| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/23/2025 | $947K | — | — → — | $541/sf building |
| 12/20/2023 | $570K | — | Private party → REAL HORIZON INC. | $325/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ISEED CONSTRUCTION INC | 2 | 03/02/2025 |
| MSM ENGINEERING SERVICES, PLLC | 2 | 08/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| MODERN BUILDING CONSULTANT | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JZ CONSTRUCTION GROUP INC | General Contractor | 1 | 07/08/2026 |
| KALE CONSTRUCTION INC | General Contractor | 1 | 04/08/2026 |
| SJ CONSTR DESIGN INC | General Contractor | 1 | 04/09/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ISEED CONSTRUCTION INC | 8336 | 2 | 03/02/2025 |
| MSM ENGINEERING SERVICES, | 8449 | 2 | 08/12/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | SJ CONSTR DESIGN INC | 03/24/2026 |
| DOB NOW | Plumbing | Permit Issued | AMERICAN STANDARD P&H CORORP. | 03/31/2025 |
| DOB NOW | General Construction | Permit Issued | KALE CONSTRUCTION INC | 03/21/2025 |
| DOB NOW | General Construction | Signed-off | JZ CONSTRUCTION GROUP INC | 02/02/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/02/2025 | Permit Issued | AMERICAN STANDARD P&H COR | Gas, Water/Sanitary |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/28/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/17/2025 | HVAC-R and service water piping design and insulation | YIPENG LUAN | energy_progress |
| 02/17/2025 | Energy Code Compliance Inspections | YIPENG LUAN | progress |
| 02/17/2025 | Fire-Resistant Penetrations and Joints | YIPENG LUAN | special |
| 02/17/2025 | Tenant Protection Plan Compliance | YIPENG LUAN | special |
| 08/13/2024 | Energy Code Compliance Inspections | MOHAMED MAHMOUD | progress |
| 08/13/2024 | Fire-Resistant Penetrations and Joints | MOHAMED MAHMOUD | special |
| 08/13/2024 | Fire-Resistance Rated Construction | MOHAMED MAHMOUD | progress |
| 08/13/2024 | Interior lighting power | MOHAMED MAHMOUD | energy_progress |
| 08/07/2024 | Fire-Resistant Penetrations and Joints | MOHAMED MAHMOUD | special |
| 08/07/2024 | Interior lighting power | MOHAMED MAHMOUD | energy_progress |
| 08/07/2024 | Fire-Resistance Rated Construction | MOHAMED MAHMOUD | progress |
| 08/07/2024 | Energy Code Compliance Inspections | MOHAMED MAHMOUD | progress |