Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWEN2: As Built Energy Analysis9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISTR8: Energy Code Progress Inspections6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
10/28/2020140965347Open ↗
▸BISLIGHTING CONTROLS1
10/28/2020140965347Open ↗
▸Inspections & Test Reports27
▸BISTECHNICAL REPORT: RESPONSIBILITY21
08/15/2022121872198Open ↗
08/15/2022121872198Open ↗
10/01/2021120973679Open ↗
Showing 3 of 21 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: PILE DRIVING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
10/28/2020140965347Open ↗
▸Approvals, Objections & Sign-offs229
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST125
01/25/2023120767152Open ↗
08/30/2022121872198Open ↗
03/03/2022120738390Open ↗
Showing 3 of 125 on file for this type
▸BISADMINISTRATIVE OBJECTIONS68
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 68 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE15
11/20/2025121686185Open ↗
05/11/2023121686185Open ↗
Showing 2 of 15 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFINAL2
08/17/2022121872198Open ↗
10/28/2020140965347Open ↗
▸Cost, Insurance & Ownership236
▸BISCOST AFFIDAVIT236
02/17/2022123752947Open ↗
10/01/2021120973679Open ↗
07/07/2021120513603Open ↗
Showing 3 of 236 on file for this type
▸Filing & Intake Forms223
▸BISEFILING COVER SHEET122
05/15/2020123912891Open ↗
11/26/2019123793715Open ↗
11/13/2019123694788Open ↗
Showing 3 of 122 on file for this type
▸BISADDITIONAL INFORMATION57
12/09/2025121686185Open ↗
07/14/2025121686185Open ↗
05/30/2023121686185Open ↗
Showing 3 of 57 on file for this type
▸BISBOROUGH INTAKE FORM38
05/04/2020123738704Open ↗
03/23/2020121686185Open ↗
01/22/2020123891672Open ↗
Showing 3 of 38 on file for this type
▸BISeFiling Job Application Cover Sheet6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸Other Documents20
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION16
06/14/2024122117967Open ↗
Showing 1 of 16 on file for this type
▸BISPLOT DIAGRAM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWIRA Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type